|
|
|
_R6_files/image006.jpg)
Contents
1.3
Construction Works Programme and Construction Works Area
1.4
Summary of Environmental Status. 3
2.3
Monitoring Parameter and Frequency and Duration
2.5
Monitoring Methodology and QA/QC Procedure
2.6
Action and Limit Level for Air Quality Monitoring
3 Construction Noise Monitoring
3.3
Noise Monitoring Parameter, Frequency and Duration
3.4
Monitoring Equipment, Methodology and QA / QC Procedure
3.5
Maintenance and Calibration
8 Land Contamination (Ambient Arsenic Monitoring)
8.4
Monitoring Parameters, Frequency and Duration
8.5
Monitoring Methodology and QA/QC Procedure
8.7
Laboratory Measurement / Analysis
10 Environmental Site Inspection and Audit
10.1
Implementation Status of Environmental Mitigation Measures
11 Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions
11.2
Summary of Environmental Non-Compliance
11.3
Summary of Environmental Complaint
11.4
Summary of Environmental Summon and Successful Prosecution
12.1
Works and Potential Environmental Issues in the next Reporting Period
13.2
Comments/ Recommendations
Figures
Figure 1.1 Location and Site Layout Plan (KTN)
Figure 1.2 Location and Site Layout Plan (FLN)
Figure 2.1 Location of Air Quality Monitoring Stations for KTN NDA
Figure 2.2 Location of Air Quality Monitoring Stations for FLN NDA
Figure 3.1 Location of Noise Monitoring Stations for KTN NDA
Figure 3.2 Location of Noise Monitoring Stations for FLN NDA
Figure 8.1 Location of Ambient Arsenic Monitoring Stations for KTN NDA
Appendix 1.1 Construction Programme
Appendix 1.2 Project Organization Chart
Appendix 1.3 Implementation Status of Environmental Mitigation Measure
Appendix 2.1 Impact Monitoring Schedule during the reporting period
Appendix 2.3 Weather Information during the Reporting Period
Appendix 2.4 Event and Action Plan for Construction Dust
Appendix 3.2 Event and Action Plan for Construction Noise
Appendix 5.1 Summary of Monthly Waste Flow Table
Appendix 6.3 Event and Action Plan for Ecological Monitoring
Appendix 7.1 Event and Action Plan for Landscape and Visual
Appendix 8.2 Event and Action Plan for Ambient Arsenic Monitoring
Appendix 11.1 Statistical Summary of Environmental Complaints, Summons and Prosecution
Appendix 12.1 Impact Monitoring Schedule of Next Reporting Month
A1. This is the 2nd Monthly Environment Monitoring and Audit (EM&A) Report for Remaining Phase Development of Kwu Tung North and Fanling North New Development Areas (the Project). This report was prepared by Aurecon Hong Kong Limited (Aurecon) under Service Contract No. NDO 05/2024 Remaining Phase Development of Kwu Tung North and Fanling North New Development Areas - Environmental Team (hereinafter called the Service Contract).
A2. Since only construction works were undertaken under Works Contract No. ND/2024/01 and Works Contract No. ND/2024/07 during the reporting month, this report documents the findings of EM&A works at Works Contract No. ND/2024/01 and Works Contract No. ND/2024/07 under the Project during the reporting period only. No construction works occurred in the remaining contracts during the reporting period for Works Contract No. ND/2024/02, ND/2024/03, ND/2024/04, ND/2024/05, ND/2024/06 and ND/2024/08.
A3. This Project involves nine (9) Environmental Permits (EPs) (i.e. EP-465/2013/A, EP-466/2013/A, EP-467/2013/A, EP-468/2013/A, EP-470/2013/A, EP-471/2013/A, EP-472/2013/A, EP-473/2013/A and EP-476/2013). Details of each EPs are summarised in Table A1.
Table A1 Works Contracts under relevant Environmental Permits in the Reporting Month
|
Environmental Permit No. |
Works Contracts |
Title of Designated Project |
Designated Project (DP) |
|
EP-465/2013/A |
ND/2024/03 |
NENT - San Tin Highway and Fanling Highway Kwu Tung Section Widening (Between San Tin Interchange and Po Shek Wu Interchange) |
DP1 |
|
EP-466/2013/A |
ND/2024/03 |
NENT - Castle Peak Road Diversion |
DP2 |
|
EP-467/2013/A |
ND/2024/01
|
NENT - Kwu Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange Improvement |
DP3 |
|
EP-468/2013/A |
ND/2024/01 |
Kwu Tung North New Development Area Road D1 to D5 |
DP4 |
|
EP-469/2013 |
- |
Sewage Pumping Stations in Kwu Tung North New Development Area |
DP5 |
|
EP-470/2013/A |
ND/2024/06 |
Utilization of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment Works |
DP7 |
|
EP-471/2013/A |
ND/2024/04 |
Po Shek Wu Interchange Improvement |
DP8 |
|
EP-472/2013/A |
ND/2024/08 |
Fanling Bypass Western Section |
DP9 |
|
EP-473/2013/A |
- |
Fanling Bypass Eastern Section |
DP10 |
|
- |
Shek Wu Hui Sewage Treatment Works - Further Expansion at Fanling North New Development Area |
DP11 |
|
|
ND/2024/07 ND/2024/08 |
NENT - Sewage Pumping Stations in Fanling North New Development Area (FLNDA) |
DP13 |
A4. Apart from the construction works undertaken under Works Contract No. ND/2024/01 since 20 January 2025, construction works under Works Contract No. ND/2024/07 has also been commenced since 27 February 2025. No construction works occurred in the remaining Works Contracts (i.e. Works Contract No. ND/2024/02, ND/2024/03, ND/2024/04, ND/2024/05, ND/2024/06 and ND/2024/08) during the reporting period. The commencement dates of each Works Contracts are summarized in Table A2.
Table A2 Commencement Dates of Each Works Contracts
|
Works Contracts |
Commencement Dates |
|
ND/2024/01 |
20 January 2025 |
|
ND/2024/02 |
Not Commenced |
|
ND/2024/03 |
Not Commenced |
|
ND/2024/04 |
Not Commenced |
|
ND/2024/05 |
Not Commenced |
|
ND/2024/06 |
Not Commenced |
|
ND/2024/07 |
27 February 2025 |
|
ND/2024/08 |
Not Commenced |
A5. A summary of construction activities undertaken during the reporting period is presented below:
Works Contract No. ND/2024/01:
· All Site Resumption Area(s)
1. Tree survey
2. Site Clearance
· Portion XL (40)
1. Site Clearance
2. Ground Investigation Works
3. Preparation Work for Site Formation Work
Works Contract No. ND/2024/07:
· Site Clearance for works areas
· Construction of Site Accommodation
· Pre-bored Socketed H Pile Construction
· Trial Pit Excavation
· Tree Felling
· Land Contamination Investigation
· Internal Movement / Exportation of C&D materials
Works Contract No. ND/2024/02, ND/2024/03, ND/2024/04, ND/2024/05, ND/2024/06 and ND/2024/08.
· No Construction Work during reporting period.
A6. The environmental monitoring activities, including 1-hour Total Suspended Particulates (TSP) monitoring, 24-hour TSP monitoring, noise monitoring, ecological survey, 24-hour Respirable Suspended Particulates (RSP) (Ambient Arsenic) monitoring for land contamination and environmental site inspection, were undertaken by Environmental Team (ET) under Service Contract No. NDO 04/2019 (i.e. First Phase ET Wellab) during the reporting period in accordance with the approved Updated EM&A Manual. A summary of the monitoring and audit activities during the reporting period is presented in Table A3.
