_R2_files/image004.jpg)
Contents
1.3 Construction Works Programme and Construction Works Area
1.4 Summary of Environmental Status
2.3 Monitoring Parameter and Frequency and Duration
2.5 Monitoring Methodology and QA/QC Procedure. 10
2.6 Action and Limit Level for Air Quality Monitoring
3 Construction Noise Monitoring
3.3 Noise Monitoring Parameter, Frequency and Duration
3.4 Monitoring Equipment, Methodology and QA / QC Procedure
3.5 Maintenance and Calibration
8 Land Contamination (Ambient Arsenic Monitoring)
8.4 Monitoring Parameters, Frequency and Duration
8.5 Monitoring Methodology and QA/QC Procedure. 41
8.7 Laboratory Measurement / Analysis
10 Environmental Site Inspection and Audit
10.1 Implementation Status of Environmental Mitigation Measures
11 Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions
11.2 Summary of Environmental Non-Compliance. 51
11.3 Summary of Environmental Complaint
11.4 Summary of Environmental Summon and Successful Prosecution
12.1 Works and Potential Environmental Issues in the next Reporting Period
13.2 Comments/ Recommendations
Figures
Figure 1.1 Location and Site Layout Plan (KTN)
Figure
1.2 Location and Site Layout
Plan (FLN)
Figure 2.1 Location of Air Quality Monitoring Stations for KTN NDA
Figure 2.2 Location of Air Quality Monitoring Stations for FLN NDA
Figure 3.1 Location of Noise Monitoring Stations for KTN NDA
Figure 3.2 Location of Noise Monitoring Stations for FLN NDA
Figure 8.1 Location of Ambient Arsenic Monitoring Stations for KTN NDA
Appendix 1.1 Construction Programme
Appendix 1.2 Project Organization Chart
Appendix 1.3 Implementation Status of Environmental Mitigation Measure
Appendix 2.1 Impact Monitoring Schedule during the reporting period
Appendix 2.2 Impact Air Quality Monitoring Data & Graphical Presentations & Calibration Certificates
Appendix 2.3 Weather Information during the Reporting Period
Appendix 2.4 Event and Action Plan for Construction Dust
Appendix 3.1 Impact Noise Monitoring Data & Graphical Presentations & Calibration Certificates
Appendix 3.2 Event and Action Plan for Construction Noise
Appendix
5.1 Summary of Monthly Waste Flow Table
Appendix 6.1 Detailed Results of the Ecological Waterbird Monitoring during this Reporting Period
Appendix 6.2 Detailed Results of the Ecological Aquatic Monitoring during this Reporting Period
Appendix 6.3 Detailed Results of the Ecological Non-aquatic Monitoring during this Reporting Period
Appendix 6.4 Event and Action Plan for Ecological Monitoring
Appendix 7.1 Event and Action Plan for Landscape and Visual
Appendix 8.2 Event and Action Plan for Ambient Arsenic Monitoring
Appendix 11.1 Statistical Summary of Environmental Complaints, Summons and Prosecution
Appendix 12.1 Impact Monitoring Schedule of Next Reporting Month
A1. This is the 8th Monthly Environment Monitoring and Audit (EM&A) Report for Remaining Phase Development of Kwu Tung North and Fanling North New Development Areas (the Project). This report was prepared by Aurecon Hong Kong Limited (Aurecon) under Service Contract No. NDO 05/2024 Remaining Phase Development of Kwu Tung North and Fanling North New Development Areas - Environmental Team (hereinafter called the Service Contract).
A2. Since only construction works were undertaken under Works Contract No. ND/2024/01, Works Contract No. ND/2024/03, Works Contract No. ND/2024/04, Works Contract No. ND/2024/06 and Works Contract No. ND/2024/07 during the reporting month, this report documents the findings of EM&A works at Works Contract No. ND/2024/01, Works Contract No. ND/2024/03, Works Contract No. ND/2024/04, Works Contract No. ND/2024/06 and Works Contract No. ND/2024/07 under the Project during the reporting period only. No construction works occurred in the remaining contracts during the reporting period for Works Contract No. ND/2024/02, ND/2024/05 and ND/2024/08.
