2               PROJECT INFORMATION

Background

2.1         The Kwu Tung North (KTN) and Fanling North (FLN) New Development Areas (NDAs) are one of the important sources of land and housing supply in the medium and long term. The development of the KTN and FLN NDAs will be implemented in phase for full completion by 2031. The Phase 1 of the NDAs development, comprising the Advance Works and First Stage Works, is targeted to be implemented from the second half of 2019 progressively. The Advance and First Stage Works would include site formation, engineering infrastructure works (including roads, drainage, sewerage, waterworks, landscaping works, pumping stations, and fresh water and flushing water service reservoirs), soil remediation, reprovisioning of North District Temporary Wholesale Market, development of a nature park at Long Valley and implementation of environmental mitigation measures.

2.2         The scope of works under the Advance and First Stage Works comprises the following:

a)                   The Advance Works (PWP item No. 7747CL-2) consist of:

i)         site formation of land (including soil remediation) in KTN and FLN NDAs for housing, community facilities and engineering infrastructure;

ii)       construction of roads including the eastern section of Fanling Bypass (FLBP(E)) connecting the FLN NDA to Fanling Highway and other roads with footpaths and cycle tracks, and associated junction/ road improvements;

iii)     engineering infrastructure works including drainage. Sewerage (including two sewage pumping stations), waterworks (including a fresh water service reservoir and a flushing water service reservoir in the KTN NDA), landscape works and slopeworks;

iv)     part expansion and upgrading of Shek Wu Hui Sewage Treatment Works (SWHSTW);

v)        reprovisioning works; and

vi)     implementation of environmental mitigation measures and environmental monitoring and audit (EM&A) programme for the works mentioned in (i) to (v) above.

b)                  The First Stage Works (PWP item No. 7759CL) consist of:

i)         development of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung Yue River for connection between these two facilities;

ii)       reprovisioning of two egretry sites in the FLN NDA and enhancement works to an existing egretry site in the KTN NDA;

iii)     site formation of land for a village resite area and a district police station in the KTN NDA;

iv)     engineering infrastructure works including roads, drainage, sewerage, waterbirds, and landscape works; and 

v)        implementation of environmental mitigation measures and environmental monitoring and audit (EM&A) programme for the works mentioned in (i) to (iv) above.


 

2.3         The Project which covers KTN and FLN NDAs is a designated project (DP) under Schedule 3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October 2013, the EIA Report (AEIAR-175/2013) for the Project was approved by the Director of Environmental Protection pursuant to the EIA Ordinance. The relevant EPs under the Project and the respective Work Contracts are summarised in Tables 2.1a and 2.1.b.

 

Table 2.1a         Summary of EPs under the Project and the Respective Work Contracts

EP No.

Designated Project

C1

C2

C3

C5A

C5B

C6

C7

EP-466/2013/A

Castle Peak Road Diversion

ü

¡@

EP-467/2013/A

Kwu Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange Improvement

ü

¡@

EP-468/2013/A

Kwu Tung North New Development Area Road D1 to D5

ü

ü

¡@

EP-469/2013

Sewage Pumping Stations in Kwu Tung North New Development Area

ü

¡@

EP-470/2013/A

Utilization of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment Works

ü

¡@

EP-473/2013/A

Fanling Bypass Eastern Section

ü

ü

ü

¡@

EP-475/2013/A

Reprovision of temporary Wholesale Market in Fanling North New Development Area

ü

¡@

EP-546/2017

Fanling North Temporary Sewage Pumping Station

ü

¡@

                Notes: C1: ND/2019/01     C2: ND/2019/02  C3: ND/2019/03  C5A: ND/2019/04

                     C5B: ND/2019/05         C6: ND/2019/06  C7: ND/2019/07

Table 2.1b Summary of Scope of Works under concerned EP

Environmental Permit (EP) No.