Table A3 Summary of EM&A Activities in the Reporting Period
|
|
|
Works Contract(s)(5) |
|||||||
|
EM&A |
Monitoring Station(s) |
ND/2024/01 |
ND/2024/02 |
ND/2024/03 |
ND/2024/04 |
ND/2024/05 |
ND/2024/06 |
ND/2024/07 |
ND/2024/08 |
|
1-hour TSP Monitoring(1) |
KTN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS4(B)(2)(3) |
3, 6, 12, 18, 24, 28 Feb 2025(4) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A(8) |
N/A |
|
|
FLN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
28 Feb 2025(13) |
N/A |
|
|
FLN-DMS6(A)(2)(3) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS7(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
24-hour TSP Monitoring(1) |
KTN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS4(B)(2)(3) |
3, 6, 12, 18, 24, 28 Feb 2025(4) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
28 Feb 2025(13) |
N/A |
|
|
FLN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS5(A)(2)(3) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
28 Feb 2025(13) |
N/A |
|
|
FLN-DMS6(A)(2)(3) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS7(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Noise Monitoring(1) |
CP-KTN-NMS1(2)(7) |
N/A(1) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
CP-KTN-NMS2(2) |
3, 12, 18, 24 Feb 2025(4) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS3(2) |
3, 12, 18, 24 Feb 2025(4) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS6(2) |
3, 12, 18, 24 Feb 2025(4) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS7(2)(9) |
N/A(1) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A(10) |
N/A |
|
|
CP-FLN-NMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS4(A)(2)(3) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A(11) |
N/A |
|
|
CP-FLN-NMS6(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A(11) |
N/A |
|
|
Ecological Monitoring (6) |
Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley |
Weekly monitoring: 03, 04, 11, 13, 17, 18, 27, and 28 Feb 2025(4) (Transect T1, T2, T3, and T5)
Additional nighttime monitoring at Long Valley: 03 and 13(4) Feb 2025 (Transect T3 and T5) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution |
Monthly Monitoring: 26 Feb 2025(4) (Transect T1) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
24-hour RSP (Ambient Arsenic) Monitoring for Land Contamination (1) |
KTN-DMS-4A(2)(3) |
03, 06, 12, 18, 24, 28 Feb 2025(4) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Water Quality Monitoring |
KTN-IS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-CS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Landfill Gas Monitoring |
250m Landfill Consultation Zone of Ma Tao Lung Landfill |
N/A(12) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Environmental Site Inspection |
Site Area under Works Contract No. ND/2024/01 |
04, 11, 18, 25 Feb 2025 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Site Area under Works Contract No. ND/2024/07 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
27 Feb 2025 |
N/A |
|
Remarks:
(1) For 1-hour and 24-hour TSP & 24-hour RSP (Ambient Arsenic) monitoring, monitoring stations that are specifically within the 500m buffer area projected from the site boundary of works contract(s) will be considered being the representative monitoring stations for the corresponding works contract(s) and the associated impact monitoring exercises will be kicked off once the nearest works contracts have been commenced and undertaken during the reporting period/month.
For Noise Monitoring, monitoring stations that are specifically within the 300m buffer area projected from the site boundary of works contract(s) will be considered being the representative monitoring stations for the corresponding works contract(s) and the associated impact monitoring exercises will be kicked off once the nearest works contracts have been commenced and undertaken during the reporting period/month.
For Water Quality Monitoring, monitoring stations at which inland waters runs into the major water systems, including their tributaries, passing through the site boundary of works contract(s) involving construction of channelisation works, potentially causing water quality impacts as a result of water bodies contamination, will be considered being the representative monitoring stations for the corresponding works contract(s) involving construction of channelisation works as the rationale for determination of contract involvement in terms of environmental monitoring.
(2) New monitoring station IDs are presented. The corresponding monitoring station IDs are as follows:
|
1-hr and 24-hr TSP & 24-hr RSP (Ambient Arsenic) KTN-DMS1 = DMS1 |
Noise CP-KTN-NMS1 = CP-NMS1 CP-KTN-NMS7
= CP-NMS4 |
(3) Alternative monitoring stations to the corresponding original monitoring stations.
(4) The monitoring date for February 2025 was conducted by the ET from the First Phase of KTN/FLN NDAs Project.
(5) N/A No relevant monitoring is required according to the approved updated EM&A Manual.
(6) Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley and additional nighttime ecological monitoring at Long Valley and Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution were conducted by the First Phase ET of the KTN/FLN NDAs Project. The monitoring activities in Transects T1, T2, T3, and T5 under Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley were conducted prior to the commencement date of Works Contract No. ND/2024/07 (but for Transects T1 and T2 on 28 February); hence, not all monitoring data under this requirement is relevant to this contract. Also, monitoring for Transect T4 Shek Sheung River under Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley and for Transect T3 Area west of Siu Hang San Tsuen stream under Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution were not conducted. No additional monitoring activities were undertaken due to the short period between the commencement date of construction works for Works Contract No. ND/2024/07 (27 February 2025) and the end of the reporting month (28 February 2025). This interval is insufficient to coordinate and execute these additional ecological monitoring activities. This situation is only specific to this reporting month. Regular monitoring will commence in March 2025. No ecological monitoring was conducted for the Monitoring of Measures to Minimize Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream for this reporting period as this monitoring is only conducted during wet season (April October).
(7) As confirmed by the Supervisor Team, the works area within Portion 51 was not acquired from relevant stakeholder(s)* during the reporting period February 2025. Such that no noise monitoring at CP-KTN-NMS1 adjacent to Portion 51 was carried out in the reporting period. *Relevant stakeholders refer to parties owning the works areas to be acquired by works contract(s) (e.g. landlords, premises owners, relevant authorities, etc.)
(8) For 1-Hour TSP monitoring at FLN-DMS1, it was conducted by the First Phase ET dated on 1, 7, 13, 19 and 25 February 2025. The last monitoring event in February 2025 occurred prior to the commencement of ND/2024/07 (i.e., before 27 February 2025). Only monitoring data during reporting period would be presented and no impact monitoring was conducted during the reporting period of 27 to 28 February 2025. Monitoring will resume in March 2025 under ND/2024/07. Therefore, Not Applicable(N/A).
(9) For CP-KTN-NMS7, baseline monitoring for CP-KTN-NMS7 will be conducted in March 2025. Therefore, no impact noise monitoring at CP-KTN-NMS7 was carried out in the reporting period and would be resumed in March 2025.
(10) For Noise monitoring at CP-FLN-NMS1, it was conducted by the First Phase ET on 7, 13, 19 and 25 February 2025. The last monitoring event in February 2025 occurred prior to the commencement date of ND/2024/07 (i.e. before 27 February 2025). Only monitoring data during the reporting period would be presented and no impact monitoring was conducted during the reporting period of 27 to 28 February 2025. Monitoring will resume in March 2025 under ND/2024/07. Thus, Not Applicable(N/A).
(11) For CP-FLN-NMS5 and CP-FLN-NMS6 were not monitored as the interval was insufficient to coordinate and execute the noise monitoring under the Works Contract No. ND/2024/07 during the reporting month, monitoring will resume in March 2025. Thus, Not Applicable(N/A).
(12) As confirmed by the Supervisor Team, no ground disturbance works were carried out in the work area within 250m Landfill Consultation Zone of Ma Tso Lung Landfill including construction of the infrastructure, development works, excavation works and works involve confined spaces. Routine gas monitoring should be undertaken during groundwork construction and in all excavations.