A3. This Project involves nine (9) Environmental Permits (EPs) (i.e. EP-465/2013/A, EP-466/2013/A, EP-467/2013/A, EP-468/2013/A, EP-470/2013/A, EP-471/2013/A, EP-472/2013/A, EP-473/2013/A and EP-476/2013). Details of each EPs are summarised in Table A1.
Table A1 Works Contracts under relevant Environmental Permits in the Reporting Month
|
Environmental Permit No. |
Works Contracts |
Title of Designated Project |
Designated Project (DP) |
|
EP-465/2013/A |
ND/2024/03 |
NENT - San Tin Highway and Fanling Highway Kwu Tung Section Widening (Between San Tin Interchange and Po Shek Wu Interchange) |
DP1 |
|
EP-466/2013/A |
ND/2024/03 |
NENT - Castle Peak Road Diversion |
DP2 |
|
EP-467/2013/A |
ND/2024/01
|
NENT - Kwu Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange Improvement |
DP3 |
|
EP-468/2013/A |
ND/2024/01 |
Kwu Tung North New Development Area Road D1 to D5 |
DP4 |
|
EP-469/2013 |
- |
Sewage Pumping Stations in Kwu Tung North New Development Area |
DP5 |
|
EP-470/2013/A |
ND/2024/06 |
Utilization of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment Works |
DP7 |
|
EP-471/2013/A |
ND/2024/04 |
Po Shek Wu Interchange Improvement |
DP8 |
|
EP-472/2013/A |
ND/2024/08 |
Fanling Bypass Western Section |
DP9 |
|
EP-473/2013/A |
- |
Fanling Bypass Eastern Section |
DP10 |
|
- |
Shek Wu Hui Sewage Treatment Works - Further Expansion at Fanling North New Development Area |
DP11 |
|
|
ND/2024/07 ND/2024/08 |
NENT - Sewage Pumping Stations in Fanling North New Development Area (FLNDA) |
DP13 |
A4. Apart from the construction works undertaken under Works Contract No. ND/2024/01 since 20 January 2025, construction works under Works Contract No. ND/2024/07 commenced since 27 February 2025, construction works under Works Contract No. ND/2024/06 commenced since 10 March 2025, construction works under Works Contract No. ND/2024/04 commenced since 10 May 2025, construction works under Works Contract No. ND/2024/03 has also been commenced since 2 June 2025. No construction works occurred in the remaining Works Contracts (i.e. Works Contract No. ND/2024/02, ND/2024/05 and ND/2024/08) during the reporting period. The commencement dates of each Works Contracts are summarized in Table A2.
Table A2 Commencement Dates of Each Works Contracts
|
Works Contracts |
Commencement Dates |
|
ND/2024/01 |
20 January 2025 |
|
ND/2024/02 |
Not Commenced |
|
ND/2024/03 |
2 June 2025 |
|
ND/2024/04 |
10 May 2025 |
|
ND/2024/05 |
Not Commenced |
|
ND/2024/06 |
10 March 2025 |
|
ND/2024/07 |
27 February 2025 |
|
ND/2024/08 |
Not Commenced |
A5. A summary of construction activities undertaken during the reporting period is presented below:
Works Contract No. ND/2024/01:
· All Site Resumption Area(s)
1. Tree survey
2. Site Clearance
· Portion I (1)
1. Asbestos Abatement Works
· Portion IX (9)
1. Demolition Works
· Portion VI (6), XXXVIII (38)
1. Demolition Works
· Portion XI (11), XXIII (23)
1. Asbestos Abatement Works
· Portion XL (40)
1. Excavation, Mixing with General fill & Backfilling
· Portion XLIV (44)
1. Asbestos Abatement Works
· Portion LIX (59)
1. Setting Up of High Arsenic-Containing Soil (HAS) Treatment Plant
Works Contract No. ND/2024/03:
Kwu Tung Road Bridge
· Site Clearance and Tree Works
· Site formation and cutback the existing slope
· Predrilling
Works Areas WA1, WA2, WA3 , WA4 & WA5
· Hoarding Works
Portion XI East Abutment
· Trial Pits for UUs
· Predrilling
Works Contract No. ND/2024/04:
· Site Clearance
· Site Establishment
· Tree felling
· Trial Pit
· Ground Investigation
· Pre-drilling
· Haul Road Construction
· Hoarding Erection
· Demolition Works
Works Contract No. ND/2024/06:
· Excavation to +108 mPD of Portion A;
· Backfill and reinstatement of Portion C
· Watermains laying works of Portion D
· Demolition of DN2000 pipes and associated thrust blocks of Portion D
Works Contract No. ND/2024/07:
· Site Clearance
· Site Formation
· Ground Investigation
· Pile Cap Construction
· Pier Construction
· UU Diversion
· Tree Felling & Transportation
· Asbestos Containing Materials Survey
· Asbestos Containing Materials Removal
· Archaeological Impact Assessment
· Land Contamination Investigation
· Internal Movement, Importation & Exportation of C&D materials
Works Contract No. ND/2024/02, ND/2024/05 and ND/2024/08.
