Table II   Summary Table for EM&A Activities in the Reporting Month

EM&A Activities

Monitoring Station (s)

Works Contracts

ND/2019/01

ND/2019/02

ND/2019/03

ND/2019/04

ND/2019/05

ND/2019/06

ND/2019/07

 

1-hr Total Suspended Particulates (TSP) Monitoring

FLN-DMS1

N/A

N/A

N/A

4, 10, 16, 20 and 26 Mar 26

N/A

N/A

N/A

 

FLN-DMS3

N/A

4, 10, 16, 20 and 26 Mar 26

 

FLN-DMS5

3, 9, 13, 19, 25 and 31 Mar 26

N/A

 

KTN-DMS4(B)

3, 9, 13, 19, 25 and 31 Mar 26

N/A

 

24-hr TSP Monitoring

FLN-DMS1

N/A

N/A

N/A

3, 9, 13, 19, 25 and 31 Mar 26

N/A

N/A

N/A

 

FLN-DMS3

N/A

3, 9, 13, 19, 25 and 31 Mar 26

 

FLN-DMS5A

3, 9, 13, 19, 25 and 31 Mar 26

N/A

 

KTN-DMS4(B)

3, 9, 13, 19, 25 and 31 Mar 26

N/A

 

Noise Monitoring

CP-FLN-NMS1

N/A

4, 10, 16 and 26 Mar 26

N/A

N/A

 

CP-FLN-NMS2

N/A

4, 10, 16 and 26 Mar 26

N/A

 

 

CP-KTN-NMS2

3, 9, 19, 25 and 31 Mar 26

N/A

N/A

 

 

CP-KTN-NMS3

 

CP-KTN-NMS5

 

CP-KTN-NMS6

N/A

3, 9, 19, 25 and 31 Mar 26

 

Ecological Survey

Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley

N/A

5, 11, 17, 23 and 30 Mar 26

N/A**

2, 9, 20, 24 and 31 Mar 26

N/A

N/A

N/A

 

Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream

N/A*

N/A*

N/A*

N/A*

N/A*

N/A*

N/A*

 

Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution

3 and 6 Mar 26

3 and 6 Mar 26

N/A

3 Mar 26

3 Mar 26

N/A*

N/A*

 

Egretry Monitoring

N/A

N/A

N/A

N/A

N/A

N/A

N/A

 

24-hr RSP (Ambient Arsenic) Monitoring for Land Contamination

3, 9, 13, 19, 25 and 31 Mar 26

N/A

N/A

N/A

N/A

N/A

N/A

 

Water Quality Monitoring#

N/A

N/A

N/A

N/A

N/A

N/A

N/A

 

Landfill Gas Monitoring

6 Mar 26

N/A

N/A

N/A

N/A

N/A

N/A

 

Built Heritage Monitoring

N/A

N/A

N/A

N/A

N/A

N/A

N/A

 

Environmental Site Inspection

3, 10, 17, 24 and 30 Mar 26

4, 10, 18, 24 and 30 Mar 26

NIL

5, 12, 16 and 26 Mar 26

5, 12, 17 and 26 Mar 26

NIL

NIL

 

 




 

 

 

Remarks:  

N/A – No relevant monitoring is required according to the updated EM&A Manual

N/A* – No relevant monitoring is required according to the Baseline Ecological Monitoring Plan (Table 3.1)

[1] Since the distance between monitoring station CP-KTN-NMS2 and site boundary of ND/2019/03 under EP-468/2013/A exceeds 300m, the monitoring station is not applicable to ND/2019/03

[2] Since the distance between monitoring station CP-KTN-NMS3 and site boundary of ND/2019/03 under EP-468/2013/A exceeds 300m, the monitoring station is not applicable to ND/2019/03

[3] Since the distance between monitoring station CP-KTN-NMS1 and site boundary of ND/2019/02 under EP-469/2013 exceeds 300m, the monitoring station is not applicable to ND/2019/02

[4] Since the distance between monitoring station FLN-DMS1 and site boundary of ND/2019/05 under EP-473/2013/A exceeds500m, the monitoring station is not applicable to ND/2019/05

[5] Since the distance between monitoring station FLN-DMS3 and site boundary of ND/2019/03 and ND/2019/04 under EP-473/2013/A exceeds 500m, the monitoring station is not applicable to ND/2019/03 and ND/2019/04

[6] Since the distance between monitoring station FLN-DMS5 and site boundary of ND/2019/05 under EP-473/2013/A exceeds 500m, the monitoring station is not applicable to ND/2019/05

[7] Since the distance between monitoring station CP-FLN-NMS2 and site boundary of ND/2019/03 and ND/2019/04 under EP-473/2013/A exceeds 300m, the monitoring station is not applicable to ND/2019/03 and ND/2019/04

[8] Since the distance between monitoring station CP-FLN-NMS1 and site boundary of ND/2019/03 under EP-473/2013/A exceeds 300m, the monitoring station is not applicable to ND/2019/03

N/A** – According to the recommendation from AFCD, Avifauna monitoring in Long Valley (i.e., T5) during the construction period and its results reporting in the Monthly EM&A Report will be continued until the completion of works within 200m of Long Valley.

# - River Indus and near Siu Hang San Tsuen Stream: Temporary suspension of all impact water quality monitoring start from 15 December 2025, until the commencement of the temporary works removal to commence in June 2026 or any other activity that may impact the river (whichever is earlier). River Beas: All potential sources of water quality impact from the above works in River Beas have been eliminated in December 2025. Additional water quality monitoring at River Beas has been terminated starting from 15 December 2025.