(13) For 1-Hour TSP monitoring at FLN-DMS5 and 24-Hour TSP monitoring at FLN-DMS1 and FLN-DMS5A, it was conducted by the First Phase ET on 3, 6, 12, 18, 24 and 28 February 2025. Only monitoring data during the reporting period would be presented and no impact monitoring was conducted during the reporting period of 27 to 28 February 2025. Monitoring will resume in March 2025 under ND/2024/07. Therefore, Not Applicable(N/A).
A7. Summary of the environmental exceedances of the reporting period is tabulated in Table A4.
Table A4 Summary of Exceedances in the Reporting Period
|
Environmental Monitoring |
Parameter(s) |
No. of Exceedances |
Total No. of Exceedances |
No. of Non-project Related Exceedances |
Total No. of Non-project Related Exceedances |
No. of Exceedances Related to the Project |
Total No. of Exceedances Related to the Project |
|||
|
AL |
LL |
|
AL |
LL |
|
AL |
LL |
|
||
|
Air Quality |
1-hour TSP |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
24-hourTSP |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
24-hour RSP (Ambient Arsenic) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
Noise |
Leq(30mins) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Ecological Monitoring |
Avifauna |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Non-aquatic fauna |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Air Quality
A8. No AL or LL exceedance was recorded for air quality monitoring in the reporting period.
Noise
A9. No AL or LL exceedance was recorded for construction noise monitoring in the reporting period.
Ambient Arsenic
A10. No AL or LL exceedance was recorded for ambient arsenic monitoring in the reporting period.
Ecological Monitoring
A11. Action and Limit Levels for monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley and Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution could not be completely assessed during the reporting month. Avifauna monitoring for Transects T1, T2, T3, and T5 were only relevant to Works Contract No. ND/2024/01 as monitoring for these transects were conducted before the commencement of Works Contract No. ND/2024/07 (except for Transects T1 and T2 conducted on 28 February 2025); and monitoring for Transect T4 Shek Sheung River and Transect T3 west of Siu Hang San Tsuen Stream during the reporting period were not conducted. No additional monitoring was conducted due to insufficient time between the commencement date (27 February 2025) of Works Contract No. ND/2024/07 and the close of the reporting month (28 February 2025). Regular ecological monitoring for these transects will commence in March 2025 and Action and Limit Levels for these monitoring requirements will be subsequently reported. No exceedances are reported under Monitoring of Measures to Minimize Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream as monitoring activities for this requirement are scheduled during wet season (April-October).
A12. No environmental complaint was received in the reporting period.
A13. No notification of summons or successful prosecutions was received in the reporting period.
A14. There was no change to be reported that may affect the on-going EM&A programme.
A15. The major site activities for the next reporting period are summarized below and shown in Appendix 1.1:
Contract No. ND/2024/01:
All Site Resumption Area(s)
1. Tree survey
2. Site Clearance
Portion XXll (22) and Portion XLIV (44)
1. Site Clearance and Demolition
Portion XL (40)
1. Site Clearance and Tree Felling
2. Excavation, Mixing with General fill & Backfilling
3. Construct Retaining Wall & Backfilling
Contract No. ND/2024/06
Forming haul road for excavation works of Portion A;
Tree felling of Portion A;
Transplantation of fern (2nd batch);
General excavation to +108 mpd platform of Portion A;
Ground investigation works (borehole BH01-05 and piezometer B1
Slope trimming and soil nailing works of cut slope S1 & S2 / access road of Portion A;
Trial run for Temporary Traffic Arrangement (TTA) of Portion C;
Demolition of DN2000 pipes and associated thrust blocks of Portion D &
Watermains laying works at Fu Tei Au Road of Portion C & Portion D.
Contract No. ND/2024/07
Site Clearance for works areas
Construction of Site Accommodation
Pre-bored Socketed H Pile Construction
Trial Pit Excavation
Tree Felling
Land Contamination Investigation
Internal Movement / Exportation of C&D materials
1.1.1 The KTN/FLN NDAs development are implemented in two phases, comprising First Phase and Remaining Phase developments. The construction works for the First Phase development commenced in December 2019. The construction works for the Remaining Phase development (the Project), including site clearance and formation, roads, drainage, sewerage and water supply systems, commenced progressively from the January 2025.
1.1.2 The Project is delivered under eight (8) Works Contracts as below.
· Contract No. ND/2024/01: Site Formation and Infrastructure Works (South);
· Contract No. ND/2024/02: Site Formation and Infrastructure Works (North);
· Contract No. ND/2024/03: Improvement Works of Fanling Highway (Kwu Tung Portion) and Associated Works;
· Contract No. ND/2024/04: Improvement Works of Tai Tau Leng Roundabout and Po Shek Wu Road and Associated Works;
· Contract No. ND/2024/05: Improvement Works of Fanling Highway (Pak Shek Au Portion) and Associated Works;
· Contract No. ND/2024/06: Fresh Water and Flushing Water Service Reservoirs and Associated Works;
· Contract No. ND/2024/07: Site Formation and Infrastructure Works (East); and
· Contract No. ND/2024/08: Site Formation and Infrastructure Works (West).
1.1.3 The EIA Report (AEIAR-175/2013) for NENT NDA was approved with conditions under EIAO in 2013. The Environmental Permits for corresponding Designated Projects were also issued by DEP in November 2013. Subsequent to the findings of preliminary design and P&E Review for accommodating additional population in KTN and FLN NDAs, VEP were subsequently applied for nine EPs under the Project (i.e. EP-465/2013/A, EP-466/2013/A, EP-467/2013/A, EP-468/2013/A, EP-470/2013/A, EP-471/2013/A, EP-472/2013/A, EP-473/2013/A and EP-476/2013).
1.1.4 Aurecon was commissioned by Civil Engineering and Development Department (CEDD) to provide EM&A services for the works contracts in relation to the Project pursuant to the requirements as specified in relevant EPs, the EM&A Manual issued in the EIA stage, the Updated EM&A Manual prepared for Contract No. NDO 14/2018 and the approved EIA Report for the Project to discharge the duties of the ET for the Project.
1.1.5 This is the 2nd Monthly EM&A Report summarizing the findings of EM&A works at Contract No. ND/2024/01 under the Project with EP-467/2013/A and EP-468/2013/A during the reporting period from 01 to 28 February 2025 and Works Contract No. ND/2024/07 under Environmental Permit No. EP-476/2013 during the reporting period from 27 February 2025 to 28 February 2025. No construction works occur in the remaining contracts during the reporting period for Contract No. ND/2024/02, ND/2024/03, ND/2024/04, ND/2024/05, ND/2024/06 and ND/2024/08.
