Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (February 2026)

ND/2019/01

(a)          Drainage works, slope works, road works and UU works in Portion 1a

(b)         Site formation, watermain works, ELS construction, drainage works, sewage works, backfilling and road works in Portion 1b and 1c

(c)          Site formation, construction of subway, drainage works, road works and slope works in Portion 2

(d)         Excavation, drainage works and UU works in Portion 3

(e)          Road works, UU works and site formation in Portion 5

(f)          Backfilling, drainage works, watermain works, slope works, road works, district cooling system and UU works in Portion 6a and 9c

(g)         Storage area in Portion 6b

(h)         Excavation, drainage works, road works (UU) and smart lighting in Portion 7

(i)           RC structure works, drainage works, backfilling, planting, metal works, slope works and E&M works in Portion 8a

(j)           TBM pipe jacking, grouting, watermain construction, ELS construction and RC structure works in Portion 8b

(k)         Excavation, road works, drainage works, watermain works, slope works and smart lighting in Portion 9b

(l)           Watermain works and road works in Portion 11b

(m)       Stockpile of soil in Portion 13

ND/2019/02

(a)           Backfilling

(b)           Excavation

(c)            Concreting

(d)           Cut and Fill of Slope

(e)            Sheet Piling

(f)            Pipe Jacking

(g)           Pipe laying and bedding

(h)           Grouting

ND/2019/03

All construction activities with significant environmental impact have been substantially completed in April 2024 and all outstanding works with defect rectification have also been completed on 28 March 2025.

ND/2019/04

(a)           Back Filling

(b)           Excavation

(c)           Grouting

(d)           Road works

(e)           Formwork

(f)            Rebar Fixing

(g)           Concreting

(h)           MIC

(i)            Noise barrier installation

(j)            Asphalt paving

ND/2019/05

(a)          South Team

-          BBI Toilet ¡V Pre-handover inspection carried out on 20 January 2026. Rectification of defects was on-going.

-          BBI Toilet ¡V Dwarf Wall construction will resume after completion of BBI Toilet.

-          BBI Covered Walkway ¡V Installation of columns from Bay 1 to 6 in progress.

-          Lift LT01 ¡V Lift is scheduled to open on 28 Feb 2026.

-          Road D400 ¡V Road and drain was in progress.

-          Road D300 ¡V Installation of road lights was carried out and road formation was in progress.

-          FS24 ¡V U-channel construction at slope toe is in progress. 110m out of 130m completed.

-          ADS21 PC2 ¡V Backfilling works completed. Reinstatement works was in progress.

-          DS11 ¡V Backfilling works completed. Reinstatement works was in progress.

-          D2-02 ¡V Swabbing was carried out and water meter box was completed.

-          E3-01 ¡V Backfilling up to +15.4 mPD for slope reinstatement.

-          E4 Retaining Wall ¡V Pavement and road marking completed.

-          E4 Ramp Utrough Bay 17~21 ¡V Pavement completed.

-          FW56 Bay 22~25 ¡V Backfilling up to subbase level. Pavement works will commence on 23 Feb 2026.

-          Noise barrier NB69 and NB68

A.         NB68 ¡V Bay3 and 4 were backfilled with sheetpiles extracted. Excavation for drainage works was in progress.

-          Noise barrier NB 108

A.         Construction of Bay 9 ~16 Footing (7 nr.) were completed. Backfilling was in progress.

B.          Construction of Bay 6 capping beam was completed. Construction of Bay 3 and 7 capping beam was in progress.

-          Noise barrier NB 66

A.         Piling works commenced on 3 January 2026. 10 out of 30 piles were grouted. Drilling works was in progress.

-          Noise Barrier NB29 Trough Bay 1-23

A.         Footing 100% completed.

B.          Wall (exclude parapet) is 100% completed

C.          Backfilling work to formation layer 100% completed.

D.         Parapet construction in progress, 100% completed

E.          Drainage work in progress 100% completed

F.          Bitumen laying work 95% completed

-          Noise barrier NB 30

A.         Drainage work & backfilling work completed.

B.          Parapet construction in progress, 90% completed

C.          Drainage work in progress 80% completed

D.         Bitumen laying work 80% completed

-          Noise barrier NB 77

E.          NB1 Footing completed, stem wall in progress

F.          NB3 ELS completed, socket H pile in progress

-          Sign Gantry

A.         20 out of 20 columns fabrication (100%) were completed. 19 Columns were installed.

B.          11 out of 11 mid chords fabrication (100%) were completed. FADS21 mid chord was completed.

C.          10 out of 11 sign gantries (3 on viaducts, 7 at grade) were installed.

-            Fabrication of Noise Barrier ¡V 75% of overall noise barrier columns were completed. Fabrication of NB68 and NB69 noise barrier columns was completed.

(b)         North Team

-          C1-03, C3-02, C4-03 & D1-02 catch pit & manhole construction completed.

-          C1-03, C3-02, C4-03 & D1-02 outfall construction in progress

-          C3-03B, C1-03, C2-01 & D1-01 watermain works in progress.

-          Reinstatement work at C3-04B footpath in progress.

-          JCR: Construction of new central median & ducting works for traffic signal & road light were completed of 100%. Road commissioning on 19 Dec 2025

-          JCR & Tong Hang Village J/O improvement works (FS 25): slope works 100 % completed.

-          Road commissioning on 22 Jan 2026

-          JCR near F63 ¡Vslope feature construction works completed. Street furniture in progress.

-          Pavilion construction in progress

(c)          Bridges and Structures

-          Parapet at C3-01 completed. All profile barrier on the bridge completed.

-          Water test of fire hydrant in progress.

-          Reinstate of lifting tower NF83A in progress. The E&M test completed.

-          Installation of stainless-steel cover plate for MJ in progress, 50/54 completed.

-          Installation hopper for MJ in progress, 6/9 completed.

-          All Water proofing at bridge deck completed.

-          Asphalt pavement of all bridges completed.

-          Noise barrier NB27a at bridge C3 completed. All NB completed.

-          Installation of L3 railing at bridge C3 completed. All railing completed.

-          Step iron at deck void in progress

-          Water proofing for PT anchorage In Progress.

-          All external tendon completed

-          Step iron at deck void in progress

-          Maintenance scaffold storage at deck void in progress

ND/2019/06

The construction phase was completed and handed over to AFCD since 4 April 2022.

ND/2019/07

All construction activities with significant environmental impact have been substantially completed in October 2025.