· No Construction Work during reporting period.
The environmental monitoring activities, including 1-hour Total Suspended Particulates (TSP) monitoring, 24-hour TSP monitoring, noise monitoring, ecological survey, 24-hour Respirable Suspended Particulates (RSP) (Ambient Arsenic) monitoring for land contamination and environmental site inspection, were undertaken by Environmental Team (ET) under Service Contract No. NDO 04/2019 (i.e. First Phase ET Wellab) and under Service Contract No. NDO 05/2024 (i.e. Remaining Phase ET Aurecon) during the reporting period in accordance with the approved Updated EM&A Manual. A summary of the monitoring and audit activities during the reporting period is presented in Table A3.
Table A3 Summary of EM&A Activities in the Reporting Period
|
|
|
Works Contract(s)(5) |
|||||||
|
EM&A |
Monitoring Station(s) |
ND/2024/01 |
ND/2024/02 |
ND/2024/03 |
ND/2024/04 |
ND/2024/05 |
ND/2024/06 |
ND/2024/07 |
ND/2024/08 |
|
1-hour TSP Monitoring(1) |
KTN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS4(B)(2)(3) |
6, 12, 18, 22, 28 August 2025 |
N/A |
6, 12, 18, 22, 28 August 2025 |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
1, 7, 13, 19, 25, 29 August 2025 |
N/A |
|
|
FLN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
6, 12, 18, 22, 28 August 2025 |
N/A |
|
|
FLN-DMS6(A)(2)(3) |
N/A |
N/A |
1, 7, 13, 19, 25, 30 August 2025 (7) |
N/A |
N/A |
N/A |
N/A |
||
|
FLN-DMS7(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
24-hour TSP Monitoring(1) |
KTN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS4(B)(2)(3) |
6, 12, 18, 22, 28 August 2025 |
N/A |
6, 12, 18, 22, 28 August 2025 |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
6, 12, 18, 22, 28 August 2025 |
N/A |
|
|
FLN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS5(A)(2)(3) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
6, 12, 18, 22, 28 August 2025 |
N/A |
|
|
FLN-DMS6(A)(2)(3) |
N/A |
N/A |
1, 7, 13, 19, 25, 30 August 2025 (7) |
N/A |
N/A |
N/A |
N/A |
||
|
FLN-DMS7(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Noise Monitoring(1) |
CP-KTN-NMS1(2) |
1, 7, 13, 19, 28 August 2025(7) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
CP-KTN-NMS2(2) |
6, 12, 18, 28 August 2025 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS3(2) |
6, 12, 18, 28 August 2025 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
6, 12, 18, 28 August 2025 |
N/A |
N/A |
|
|
CP-KTN-NMS6(2) |
6, 12, 18, 28 August 2025 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS7(2) |
1, 7, 13, 19, 28 August 2025 (7) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
7, 13, 19, 25 August 2025 |
N/A |
||
|
CP-FLN-NMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS4(A)(2)(3) |
N/A |
N/A |
N/A |
4, 15, 21, 27 August 2025(7) |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
4, 15, 21, 27 August 2025(7) |
N/A |
|
|
CP-FLN-NMS6(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
4, 15, 21, 27 August 2025(7) |
N/A |
|
|
Ecological Monitoring (6) |
Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley |
Weekly Monitoring: 7, 8, 14, 15, 19, 21, 26, 29 August 2025(4) (Transect T1, T2, T3, and T5) |
N/A |
Weekly Monitoring: 7, 8, 14, 15, 19, 21, 26, 29 August 2025(4) (Transect T1, T2, T3, and T5) |
Weekly Monitoring: 4, 8, 12, 15, 20, 22, 25, 28 August 2025(4) (Transect T4) |
N/A |
Weekly Monitoring: 7, 8, 14, 15, 19, 21, 26, 29 August 2025(4) (Transect T1, T2, T3) |
Weekly Monitoring: 4, 7, 8, 12, 14, 15, 19, 20, 21, 22, 25, 26, 28, 29 August 2025(4) (Transect T1, T2, T3, T4) |