Table 1.1 Parties Involved in Project Organization for all Works Contracts
|
|
Works Contract(s) |
||||||||
|
Parties |
ND/2024/01 |
ND/2024/02 |
ND/2024/03 |
ND/2024/04 |
ND/2024/05 |
ND/2024/06 |
ND/2024/07 |
ND/2024/08 |
|
|
Project Proponent |
CEDD |
||||||||
|
Supervisor / Engineers Representative (ER) |
AECOM Asia Co. Ltd. |
- |
- |
- |
- |
- |
Atkins China Ltd. |
- |
|
|
Contractor |
Build King Richwell Engineering Joint Venture (BKJV) |
- |
- |
- |
- |
- |
Build King Richwell Engineering Joint Venture (BKJV) |
- |
|
|
ET |
Aurecon Hong Kong Limited |
||||||||
|
Independent Environmental Checker (IEC) |
Mott MacDonald Hong Kong Limited |
||||||||
Works Contract No. ND/2024/01:
All Site Resumption Area(s)
1. Tree survey
2. Site Clearance
Portion XL (40)
1. Site Clearance
2. Ground Investigation Works
3. Preparation Work for Site Formation Work
Work Contract No. ND/2024/07:
Site Clearance for works areas
Construction of Site Accommodation
Pre-bored Socketed H Pile Construction
Trial Pit Excavation
Tree Felling
Land Contamination Investigation
Internal Movement / Exportation of C&D materials
Table 1.2 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/01
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10008709 |
02/09/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7052236 |
20/09/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN: 5213-548-B2781-01 |
06/12/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00045924-2024 |
15/01/2025 |
31/01/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0060-25 |
20/01/2025 |
19/07/2025 |
Valid |
Table 1.3 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/07
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-476/2013 |
21/11/2013 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10007874 |
09/08/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7051974 |
20/08/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-625-B2775-01 |
19/08/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00045532-2024 |
10/12/2024 |
31/12/2029 |
Valid |
|
WT00046059-2025 |
14/02/2025 |
28/02/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN1230-24 |
28/10/2024 |
30/04/2025 |
Valid |
Table 2.1 Summary of Impact Air Quality Monitoring Stations in related to the Works Contracts in the Reporting Period
|
Monitoring Station(s) |
Works Contract(s) |
ASR ID in EIA |
Planned(3) or Existing |
Monitoring Location(s) |
|
KTN-DMS1 |
ND/2024/01 |
KTN-19 |
Planned |
Nursery Classes and Kindergarten; Post Offices |
|
KTN-DMS2 |
ND/2024/01 |
KTN-90 |
Planned |
Nursery Classes and Kindergarten (2 nos); District Elderly Community Centre |
|
KTN-DMS3 |
ND/2024/01 |
KTN-326 |
Planned |
Village Resite |
|
KTN-DMS4(B)(1)(2) |
ND/2024/01 |
KTN-E-162 |
Existing |
Temporary Structure at Pak Shek Au |
|
FLN-DMS1 |
ND/2024/07 |
FLN-E62 |
Existing |
Scattered Village Houses North of Proposed Potential Ecopark |
|
FLN-DMS2 |
ND/2024/07 |
FLN-E243 |
Planned |
Residential Building, Nursery Classes and Kindergartens, Neighbourhood Elderly Community Centre, Residential Home for the Elderly, Post Office |
|
FLN-DMS5, FLN-DMS5(A) |
ND/2024/07 |
FLN-E124 |
Existing |
Noble Hill / Good View New Village |
|
FLN-DMS7 |
ND/2024/07 |
FLN-20 |
Planned |
Planned premise for Weapon Training Division |
Remarks:
(1) KTN-DMS4(B) is the alternative air monitoring stations proposed to replace KTN-DMS4.
(2) As KTN-DMS4 - Temporary structure near Fanling Highway (near Pak Shek Au) is no longer as existing ASR, air quality monitoring station should be relocated to the alternative dust monitoring location according to the updated EM&A Manual, Section 2.6.2. According to Figure 3.1 of Approved EIA report and site visits conducted in June 2022, ASR at near KTN-E70 Temporary Structure near Fanling Highway near Pak Shek Au is considered as the most representative alternative station KTN-DMS4(B) for air quality monitoring for KTN-DMS4 (i.e. KTNE162).
(3) Impact monitoring will be carried out when the planned sensitive receivers are commissioned.
Table 2.2 Parameters Measured in the Impact Air Quality Monitoring
|
Parameter(s) |
Frequency(1) |
|
1-hour TSP |
Three times / 6 days |
|
24-hour TSP |
Once / 6 days |
Remark:
1) The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.
Table 2.3 Air Quality Monitoring Equipment
|
Monitoring Station(s) |
Manufacturer |
Model |
Equipment |
Quantity |
|
KTN-DMS4(B)(1), FLN-DMS1(1), FLN-DMS5(1), FLN-DMS5(A)(1) |
Met One Instruments |
AEROCET-831 |
Dust Monitor (1-hour and 24-hour TSP) |
3 |
Remark:
(1) The air
quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET
during the reporting period.
Instrumentation
Place the dust meter at least 1.3 meters above ground;
Press and hold the Power key momentarily to power on the unit and make sure that the battery level was not flash or in low level;
Allow the instrument to stand for about 3 second to display the Sample Screen minutes;
Press the START / STOP key to run the internal vacuum pump for 1 minute and be ready to use;
Use the select dial to select the PM range and press the START / STOP key to start a measurement;
Finally, push the START/STOP key to stop the measurement after 24-hour sampling;
Information such as sampling date, time, value and site condition were recorded during the monitoring period; and
All data were recorded in the data logger for further data processing.
Maintenance/Calibration
Check and calibrate the meters by High Volume Sampler (HVS) to check the validity and accuracy of the results measured by direct reading method at 2-month intervals throughout all stages of the air quality monitoring.
Table 2.4 Action and Limit Levels for 1-hour TSP Air Quality Monitoring
|
Monitoring Station |
AL (μg/m3) |
LL (μg/m3) |
|
KTN-DMS4(B) |
297 |
500 |
|
FLN-DMS1 |
303 |
500 |
|
FLN-DMS5 |
279 |
500 |
Table 2.5 Action and Limit Levels for 24-hour of TSP Air Quality Monitoring
|
Monitoring Station |
AL (μg/m3) |
LL (μg/m3) |
|
KTN-DMS4(B) |
192 |
260 |
|
FLN-DMS1 |
150 |
260 |
|
FLN-DMS5(A) |
153 |
260 |
Table 2.6 Summary Table of 1-hour TSP Monitoring Result during the Reporting Month
|
Monitoring Station |
Averaged Measured Value (μg/m3) |
Minimum Measured Value (μg/m3) |
Maximum Measured Value (μg/m3) |
Action Level (μg/m3) |
Limit Level, (μg/m3) |
|
KTN-DMS4(B)(1) |
77 |
48 |
142 |
297 |
500 |
|
FLN-DMS1(1)(2) |
N/A |
N/A |
N/A |
303 |
500 |
|
FLN-DMS5(1) |
46 |
56 |
41 |
279 |
500 |
(1) The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.
(2) For 1-Hour TSP monitoring at FLN-DMS1, it was conducted by the First Phase ET dated on 1, 7, 13, 19 and 25 February 2025. The last monitoring event in February 2025 occurred prior to the commencement of ND/2024/07 (i.e., before 27 February 2025). Only monitoring data during reporting period would be presented and no impact monitoring was conducted during the reporting period of 27 to 28 February 2025. Monitoring will resume in March 2025 under ND/2024/07. Therefore, Not Applicable(N/A).
Table 2.7 Summary Table of 24-hour TSP Monitoring Result during the Reporting Month
|
Monitoring Station |
Averaged Measured Value (μg/m3) |
Minimum Measured Value (μg/m3) |
Maximum Measured Value (μg/m3) |
Action Level (μg/m3) |
Limit Level, (μg/m3) |
|
KTN-DMS4(B)(1) |
79 |
54 |
125 |
192 |
260 |
|
FLN-DMS1(1) |
58 |
58 |
58 |
150 |
260 |
|
FLN-DMS5(A) (1) |
73 |
73 |
73 |
153 |
260 |
Remark:
(1) The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.
