Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
|
Contract No. |
Site Activities (February
2026) |
|
ND/2019/01 |
(a)
Drainage
works, slope works, road works and UU works in Portion 1a (b)
Site
formation, watermain works, ELS construction, drainage works, sewage works,
backfilling and road works in Portion 1b
and 1c (c)
Site
formation, construction of subway, drainage works, road works and slope works in
Portion 2 (d)
Excavation, drainage works
and UU works in Portion 3 (e)
Road
works, UU works and
site formation in
Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road works, district cooling
system and UU works in
Portion 6a and 9c (g)
Storage
area in Portion 6b (h)
Excavation,
drainage works, road works (UU) and smart lighting in Portion 7 (i)
RC structure works,
drainage works, backfilling, planting, metal works, slope works and E&M
works in Portion 8a (j)
TBM pipe jacking, grouting,
watermain construction, ELS construction and RC structure works in Portion 8b (k)
Excavation, road works,
drainage works, watermain works, slope works and smart lighting in Portion 9b (l)
Watermain works and road
works in Portion 11b (m)
Stockpile of soil
in Portion 13 |
|
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
|
ND/2019/03 |
All
construction activities with significant environmental impact have been
substantially completed in
April 2024 and all outstanding works with defect rectification have also been
completed on 28 March 2025. |
|
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork (f)
Rebar Fixing (g)
Concreting (h)
MIC (i)
Noise barrier installation (j)
Asphalt paving |
|
ND/2019/05 |
(a)
South
Team -
BBI
Toilet ¡V Pre-handover inspection carried out on 20 January 2026.
Rectification of defects was on-going. -
BBI
Toilet ¡V Dwarf Wall construction will resume after completion of BBI Toilet. -
BBI
Covered Walkway ¡V Installation of columns from Bay 1 to 6 in progress. -
Lift LT01
¡V Lift is scheduled to open on 28 Feb 2026. -
Road D400
¡V Road and drain was in progress. -
Road D300
¡V Installation of road lights was carried out and road formation was in
progress. -
FS24 ¡V
U-channel construction at slope toe is in progress. 110m out of 130m
completed. -
ADS21 PC2
¡V Backfilling works completed. Reinstatement works was in progress. -
DS11 ¡V
Backfilling works completed. Reinstatement works was in progress. -
D2-02 ¡V
Swabbing was carried out and water meter box was completed. -
E3-01 ¡V
Backfilling up to +15.4 mPD for slope reinstatement. -
E4
Retaining Wall ¡V Pavement and road marking completed. -
E4 Ramp
Utrough Bay 17~21 ¡V Pavement completed. -
FW56 Bay
22~25 ¡V Backfilling up to subbase level. Pavement works will commence on 23
Feb 2026. -
Noise
barrier NB69 and NB68 A.
NB68 ¡V
Bay3 and 4 were backfilled with sheetpiles extracted. Excavation for drainage
works was in progress. -
Noise
barrier NB 108 A.
Construction
of Bay 9 ~16 Footing (7 nr.) were completed. Backfilling was in progress. B.
Construction
of Bay 6 capping beam was completed. Construction of Bay 3 and 7 capping beam
was in progress. -
Noise
barrier NB 66 A.
Piling
works commenced on 3 January 2026. 10 out of 30 piles were grouted. Drilling
works was in progress. -
Noise Barrier NB29 Trough
Bay 1-23 A.
Footing
100% completed. B.
Wall
(exclude parapet) is 100% completed C.
Backfilling
work to formation layer 100% completed. D.
Parapet
construction in progress, 100% completed E.
Drainage
work in progress 100% completed F.
Bitumen
laying work 95% completed -
Noise barrier NB 30 A.
Drainage
work & backfilling work completed. B.
Parapet
construction in progress, 90% completed C.
Drainage
work in progress 80% completed D.
Bitumen
laying work 80% completed -
Noise barrier NB 77 E.
NB1
Footing completed, stem wall in progress F.
NB3 ELS
completed, socket H pile in progress -
Sign Gantry A.
20 out of
20 columns fabrication (100%) were completed. 19 Columns were installed. B.
11 out of
11 mid chords fabrication (100%) were completed. FADS21 mid chord was
completed. C.
10 out of
11 sign gantries (3 on viaducts, 7 at grade) were installed. -
Fabrication
of Noise Barrier ¡V 75% of
overall noise barrier columns were completed. Fabrication of NB68 and NB69
noise barrier columns was completed. (b)
North
Team -
C1-03,
C3-02, C4-03 & D1-02 catch pit & manhole construction completed. -
C1-03,
C3-02, C4-03 & D1-02 outfall construction in progress -
C3-03B,
C1-03, C2-01 & D1-01 watermain works in progress. -
Reinstatement
work at C3-04B footpath in progress. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 100%. Road
commissioning on 19 Dec 2025 -
JCR & Tong Hang
Village J/O improvement works (FS 25): slope works 100 % completed. -
Road commissioning on 22
Jan 2026 -
JCR near F63 ¡Vslope
feature construction works completed. Street furniture in progress. -
Pavilion construction in
progress (c)
Bridges
and Structures -
Parapet at C3-01
completed. All profile barrier on the bridge completed. -
Water test of fire hydrant
in progress. -
Reinstate of lifting tower
NF83A in progress. The E&M test completed. -
Installation of
stainless-steel cover plate for MJ in progress, 50/54 completed. -
Installation hopper for MJ
in progress, 6/9 completed. -
All Water proofing at
bridge deck completed. -
Asphalt pavement of all
bridges completed. -
Noise barrier NB27a at
bridge C3 completed. All NB completed. -
Installation of L3 railing
at bridge C3 completed. All railing completed. -
Step iron at deck void in
progress -
Water proofing for PT
anchorage In Progress. -
All external tendon
completed -
Step iron at deck void in
progress -
Maintenance scaffold
storage at deck void in progress |
|
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
|
ND/2019/07 |
All construction
activities with significant environmental impact have been substantially
completed in October 2025. |