N/A |
|
Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream |
Monthly Monitoring: 11 August 2025(4) (MS_01 MS_10) |
N/A |
N/A |
N/A |
N/A |
N/A |
Monthly Monitoring: 11 August 2025(4) (MS_11 MS_15) |
N/A |
|
|
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution |
Monthly Monitoring: 19 August 2025(4) (Transect T1) |
N/A |
Monthly Monitoring: 12 August 2025(4) (Transect T4) |
N/A |
N/A |
Monthly Monitoring: 27 August 2025(4) (Transect T2) |
Monthly Monitoring: 12 August 2025(4) (Transect T3) |
N/A |
|
|
24-hour RSP (Ambient Arsenic) Monitoring for Land Contamination (1) |
KTN-DMS-4A(2)(3) |
6, 12, 18, 22, 28 August 2025 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Water Quality Monitoring(1) |
KTN-IS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-CS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-IS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-CS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Landfill Gas Monitoring |
250m Landfill Consultation Zone of Ma Tso Lung Landfill |
N/A(8) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Environmental Site Inspection |
Site Area under Works Contract No. ND/2024/01 |
6, 12, 19, 26 August 2025 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Site Area under Works Contract No. ND/2024/03 |
N/A |
N/A |
4, 12, 18, 25 August 2025 |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/04 |
N/A |
N/A |
N/A |
1, 8, 13, 22, 29 August 2025 |
N/A |
N/A |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/06 |
N/A |
N/A |
N/A |
N/A |
N/A |
4, 11, 18, 25 August 2025 |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/07 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
7, 15, 21, 28 August 2025 |
N/A |
|
Remarks:
(1) For 1-hour and 24-hour TSP & 24-hour RSP (Ambient Arsenic) monitoring, monitoring stations that are specifically within the 500m buffer area projected from the site boundary of works contract(s) will be considered being the representative monitoring stations for the corresponding works contract(s) and the associated impact monitoring exercises will be kicked off once the nearest works contracts have been commenced and undertaken during the reporting period/month.
For Noise Monitoring, monitoring stations that are specifically within the 300m buffer area projected from the site boundary of works contract(s) will be considered being the representative monitoring stations for the corresponding works contract(s) and the associated impact monitoring exercises will be kicked off once the nearest works contracts have been commenced and undertaken during the reporting period/month.
For Water Quality Monitoring, monitoring stations at which inland waters runs into the major water systems, including their tributaries, passing through the site boundary of works contract(s) involving construction of channelisation works, potentially causing water quality impacts as a result of water bodies contamination, will be considered being the representative monitoring stations for the corresponding works contract(s) involving construction of channelisation works as the rationale for determination of contract involvement in terms of environmental monitoring.
(2) New monitoring station IDs are presented. The corresponding monitoring station IDs are as follows:
|
1-hr and 24-hr TSP / 24-hr RSP (Ambient Arsenic) KTN-DMS1 = DMS1 |
Noise CP-KTN-NMS1 = CP-NMS1 CP-KTN-NMS7
= CP-NMS4 |
(3) Alternative monitoring stations to the corresponding original monitoring stations.