Table 3.1 Construction Noise Monitoring Stations near in related to the Works Contracts in the Reporting period
|
Monitoring Station(s) |
Works Contract(s) |
NSR EIA ID(s) |
Location(s) |
Planned Or Existing(2) |
Type of Measurement |
|
CP-KTN-NMS1(3) |
ND/2024/01 |
CP-NMS1 |
Residential Building at Ma Tso Lung |
Existing |
Free-Field(1) |
|
CP-KTN-NMS2 |
ND/2024/01 |
CP-NMS2 |
Residential Building at Ma Tso Lung |
Existing |
Free-Field(1) |
|
CP-KTN-NMS3 |
ND/2024/01 |
CP-NMS3 |
Fung Kong Garden |
Existing |
|
|
CP-KTN-NMS4(4) |
ND/2024/01 |
CP-NMS5 |
Primary School |
Planned |
|
|
CP-KTN-NMS6 |
ND/2024/01 |
N/A |
Ho Sheung Heung, Hau Ku ShekAncestral Hall, Hung Shing Temple & Pai Fung Temple and Sin Wai Nunnery |
Existing |
Faηade |
|
CP-KTN-NMS7(6) |
ND/2024/01 |
CP-NMS4 |
Oi Lok Home |
Existing |
Free-Field(1) |
|
CP-FLN-NMS1 |
ND/2024/07 |
CP-NMS10 |
Belair Monte |
Existing |
Facade |
|
CP-FLN-NMS3(4) |
ND/2024/07 |
CP-NMS12 |
Secondary School |
Planned |
Free-Field(1) |
|
CP-FLN-NMS5(7) |
ND/2024/07 |
CP-NMS8 |
Man Kok Village |
Existing |
Free-Field(1) |
|
CP-FLN-NMS6(7) |
ND/2024/07 |
CP-NMS9 |
Woodland Crest |
Existing |
Faηade |
Remarks:
(1) For Free Field measurement, +3 dB(A) should be added to the measured results.
(2) Impact monitoring will be carried out when the planned sensitive receivers are commissioned.
(3) As confirmed by the Supervisor Team, the works area within Portion 51 was not acquired from relevant stakeholder(s)* during the reporting period February 2025. Such that no noise monitoring at CP-KTN-NMS1 adjacent to Portion 51 was carried out in the reporting period. *Relevant stakeholders refer to parties owning the works areas to be acquired by works contract(s) (e.g. landlords, premises owners, relevant authorities, etc.)
(4) As confirmed with Engineer Representative, the planned school at CP-KTN-NMS4 and CP-FLN-NMS3 are not constructed yet. Thus, the impact noise monitoring will be carried out at monitoring station CP-KTN-NMS4 and CP-FLN-NMS3 after the construction and occupation of the planned school. No noise monitoring of the mentioned station was carried out in this reporting period.
(5) The monitoring date at CP-FLN-NMS1 conducted by the First Phase ET was before the commencement date of ND/2024/07, no monitoring conducted during the reporting period for FLN-NMS1 under ND/2024/07 and monitoring will resume in March 2025. Thus, Not Applicable(N/A).
(6) For CP-KTN-NMS7, baseline monitoring for CP-KTN-NMS7 will be conducted in March 2025. Therefore, no impact noise monitoring at CP-KTN-NMS7 was carried out in the reporting period and would be resumed in March 2025.
(7) For CP-FLN-NMS5 and CP-FLN-NMS6 were not monitored as the interval was insufficient to coordinate and execute the noise monitoring under the Works Contract No. ND/2024/07 during the reporting month, monitoring will resume in March 2025.
Table 3.2 Construction Noise Monitoring Parameter, Frequency and Duration
|
Monitoring Station |
Parameter |
Frequency and Duration |
|
CP-KTN-NMS2(1), CP-KTN-NMS3(1), CP-KTN-NMS6(1), CP-FLN-NMS1 |
Leq(30mins), L10 and L90 (as six consecutive Leq,5min readings) |
Once every week throughout the construction phase |
Remark:
(1) The noise monitoring was conducted by First Phase ET during the reporting period.
For faηade measurement, the monitoring station was set at a point 1 m from the exterior of the sensitive receivers buildING faηade and set at a position 1.2 m above the ground. For free-field measurement, the monitoring station was set at a position 1.2 m above the ground.
The battery condition was checked to ensure good functioning of the meter.
Parameters such as frequency weighting, the time weighting and the interval were set as follows:
- Frequency weighting: A
- Time weighting: Fast
- Interval: 30 minutes (Leq(30mins))
Prior to and after each noise measurement, the meter was calibrated using an acoustic calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration level before and after measurement is more than 1.0 dB, the measurement was considered invalid and repeat of noise measurement will be required after re-calibration or repair the equipment.
At the end of the monitoring period, the values of Leq, L10 and L90 were recorded. In addition, noise sources were recorded on a standard record sheet.
Table 3.3 Construction Noise Monitoring Equipment
|
Equipment(1) |
Manufacturer |
Model |
No. of Equipment |
Serial No. |
|
Sound Level Meter |
BSWA |
BSWA 308 |
2 |
580005 580006 |
|
Acoustic Calibrator |
SVANTEK |
SV30A |
1 |
24803 |
|
Bruel & Kjaer |
B&K 4231 |
1 |
2412367 |
Remark:
(1) The noise monitoring was conducted by First Phase ET during the reporting period.
The microphone head of the sound level meter and calibrator were regularly cleaned with a soft cloth;
The sound level meter and acoustic calibrator were calibrated annually; and
The accuracy of the sound level meter was checked using an acoustic calibrator generating a known sound pressure level at a known frequency immediately prior to and following each noise measurement. Measurements were accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB(A).
Table 3.4 Action and Limit Levels for Construction Noise Monitoring
|
Time Period |
Action |
Limit Level |
|
07:00 19:00 on normal weekdays |
When one or more documented complaints are received |
75 dB(A) |
Table 3.5 Summary of Construction Noise Monitoring Results during the Reporting Month
|
Works Contracts |
Monitoring Stations |
Noise Levels, Leq(30min), dB(A) |
Baseline Levels, dB(A) |
Limit Levels, dB(A) |
|
ND/2024/01 |
CP-KTN-NMS1(3) |
N/A(4) |
65.7 |
75 |
|
CP-KTN-NMS2(1)(2) |
53.5 59.1 |
58.6 |
||
|
CP-KTN-NMS3(1)(2) |
49.6 53.1 |
51.6 |
||
|
CP-KTN-NMS6(2) |
52.6 65.2 |
55.1 |
||
|
CP-KTN-NMS7(6) |
N/A |
N/A(4) |
||
|
ND/2024/07 |
CP-FLN-NMS1(2) |
N/A(5) |
69.9 |
|
|
CP-FLN-NMS5(2) |
N/A(7) |
N/A(4) |
||
|
CP-FLN-NMS6(2) |
N/A(7) |
N/A(4) |
Remarks:
(1) For Free Field measurement, +3 dB(A) was added to the measured results.
(2) The noise monitoring was conducted by First Phase ET during the reporting period.
(3) As confirmed by the Supervisor Team, the works area within Portion 51 was not acquired from relevant stakeholder(s)* during the reporting period February 2025. Such that no noise monitoring at CP-KTN-NMS1 adjacent to Portion 51 was carried out in the reporting period. *Relevant stakeholders refer to parties owning the works areas to be acquired by works contract(s) (e.g. landlords, premises owners, relevant authorities, etc.)
(4) The baseline level is under establishment.
(5) For Noise monitoring at CP-FLN-NMS1, it was conducted by the First Phase ET on 7, 13, 19 and 25 February 2025. The last monitoring event in February 2025 occurred prior to the commencement date of ND/2024/07 (i.e. before 27 February 2025). Only monitoring data during the reporting period would be presented and no impact monitoring was conducted during the reporting period of 27 to 28 February 2025. Monitoring will resume in March 2025 under ND/2024/07. Thus, Not Applicable(N/A).