Work Contract(s)

Scope of Works under concerned EP(s)

Site Layout Plan under concerned EP(s)

EP-466/2013/A(Part)

C1

Realign Castle Peak Road and join with the Pak Shek Au Interchange at the western end

Figure 12

EP-467/2013/A(Part)

C1

Construction of new primary distributor road (P1) within Kwu Tung North New Development Area

Figure 13

EP-468/2013/A(Part)

C1

Construction of new primary distributor roads (D1, D3, D4 and part of D5) within Kwu Tung North New Development Area

Figure 14

C3

Development of a nature park at Long Valley and ecological mitigation and enhancement works for the nature park (Condition 2.9)

Figure 15

EP-469/2013(Part)

C2

Construction of one sewage pumping station in Kwu Tung North with installed capacity of more than 2,000 m3 per day

Figure 16

EP-470/2013/A(Part)

C1

Construction of service reservoir and watermain for the reuse of treated sewage effluent for reuse in Kwu Tung North Development Areas

Figure 17

EP-473/2013/A(Part)

C3

Establishment of alternative egretry sites and enhance the existing egretry site at Ho Sheung Heung and/or its vicinity (Condition 2.7)

Figure 18

EP-473/2013/A(Part)

C5A

Construction of new district distributor inside FLN NDA, which provides a linkage between the Man Kam To Road and the proposed Fanling Bypass Eastern Section

Figure 19

EP-473/2013/A(Part)

C5B

Figure 20

EP-475/2013/A

C6

The re-provisioned wholesale market will have approximately 1,000 market stalls within a site area of around 1.3 ha

Figure21

EP-546/2017

C5A

Construct and operate a temporary sewage pumping station in Fanling North with installed capacity (average dry weather flow) of about 3,600m3/day

Figure 22

Remark: The EP(s) not related to the Project of the First Phase of the Kwu Tung North (KTN) and Fanling North (FLN) New Development Area (NDA) Development Areas are not included in the Table.

2.4         The site boundary of the Project and all Works Contracts are shown in Drawing No. 1.

2.5         The required submissions and submission status under Environmental Permits are shown in Appendix U.

2.6         The site layout plans under concerned Environmental Permits are shown in Figures 12 - 22.

Project Organization

2.7         Different parties with different levels of involvement in the Project organisation include:

Ÿ    Project Proponent ¡V Civil Engineering and Development Department (CEDD)

Ÿ    Supervisor / Supervisor's Representative ¡V AECOM Asia Co. Ltd.

Ÿ    Environmental Team (ET) ¡V Wellab Limited

Ÿ    Independent Environmental Checker (IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)

2.8         The names and contact numbers of key personnel are summarised in Table 2.2.


Table 2.2   Key Contacts of the Project

Party

Role

Contact Person

Phone No.

Fax No.

Civil Engineering and Development Department, HKSAR (CEDD)

Project Proponent

Mr. Ryan Chau

3797 5387

3547 1658

Supervisor / Supervisor's Representative

(AECOM Asia Co. Ltd.)

Chief Resident Engineer

Mr. Alan Lee

6398 5982

2680 9515

Senior Resident Engineer

Mr. King-man Chan

9651 2635

2680 9515

Environmental Team

(Wellab Limited)

Environmental Team Leader

Dr. Priscilla Choy

2898 7388

2898 7076

Independent Environmental Checker (MottMac)

Independent Environmental Checker

Mr. Thomas Chan

2828 5967

2827 1823

Contract No. ND/2019/01

Contractor (Build King ¡V Richwell Engineering Joint Venture)

Site Agent

Mr. Ivan Leung

9640 8340

--

Environmental Officer

Mr. Edward Tam

9287 8270

Contract No. ND/2019/02

Contractor (Chun Wo ¡V Kwan Lee Joint Venture.)

Site Agent

Mr. Andy Chan

3485 9780

--

Environmental Officer

Ms. Barbara Yiu

9758 2034

Contract No. ND/2019/03

Contractor (Sang Hing Kuly Joint Venture)

Site Agent

Mr. Tang Wing Kai

9300 7037

--

Environmental Officer

Mr. Ken Cheung

9803 5297

Contract No. ND/2019/04

Contractor (Daewoo ¡V Chun Wo ¡V Kwan Lee Joint Venture)

Site Agent

Mr. Eric Wu

9786 8630

--

Environmental Officer

Mr. Sam Lam

6178 3179

Contract No. ND/2019/05

Contractor (CRCC ¡V Paul Y. Joint Venture)

Site Agent

Mr. Darvin Lo

9467 5891

--

Environmental Manager

Mr. Pan Fong

9436 9435

Environmental Officer

Ms. Connie Yuen

6316 6931

Contract No. ND/2019/06

Contractor (New Concepts Engineering Development Ltd.)