(4) The monitoring date for the reporting month was conducted by the ET from the First Phase of KTN/FLN NDAs Project, except Transect T4 for the ecological monitoring item Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley, and Transect T2 for the ecological monitoring item Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution.
(5) N/A No relevant monitoring is required according to the approved updated EM&A Manual.
(6) Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley; Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution and Monitoring of Measures to Minimize Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream were conducted by the First Phase ET of the KTN/FLN NDAs Project except Transect T4 (waterbird monitoring) and Transect T2 (monitoring of ecological sensitive habitats).
(7) The monitoring date for the reporting month was conducted by the ET from the Remaining Phase of KTN/FLN NDAs Project.
(8) As confirmed by the Supervisor Team, no ground disturbance works were carried out in the work area within 250m Landfill Consultation Zone of Ma Tso Lung Landfill including construction of the infrastructure, development works, excavation works and works involve confined spaces. Routine gas monitoring should be undertaken during groundwork construction and in all excavations.
A6. Summary of the environmental exceedances of the reporting period is tabulated in Table A4.
Table A4 Summary of Exceedances in the Reporting Period
|
Environmental Monitoring |
Parameter(s) |
No. of Exceedances |
Total No. of Exceedances |
No. of Non-project Related Exceedances |
Total No. of Non-project Related Exceedances |
No. of Exceedances Related to the Project |
Total No. of Exceedances Related to the Project |
|||
|
AL |
LL |
|
AL |
LL |
|
AL |
LL |
|
||
|
Air Quality |
1-hour TSP |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
24-hourTSP |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
24-hour RSP (Ambient Arsenic) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
Noise |
Leq(30mins) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Ecological Monitoring |
Avifauna |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Aquatic fauna |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
Non-aquatic fauna |
0 |
2 |
2 |
0 |
2 |
2 |
0 |
0 |
0 |
|
Air Quality
A7. No AL or LL exceedance was recorded for air quality monitoring in the reporting period.
Noise
A8. No AL or LL exceedance was recorded for construction noise monitoring in the reporting period.
Ambient Arsenic
A9. No AL or LL exceedance was recorded for ambient arsenic monitoring in the reporting period.
Ecological Monitoring
A10. 2 Limit Level exceedances were recorded for the monitoring of measures to minimise impacts on ecological sensitive habitats from disturbance and pollution. All exceedances were deemed as non-project related with potential influences by abiotic factors.
A11. No environmental complaint was received in the reporting period. Details are shown in Appendix 11.1.
A12. No notification of summons or successful prosecutions was received in the reporting period.
A13. There was no change to be reported that may affect the on-going EM&A programme.
A14. The major site activities for the next reporting period are summarized below and shown in Appendix 1.1:
Contract No. ND/2024/01:
· All Site Resumption Area(s)
1. Tree survey
2. Site Clearance
· Portion XI (11), XXIII (23)
1. Asbestos Abatement Works
· Portion XL (40)
1. Excavation, Mixing with General fill & Backfilling
2. Construct Retaining Wall & Backfilling
· Portion LIX (59)
1. Setting Up including T&C of High Arsenic-Containing Soil (HAS) Treatment Plant
Contract No. ND/2024/03
· Portion XVI
1. Site Clearance and Tree Works
2. Watermain and Sewer Pipe Laying
· Portion IX
1. Asbestos Removal Works
· Portion XI
1. Site Clearance and Tree Works
2. Ground Investigation
· TTA stage 1 Works
1. Tree Works
2. Demolish of Central Divider & Barrier
3. Piling Works
· TTA stage 1B
1. Site Clearance
· Works Areas WA1, WA2, WA3, WA4 & WA5
1. Site Clearance and Site Formation
2. Hoarding Works
3. Asbestos Removal Works
Contract No. ND/2024/04
· Site Clearance
· Site Establishment
· Tree Felling
· Trial Pit
· Haul Road Construction
· Ground Investigation
· Pre-drilling
· Demolition of Existing Structures
· Existing Sewage Diversion
· Bored Piling
Contract No. ND/2024/06
· Forming Haul Road beside Existing THFWSR For Excavation Works of Portion A;
· Tree falling at Haul Road
· Ground investigation works
· Slope trimming and soil nailing works of cut slope S1 & S2 / access road of Portion A;
· Watermains laying works at Lung Yeuk Tau of Portion F.