(6) For CP-KTN-NMS7, baseline monitoring for CP-KTN-NMS7 will be conducted in March 2025. Therefore, no impact noise monitoring at CP-KTN-NMS7 was carried out in the reporting period and would be resumed in March 2025.
(7) For CP-FLN-NMS5 and CP-FLN-NMS6 were not monitored as the interval was insufficient to coordinate and execute the noise monitoring under the Works Contract No. ND/2024/07 during the reporting month, monitoring will resume in March 2025. Thus, Not Applicable(N/A).
Table 3.6 Summary of Observations at Noise Monitoring Stations
|
Works Contracts |
Monitoring Stations |
Location |
Major Noise Sources |
|
ND/2024/01 |
CP-KTN-NMS1(1) |
Residential Building at Ma Tso Lung |
N/A(5) |
|
CP-KTN-NMS2 |
Residential Building at Ma Tso Lung |
Road Traffic Noise, Excavator |
|
|
CP-KTN-NMS3 |
Fung Kong Garden |
Road Traffic Noise |
|
|
CP-KTN-NMS6 |
Ho Sheung Heung, Hau Ku ShekAncestral Hall, Hung Shing Temple & Pai Fung Temple and Sin Wai Nunnery |
Road Traffic Noise, Excavator, Breaker |
|
|
CP-KTN-NMS7(2) |
Oi Lok Home |
N/A(5) |
|
|
ND/2024/07 |
CP-FLN-NMS1(3) |
Belair Monte |
N/A(5) |
|
CP-FLN-NMS5(4) |
Man Kok Village |
N/A(5) |
|
|
CP-FLN-NMS6(4) |
Woodland Crest |
N/A(5) |
Remarks:
(1) As confirmed by the Supervisor Team, the works area within Portion 51 was not acquired from relevant stakeholder(s)* during the reporting period February 2025. Such that no noise monitoring at CP-KTN-NMS1 adjacent to Portion 51 was carried out in the reporting period. *Relevant stakeholders refer to parties owning the works areas to be acquired by works contract(s) (e.g. landlords, premises owners, relevant authorities, etc.)
(2) For CP-KTN-NMS7, baseline monitoring for CP-KTN-NMS7 will be conducted in March 2025. Therefore, no impact noise monitoring at CP-KTN-NMS7 was carried out in the reporting period and would be resumed in March 2025.
(3) For Noise monitoring at CP-FLN-NMS1, it was conducted by the First Phase ET on 7, 13, 19 and 25 February 2025. The last monitoring event in February 2025 occurred prior to the commencement date of ND/2024/07 (i.e. before 27 February 2025). Only monitoring data during the reporting period would be presented and no impact monitoring was conducted during the reporting period of 27 to 28 February 2025. Monitoring will resume in March 2025 under ND/2024/07. Thus, Not Applicable(N/A).
(4) For CP-FLN-NMS5 and CP-FLN-NMS6 were not monitored as the interval was insufficient to coordinate and execute the noise monitoring under the Works Contract No. ND/2024/07 during the reporting month, monitoring will resume in March 2025.
(5) No impact noise monitoring was carried out at the monitoring station. Thus, not applicable (N/A).
Table 4.1 Summary of Water Quality Monitoring Locations
|
New Monitoring Station(s) |
Original Monitoring Station ID(s) |
Description |
Location(s) |
Measurement Period |
|
KTN NDA |
||||
|
KTN-CS1 |
CS1 |
Control Station for KTN NDA |
Centreline of river, upstream of the channel |
During construction of channel |
|
KTN-IS1 |
IS1 |
Impact Station for KTN NDA |
Centreline of river, downstream of the channel |
During construction of channel |
|
FLN NDA |
||||
|
FLN-CS1 |
CS2 |
Control Station for FLN NDA |
Centreline of river, upstream of the channel |
During construction of channel |
|
FLN-IS1 |
IS2 |
Impact Station for FLN NDA |
Centreline of river, downstream of the channel |
During construction of channel |
Table 5.1 Summary of Waste Generated by the Construction Works from Works Contracts in the Reporting Period
|
Works Contract(s) |
Month |
Total Quantity Generated |
Actual Quantalities of Inert C&D Materials Generated Monthly |
|
Actual Quantities of C&D Wastes Generated Monthly |
||||||||
|
|
Hard Rock and Lage Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
Metals |
Paper / Carboard Packing |
Plastics |
Chemical Waste |
Yard Waste recycled in Shredding Facility |
Others e.g., general refuse |
||
|
(in 000m3) |
(in 000m3) |
(in 000m3) |
(in 000m3) |
(in 000m3) |
(in 000m3) |
(in 000kg) |
(in 000kg) |
(in 000kg) |
(in 000kg) |
(in 000kg) |
(in 000m3) |
||
|
ND/2024/01 |
February 2025 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
437.356 |
0.001 |
0.375 |
0.001 |
0.000 |
0.000 |
170.667 |
|
ND/2024/07 |
February 2025 |
0.003 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
0.003 |
0.003 |
Table 6.1 Summary of Monitoring Activities, Relevant Contracts, and Corresponding Transects
|
Monitoring Activity |
Relevant Works Contract(s) |
Relevant Transect(s)/Monitoring Station(s) |
|
|
First Phase ET |
Remaining Phase ET |
||
|
Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung, Sheung Yue, and Shek Sheung Rivers and Long Valley |
ND/2024/01* |
T1, T2, T3, T5 |
- |
|
ND/2024/02 |
T1, T2, T3, T5 |
T4 |
|
|
ND/2024/03 |
T1, T2, T3, T5 |
- |
|
|
ND/2024/04 |
- |
T4 |
|
|
ND/2024/05 |
N/A(1) |
N/A(1) |
|
|
ND/2024/06 |
T1, T2, T3 |
- |
|
|
ND/2024/07* |
T1, T2, T3 |
T4 |
|
|
ND/2024/08 |
T1, T2, T3 |
T4 |
|
|
Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream, and Long Valley |
ND/2024/01*^ |
MS_01, MS_02, MS_03, MS_04, MS_05, MS_06, MS_07, MS_08, MS_09, MS_10 |
- |
|
ND/2024/02 |
MS_01, MS_02, MS_03, MS_04, MS_05, MS_06, MS_07, MS_08, MS_09, MS_10 |
- |
|
|
ND/2024/03 |
N/A(2) |
N/A(2) |
|
|
ND/2024/04 |
N/A(2) |
N/A(2) |
|
|
ND/2024/05 |
N/A(2) |
N/A(2) |
|
|
ND/2024/06 |
N/A(2) |
N/A(2) |
|
|
ND/2024/07*^ |
MS_11, MS_12, MS_13, MS_14, MS_15 |
- |
|
|
ND/2024/08 |
N/A(2) |
N/A(2) |
|
|
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution |
ND/2024/01* |
T1 |
- |
|
ND/2024/02 |
T1, T6 |
- |
|
|
ND/2024/03 |
T4 |
- |
|
|
ND/2024/04 |
N/A(3) |
N/A(3) |
|
|
ND/2024/05 |
T4, T6 |
- |
|
|
ND/2024/06 |
- |
T2 |
|
|
ND/2024/07* |
T3 |
- |
|
|
ND/2024/08 |
T3 |
- |
|
Remarks:
(1) Contracts that are located relatively far from river channels.
(2) Contracts that are located relatively far from Ma Tso Lung and Siu Hang San Tsuen streams.