Project Manager

Mr. Joe Cheng

9861 0060

--

Environmental Officer

Mr. Alex Choy

6360 3236

Contract No. ND/2019/07

Contractor (China Road and Bridge Corporation)

Site Agent

Mr. Mac Chow

9169 9567

--

Environmental Manager

Mr. K. M. Lui

5113 8223

 


 

Summary of Construction Works Undertaken During Reporting Month

2.9         The major site activities undertaken in the reporting month are shown in Table 2.3.

Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (March 2026)

ND/2019/01

(a)          Drainage works, road works and UU works in Portion 1a

(b)         Site formation, watermain works, ELS construction, drainage works, sewage works, backfilling and road works in Portion 1b and 1c

(c)          Construction of subway, drainage works, road works and slope works in Portion 2

(d)         Excavation, slope works, drainage works and UU works in Portion 3

(e)          Road works and UU works in Portion 5

(f)          Backfilling, drainage works, road works and UU works in Portion 6a and 9c

(g)         Storage area in Portion 6b

(h)         Excavation, drainage works, road works (UU) and smart lighting in Portion 7

(i)           RC structure works, drainage works, backfilling, metal works, slope works and E&M works in Portion 8a

(j)           TBM pipe jacking, grouting, watermain construction, ELS construction and RC structure works in Portion 8b

(k)         Excavation, road works, drainage works, watermain works, slope works and smart lighting in Portion 9b

(l)           Road works in Portion 11b

(m)       Stockpile of soil in Portion 13

ND/2019/02

(a)           Backfilling

(b)           Excavation

(c)            Concreting

(d)           Cut and Fill of Slope

(e)            Sheet Piling

(f)            Pipe Jacking

(g)           Pipe laying and bedding

(h)           Grouting

ND/2019/03

All construction activities with significant environmental impact have been substantially completed in April 2024 and all outstanding works with defect rectification have also been completed on 28 March 2025.

ND/2019/04

(a)           Back Filling

(b)           Excavation

(c)           Grouting

(d)           Road works

(e)           Formwork

(f)            Rebar Fixing

(g)           Concreting

(h)           MIC

(i)            Noise barrier installation

(j)            Asphalt paving

ND/2019/05

(a)          South Team

-          BBI Toilet ¡V Pre-handover inspection carried out on 20 January 2026. Rectification of defects was on-going.

-          BBI Toilet ¡V Dwarf Wall construction will resume after completion of BBI Toilet.

-          BBI Covered Walkway ¡V Construction of bus layby in progress

-          Lift LT01 ¡V Lift was opened to public on 28 Feb 2026.

-          Road D400 ¡V Road and drain was in progress.

-          Road D300 ¡V Road formation including the cycle parking was in progress.

-          FS24 ¡V U-channel construction at slope toe is in progress. 120m out of 130m completed.

-          ADS21 PC2 ¡V Backfilling works completed. Reinstatement works was in progress.

-          DS11 ¡V Reinstatement works was in progress.

-          D2-02 ¡V Construction of wash-out pit was in progress.

-          E3-01 ¡V Backfilling up to +16.7 mPD for slope reinstatement.

-          E4 Retaining Wall ¡V Pavement and road marking completed.

-          E4 Ramp Utrough Bay 17~21 ¡V Pavement works completed.

-           FW56 Bay 22~25 ¡V Pavement works completed.