(3) Contracts that are located relatively far from the Ecological Sensitive Habitats as identified in the EIA.
(4) * = active works contracts (ND/2024/01 and ND/2024/07); ^ = monitoring only in April October.
Monitoring Methodology
Monitoring Parameters
Abundance of birds;
Types of habitats utilized by birds; and
Notable bird behaviours such as roosting, feeding, nesting and presence of juveniles.
Monitoring Location
T1. Ng Tung River
T2. Ng River
T3. Sheung Yue River and
T5. Long Valley
T1. Ng Tung River
T2. Ng River
T3. Sheung Yue River and
T4. Shek Sheung River
Monitoring Frequency
Table 6.2 Monitoring Programme for Waterbirds Monitoring, February 2025
|
Week |
Date |
Transect(1) |
|
1 |
03 February |
T3 and T5 |
|
04 February |
T1 and T2 |
|
|
2 |
11 February |
T1 and T2 |
|
13 February |
T3 and T5 |
|
|
3 |
17 February |
T3 and T5 |
|
18 February |
T1 and T2 |
|
|
4 |
27 February |
T3 and T5 |
|
28 February(2) |
T1 and T2 |
|
|
Additional nighttime monitoring in Long Valley |
03 February |
T5 |
|
13 February |
Remarks:
(1) Transects T1, T2, T3, and T5 are relevant to Works Contract ND/2024/01; Transects T1, T2, and T3 are relevant to Works Contract ND/2024/07. No monitoring was conducted in Transect T4 as Works Contract ND/2024/07 commenced on 27 February; hence, there is no sufficient time to carry out additional monitoring before the end of the reporting month.
(2) Monitoring activities that were conducted after the commencement of Works Contract ND/2024/07.
Monitoring Results
Table 6.3 Summary Table of Waterbird Monitoring Results Relative to Corresponding Action and Limit Levels, February, Transects T1, T2, T3, and T5
|
Monitoring Parameter |
Result in Reporting Month (February 2025) |
Baseline Level in Corresponding Month (February 2020) |
Action Level |
Limit Level |
|
T1, T2, and T3(1) |
||||
|
Mean abundance of large waterbirds(2) using Ng Tung River, Sheung Yue River and Shek Sheung River |
169 |
31 |
21 |
15 |
|
Mean abundance of Chinese Pond Heron using Ng Tung River, Sheung Yue River and Shek Sheung River |
10 |
11 |
8 |
5 |
|
T5. Long Valley(1) |
||||
|
Mean Abundance of birds (all species) recorded in LVNP |
1035 |
596 |
417 |
298 |
|
Mean abundance of the Chinese Pond Heron(3) |
10 |
11 |
8 |
5 |
|
Environmental disturbance and damage from activities in LVNP |
- |
- |
Activity likely to cause unacceptable environmental disturbance or damage noted in LVNP. |
Activity likely to cause unacceptable environmental disturbance or damage noted in LVNP. |
Remarks:
(1) Only relevant to Works Contract ND/2024/01. These monitoring activities were conducted prior to the commencement of Works Contract ND/2024/07 (except for those collected on 28 February 2028 in Transects T1 and T2) and monitoring in Transect T4 was not carried out. No additional monitoring was undertaken due to the short period between the commencement date of construction works for Works Contract No. ND/2024/07 (27 February 2025) and the end of the reporting month (28 February 2025). This interval is insufficient to coordinate and execute the additional ecological monitoring. This situation is only specific to this reporting month. Regular monitoring will commence in March 2025.
(2) Large waterbirds: Great Egret (Ardea alba), Grey Heron (Ardea cinerea), Chinese Egret (Egretta eulophotes), Little Egret (Egretta garzetta), Intermediate Egret (Ardea intermedia), and Great Cormorant (Phalacrocorax carbo).
(3) Chinese Pond Heron (Ardeola bacchus) was the most abundant waterbird species recorded in Long Valley during the baseline survey and was strictly associated with wetland habitats.
Monitoring Methodology
Terrestrial Mammal
Herpetofauna (Amphibians and Reptiles)
Butterfly and Odonates
Monitoring Parameters
Species composition;
Abundance;
Distribution for fauna observed; and
Species of conservation importance would be specified.
Monitoring Location
T1. Ma Tso Lung riparian zone and associated wetland habitats; green belt areas E1-8, D1-8 and G1-3 in KTN NDA; AGR zone C2-4 and C2-2 in KTN NDA, and area north of Ng Tung River;
T2. Fanling North Freshwater Service Reservoir
T3. Area west of Siu Hang San Tsuen Stream;
T4. South side of Fanling Highway and Castle Peak Road in the vicinity of Pak Shek Au;
T5. Area west and east of the southern limit of the FLN NDA work area; and
T6. Areas in the western part of KTN.
Monitoring Frequency
Monitoring Results
Terrestrial Mammals
Herpetofauna (Amphibians and Reptiles)
Butterfly and Dragonfly
Summary of Monitoring Results
Table 6.4 Summary Table of Monitoring Results for Non-aquatic Fauna Relative to Action and Limit Levels, Transect T1
|
Monitoring Parameter |
Result in Reporting Month (February 2025) |
Baseline Level in Corresponding Month (February 2020) |
Action Level(3) |
Limit Level(4) |
|
Terrestrial Mammals (1) |
3 |
1 |
N/A |
N/A |
|
Herpetofauna (1) |
3 |
3 |
2 |
1 |
|
Dragonflies (1) |
3 |
4 |
3 |
2 |
|
Butterflies (2) |
17 |
8 |
6 |
4 |
Notes:
(1) Number of native species recorded
(2) Number of species recorded
(3) Exceedance of Action Level occurs when the monitoring result is lower than the Action Level.
(4) Exceedance of Limit Level occurs when the monitoring result is lower than the Limit Level.
Details of the Influencing Factors
Compendium Method 1O-3.1 Selection, Preparation and Extraction of Filter Material, Center for Environmental Research Information, Office of Research and Development, USEPA, June 1999; and Compendium Method 1O-3.5 determination of Metals in Ambient Particulate Matter using Inductively Coupled Plasma/Mass Spectrometry (ICP/MS., Center for Environmental Research Information, Office of Research and Development, USEPA, June 1999.
Table 8.1 Location of Ambient Arsenic Monitoring station
|
Monitoring Station(s) |
Location(s) |
Works Contract(s) |
|
KTN-DMS-4A(1)(2) |
Temporary Structure at Pak Shek Au |
ND/2024/01 |
Remarks:
(1) Monitoring at the original location of KTN-DMS-4 (originally proposed in the approved EM&A Manual) was denied as there was no electricity supply. An alternative location (KTN-DMS-4A) was proposed by First Phase ET.
(2) The ambient arsenic monitoring was conducted by First Phase ET during the reporting period.
Table 8.2 Ambient Arsenic Monitoring Equipment
|
Monitoring Station |
Equipment |
Manufacturer |
Model |
No. of Equipment |
|
KTN-DMS-4A(1)(2) |
Calibrator |
TISCH |
TE-5025A |
1 |
|
HVS Sampler (RSP) |
TISCH |
TE-6070X |
1 |
Remarks:
(1) Monitoring at the original location of KTN-DMS-4 (originally proposed in the approved EM&A Manual) was denied as there was no electricity supply. An alternative location (KTN-DMS-4A) was proposed by First Phase ET.
(2) The ambient arsenic monitoring was conducted by First Phase ET during the reporting period.
Table 8.3 Impact Ambient Arsenic Monitoring Parameters, Frequency and Duration
|
Parameters |
Frequency(1) |
|
24-hr RSP (Ambient Arsenic) |
Once/ 6 days |
Remark:
1. The ambient arsenic monitoring was conducted by First Phase ET during the reporting period.
Instrumentation
a horizontal platform with appropriate support to secure the samplers against gusty wind was provided;
no two samplers was placed less than 2 meters apart;
the distance between the sampler and an obstacle, such as buildings, was at least twice the height that the obstacle protrudes above the sampler;
a minimum of 2 meters of separation from walls, parapets and penthouses was required for rooftop samplers;
a minimum of 2 meters separation from any supporting structure, measured horizontally was required;
no furnace or incinerator flue was nearby;
airflow around the sampler was unrestricted;
the sampler was more than 20 meters from the dripline;
any wire fence and gate, to protect the sampler, were not cause any obstruction during monitoring;
permission was obtained to set up the samplers and to obtain access to the monitoring stations; and
a secured supply of electricity was needed to operate the samplers
Operating/analytical procedures for the operation of HVS
Prior to the commencement of the dust sampling, the flow rate of the high volume sampler was properly set (between 1.1 m3 /min. and 1.4 m3 /min.) in accordance with the manufacturer's instruction to within the range recommended in USEPA Standard Title 40, CFR Part 50;
The power supply was checked to ensure the sampler worked properly. On sampling, the sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter media at the designated air monitoring station;
The filter holding frame was then removed by loosening the four nuts and a weighted and conditioned filter was carefully centered with the stamped number upwards, on a supporting screen;
The filter was aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter. The filter holding frame was then tightened to the filter holder with swing bolts. The applied pressure was sufficient to avoid air leakage at the edges;
The shelter lid was closed and secured with the aluminum strip;
The timer was then programmed. Information was recorded on the record sheet, which included the starting time, the weather condition and the filter number (the initial weight of the filter paper can be found out by using the filter number);
After sampling, the filter was removed and sent to the Wellab Ltd. for weighing. The elapsed time was also recorded; and
Before weighing, all filters were equilibrated in a conditioning environment for 24 hours. The conditioning environment temperature was between 25°C and 30°C and did not vary by more than ±3°C; the relative humidity (RH) was < 50% and did not vary by more than ±5%. A convenient working RH was 40%. Weighing results were further analysis of RSP concentrations collected by each filter.
The high volume motors and their accessories were properly maintained. Appropriate maintenance such as routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power supply were in good working condition; and
High volume samplers were calibrated at bi-monthly intervals using TE-5025A Calibration Kit throughout all stages of the ambient arsenic monitoring.
Table 8.4 Result Summary Against Action and Limit Levels for 24-hour RSP Monitoring Results (Ambient Arsenic)
|
Contract No. |
Monitoring Date |
Monitoring Station |
Concentration (ƞg/m3) |
AL (ƞg/m3) |
LL (ƞg/m3) |
|
ND/2024/01 |
03/02/2025 |
KTN-DMS4A* |
3.87 |
9.36 |
11.7 |
|
06/02/2025 |
5.63 |
||||
|
12/02/2025 |
4.21 |
||||
|
18/02/2025 |
6.08 |
||||
|
24/02/2025 |
4.99 |
||||
|
28/02/2025 |
5.60 |
Remark:
* The 24-hour RSP monitoring for ambient arsenic was conducted by First Phase ET during the reporting period.
Ψ Excavation Locations: N/A
Ψ Manholes and Chambers: N/A
Ψ Relocation of monitoring wells: N/A
Ψ Any other Confined Spaces: N/A
Table 10.1 Site Observations at Works Contract No. ND/2024/01 and ND/2024/07 during the Reporting Period
|
Works Contracts |
Inspection Date |
Key Observations/ Reminders |
Follow-up Action |
|
ND/2024/01 |
04 February 2025 |
Observation:
Nil |
Nil |
|
Reminder:
Nil |
Nil |
||
|
11 February 2025 |
Observation:
Nil |
Nil |
|
|
Reminder:
1. The contractor was reminded to cover stockpile of dusty rocks at Portion XL in order to avoid fugitive dust emission. |
Nil |
||
|
18 February 2025 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
25 February 2025 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
ND/2024/07 |
27 February 2025 |
Observation:
1. Construction solid waste, debris and rubbish on site should be collected, handled and disposed of properly at Portion 1a (Footbridge FB-4 (South)) to avoid water quality impacts |
1. Soil and debris on the u-channel have been removed and the u-channel has been covered by plastic board to prevent further contamination. (Rectified on 28 February 2025) |
|
Reminder:
1. The Contractor was reminded that stockpile should be covered with tarpaulin sheet at Portion 9b to avoid fugitive dust emission. |
Nil |
All Site Resumption Area(s)
1. Tree survey
2. Site Clearance
Portion XXll (22) and Portion XLIV (44)
1. Site Clearance and Demolition
Portion XL (40)
1. Site Clearance and Tree Felling
2. Excavation, Mixing with General fill & Backfilling
3. Construct Retaining Wall & Backfilling
Contract No. ND/2024/06
Forming haul road for excavation works of Portion A;
Tree felling of Portion A;
Transplantation of fern (2nd batch);
General excavation to +108 mpd platform of Portion A;
Ground investigation works(borehole BH01-05 and piezometer B1
Slope trimming and soil nailing works of cut slope S1 & S2 / access road of Portion A;
Trial run for Temporary Traffic Arrangement (TTA) of Portion C;
Demolition of DN2000 pipes and associated thrust blocks of Portion D &
Watermains laying works at Fu Tei Au Road of Portion C & Portion D.
Contract No. ND/2024/07
Site Clearance for works areas
Construction of Site Accommodation
Pre-bored Socketed H Pile Construction
Trial Pit Excavation
Tree Felling
Land Contamination Investigation
Internal Movement / Exportation of C&D materials
Dust
Regular watering to reduce dust emissions from exposed site surface;
Stockpile of dusty materials shall be covered entirely by impervious sheeting;
Provide vehicles washing facilities at all site exits to wash away any dusty materials from vehicle body;
NRMM Labels should be displayed on the applicable equipment on site by the Contractor;
Provision of water sprinklers along the haul road for dust suppression.
Noise
Only well-maintained plant should be operated on-site, and plant should be maintained regularly during the construction programme; and
Quality Powered Mechanical Equipment (QPME) should be adopted as far as possible.
Water Quality
No effluent discharge would be allowed before acquired the effluent discharge license;
Surface run-off from construction sites should be discharged into dedicated discharge point via adequately designed sand/ silt removal facilities;
Channels/ earth bunds/ sandbags barriers should be provided on site to properly direct stormwater to silt removal facilities;
Silt removal facilities, channels and manholes should be maintained, and the deposited silt and grit should be removed regularly;
Open stockpiles of construction materials on sites should be covered with tarpaulin or similar fabric during rainstorms; and
Perimeter channels should be provided on site boundaries where necessary to intercept stormwater run-off from outside the site so that it will not wash across the site.
Waste Management
Provision of sufficient waste disposal points and regular collection of waste;
Regular cleaning and maintenance programme for drainage system; and
Chemical containers shall be stored with drip tray underneath.
Landscape and Visual
Construction activities shall be carefully designed to minimize impact on existing retained trees
Land Contamination
Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be properly covered by impermeable sheeting to reduce dust emission during dry season or contaminated run-off during rainy season. Watering should be avoided on stockpiles of soil to minimise runoff.
Landfill Gas Hazard
No Smoking and No Naked Flame notices in Chinese and English should be posted prominently around the construction site.
Ecology
Properly erect and maintain 2m high solid barriers for protection.