-          Noise barrier NB69 and NB68

A.         NB68 ¡V Road and drainage works were in progress.  

-          Noise barrier NB 108

A.         Construction of Bay 9 ~16 Backfilling was completed.

B.          Construction of Bay 6~7 capping beam was completed. Backfilling was in progress.

C.          Construction of Bay 3, 4 and 8 capping beam was in progress.

-          Noise barrier NB 66

A.         Piling works commenced on 3 January 2026. 20 out of 30 piles were completed. Drilling works was in progress.

-          Noise barrier 70

A.         Construction of Bay 13b was in progress.

B.          Site Clearance for Bay 7~12 was completed. Sheet piling was in progress.

C.          TTA456 Stage 2 for construction of Bay 14~20 to be implemented on 18 March 2026.

-          Noise Barrier NB29 Trough Bay 1-23

A.         Footing 100% completed.

B.          Wall (exclude parapet) is 100% completed

C.          Backfilling work to formation layer 100% completed.

D.         Parapet construction in progress, 100% completed

E.          Drainage work in progress 100% completed

F.          Bitumen laying work 100% completed  

-          Noise barrier NB 30

A.         Drainage work & backfilling work completed.

B.          Parapet construction in progress, 100% completed

C.          Drainage work in progress 100% completed

D.         Bitumen laying work 95% completed

-          Noise barrier NB 77

A.         NB1 Footing completed, stem wall in progress

B.          NB3 ELS completed, socket H pile in progress

-          Sign Gantry

A.         20 out of 20 columns fabrication (100%) were completed. 19 Columns were installed.

B.          11 out of 11 mid chords fabrication (100%) were completed. FADS21 mid chord was completed.

C.          10 out of 11 sign gantries (3 on viaducts, 7 at grade) were installed.  

-            Fabrication of Noise Barrier ¡V 75% of overall noise barrier columns were completed. Fabrication of NB68 and NB69 noise barrier columns was completed.

(b)         North Team

-          C1-03, C3-02, C4-03 & D1-02 catch pit & manhole construction completed.

-          C3-02, C4-03 & D1-02 outfall construction in progress

-          C3-03B, C1-03, C2-01 & D1-01 watermain works 90% completed

-          Reinstatement work at C3-04B footpath 75% completed

-          JCR: Construction of new central median & ducting works for traffic signal & road light were completed of 100%. Road commissioning on 19 Dec 2025

-          JCR & Tong Hang Village J/O improvement works (FS 25): slope works 100 % completed.

-          Road commissioning on 22 Jan 2026

-          JCR near F63 ¡Vslope feature construction works completed. Street furniture 90% completed

-          Pavilion construction in progress. Footing completed.

(c)          Bridges and Structures

-          Parapet at C3-01 completed. All profile barrier on the bridge completed.

-          Water test of fire hydrant in progress.

-          Reinstate of lifting tower NF83A in progress. The E&M test completed.

-          Installation of stainless-steel cover plate for MJ in progress, 50/54 completed.

-          Installation hopper for MJ in progress, 7/9 completed.

-          All Water proofing at bridge deck completed.

-          Asphalt pavement of all bridges completed.

-          Noise barrier NB27a at bridge C3 completed. All NB completed.

-          Installation of L3 railing at bridge C3 completed. All railing completed.

-          Step iron at deck void in progress

-          Water proofing for PT anchorage InProgress.

-          Deck Void CCTV Inspection completed at Bridge B1, B2, C1, C2, C3, C4, D1, E1 completed.

-          All external tendon completed

-          Step iron at deck void 90% completed

-          Maintenance scaffold storage at deck void 70% completed.

ND/2019/06

The construction phase was completed and handed over to AFCD since 4 April 2022.

ND/2019/07

All construction activities with significant environmental impact have been substantially completed in October 2025.

Construction Programme

2.10     Copies of Contractors¡¦ construction programmes are provided in Appendix A.

Status of Environmental Licences, Notifications and Permits

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Project is presented in Table 2.4.

Table 2.4       Status of Environmental Licences, Notifications and Permits

Contract No.

Permit / Licence No.

Valid Period

Status

From

To

Environmental Permit (EP)

ND/2019/01

EP-466/2013/A

21/11/2013

N/A

Valid

EP-467/2013/A

27/01/2017

N/A

Valid

EP-468/2013/A

27/01/2017

N/A

Valid

EP-470/2013/A

21/11/2013

N/A

Valid

ND/2019/02

EP-469/2013

21/11/2013

N/A

Valid

ND/2019/04

EP/473/2013/A

27/01/2017

N/A

Valid

EP/546/2017

16/11/2017

N/A

Valid

ND/2019/05

EP-473/2013/A

27/01/2017

N/A

Valid

Construction Noise Permit (CNP)

ND/2019/01

GW-RN1349-25

12/11/2025

11/04/2026

Valid

GW-RN1300-25

19/11/2025

18/04/2026

Valid

GW-RN1447-25

25/12/2025

24/04/2026

Valid

GW-RN0065-26

25/01/2026

24/04/2026

Valid

GW-RN1526-25

20/01/2026

19/04/2026

Valid

GW-RN1527-25

16/01/2026

15/05/2026

Valid

GW-RN1538-25

17/01/2026

16/06/2026

Valid

GW-RN1596-25

12/01/2026

11/04/2026

Valid

GW-RN0066-26

06/02/2026

05/07/2026

Valid

GW-RN0067-26

25/02/2026

24/06/2026

Valid

GW-RN0064-26

02/02/2026

01/06/2026

Valid

GW-RN0327-26

13/03/2026

30/04/2026

Valid

GW-RN0063-26

01/03/2026

31/08/2026

Valid

GW-RN0267-26

01/03/2026

30/04/2026

Valid

ND/2019/02

GW-RN1284-25

23/11/2025

22/04/2026

Valid

GW-RN1424-25

05/12/2025

04/03/2026

Expired in the reporting month

GW-RN0054-26

25/01/2026

24/04/2026

Valid

GW-RN0237-26

18/02/2026

17/07/2026

Valid

GW-RN0015-26

16/01/2026

15/04/2026

Valid

ND/2019/04

GW-RN1338-25

26/11/2025

25/03/2026

Expired in the reporting month

GW-RN1578-25

31/12/2025

26/03/2026

Expired in the reporting month

GW-RN1579-25

31/12/2025

30/03/2026

Expired in the reporting month

GW-RN1580-25

31/12/2025

26/03/2026

Expired in the reporting month

GW-RN1602-25

04/01/2026

11/03/2026

Expired in the reporting month

GW-RN0154-26

05/02/2026

04/05/2026

Valid

GW-RN0156-26

06/02/2026

05/05/2026

Valid

GW-RN0225-26

23/02/2026

22/05/2026

Valid

GW-RN0269-26

05/03/2026

30/04/2026

Valid

GW-RN0358-26

20/03/2026

31/03/2026

Expired in the reporting month

GW-RN0391-26

27/03/2026

30/05/2026

Valid


ND/2019/05

GW-RN1442-25

04/12/2025

03/03/2026

Expired in the reporting month

GW-RN1512-25

01/01/2026

30/04/2026

Valid

GW-RN1557-25

01/01/2026

31/03/2026

Expired in the reporting month

GW-RN0249-26

01/03/2026

31/08/2026

Valid

GW-RN0232-26

01/03/2026

31/05/2026

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

ND/2019/01

451792

11/12/2019

N/A

Valid

477388

02/03/2022

N/A

Valid

10023974

27/11/2025

N/A

Valid

10023973

27/11/2025

N/A

Valid

10001514

15/02/2024

N/A

Valid

ND/2019/02

454012

05/03/2020

N/A

Valid

ND/2019/04

461184

23/10/2020

N/A

Valid

ND/2019/05

454323

13/03/2020

N/A

Valid

483452

23/08/2022

N/A

Valid

Billing Account for Disposal of Construction Waste

ND/2019/01

7036265

17/01/2020

N/A

Valid

ND/2019/02

7036898

01/04/2020

N/A

Valid

ND/2019/04

7038391

22/09/2020

N/A

Valid

ND/2019/05

7036901

01/04/2020

N/A

Valid

Registration of Chemical Waste Producer

ND/2019/01

5213-545-B2578-01

10/01/2020

N/A

Valid

ND/2019/02

5213-548-C4439-01

06/05/2020

N/A

Valid

ND/2019/04

5211-624-D2709-01

26/11/2020

N/A

Valid

ND/2019/05

5213-625-C4464-01

20/05/2020

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

ND/2019/01

WT00037412-2021

05/12/2023

30/04/2026

Valid

WT00037564-2021

19/04/2021

30/04/2026

Valid

WT00037886-2021

28/06/2021

30/06/2026

Valid

WT00041311-2022

21/06/2022

30/06/2027

Valid

WT10001848-2023

05/12/2023

31/12/2028

Valid

WT00044860-2024

29/07/2024

31/07/2029

Valid

WT00044814-2024

08/07/2024

31/07/2029

Valid

WT10002972-2024

07/06/2024

30/06/2029

Valid

WT00046827-2025

30/06/2025

30/06/2030

Valid

WT00046825-2025

30/06/2025

30/06/2030

Valid

WT00046830-2025

30/06/2025

30/06/2030

Valid

WT00046840-2025

30/06/2025

30/06/2030

Valid

ND/2019/02

WT00047791-2025

17/12/2025

31/12/2030

Valid

ND/2019/04

WT00037539-2021

02/06/2022

30/04/2026

Valid

ND/2019/05

WT00042471-2022

03/11/2022

30/11/2027

Valid

WT00047635-2025

22/01/2026

31/12/2030

Valid