· Demolition of DN2000 pipes and associated thrust blocks of Portion D
· Watermains laying works at Fu Tei Au Road of Portion D
· Excavation to +102mPD of Portion A
Contract No. ND/2024/07
· Site Clearance
· Site Formation
· Ground Investigation
· Pre-bored Socketed H Pile Construction
· Sheet Piling
· Pile Cap Construction
· Pier Construction
· UU Diversion
· Sewerage Construction
· Tree Felling
· Asbestos Containing Material Removal
· Asbestos Containing Materials Survey
· Archaeological Impact Assessment
· Land Contamination Investigation
· Internal Movement, Importation & Exportation of C&D materials
1.1.1 The KTN/FLN NDAs development are implemented in two phases, comprising First Phase and Remaining Phase developments. The construction works for the First Phase development commenced in December 2019. The construction works for the Remaining Phase development (the Project), including site clearance and formation, roads, drainage, sewerage and water supply systems, commenced progressively from the January 2025.
1.1.2 The Project is delivered under eight (8) Works Contracts as below.
· Contract No. ND/2024/01: Site Formation and Infrastructure Works (South);
· Contract No. ND/2024/02: Site Formation and Infrastructure Works (North);
· Contract No. ND/2024/03: Improvement Works of Fanling Highway (Kwu Tung Portion) and Associated Works;
· Contract No. ND/2024/04: Improvement Works of Tai Tau Leng Roundabout and Po Shek Wu Road and Associated Works;
· Contract No. ND/2024/05: Improvement Works of Fanling Highway (Pak Shek Au Portion) and Associated Works;
· Contract No. ND/2024/06: Fresh Water and Flushing Water Service Reservoirs and Associated Works;
· Contract No. ND/2024/07: Site Formation and Infrastructure Works (East); and
· Contract No. ND/2024/08: Site Formation and Infrastructure Works (West).
1.1.3 The EIA Report (AEIAR-175/2013) for NENT NDA was approved with conditions under EIAO in 2013. The Environmental Permits for corresponding Designated Projects were also issued by DEP in November 2013. Subsequent to the findings of preliminary design and P&E Review for accommodating additional population in KTN and FLN NDAs, VEP were subsequently applied for nine EPs under the Project (i.e. EP-465/2013/A, EP-466/2013/A, EP-467/2013/A, EP-468/2013/A, EP-470/2013/A, EP-471/2013/A, EP-472/2013/A, EP-473/2013/A and EP-476/2013).
1.1.4 Aurecon was commissioned by Civil Engineering and Development Department (CEDD) to provide EM&A services for the works contracts in relation to the Project pursuant to the requirements as specified in relevant EPs, the EM&A Manual issued in the EIA stage, the Updated EM&A Manual prepared for Contract No. NDO 14/2018 and the approved EIA Report for the Project to discharge the duties of the ET for the Project.
1.1.5 This is the 8th Monthly EM&A Report summarizing the findings of EM&A works at Works Contract No. ND/2024/01 under the Project with EP-467/2013/A and EP-468/2013/A, Works Contract No. ND/2024/03 under the Project with EP-465/2013/A, EP-466/2013/A and EP-467/2023/A, Works Contract No. ND/2024/04 under the Project with EP-465/2013/A and EP-471/2013/A, Works Contract No. ND/2024/06 under Environmental Permit No. EP-470/2013/A and for Contract No. ND/2024/07 under Environmental Permit No. EP-476/2013 during the reporting period from 01 to 31 August 2025. No construction works occur in the remaining contracts during the reporting period for Contract No. ND/2024/02, ND/2024/05 and ND/2024/08.
Table 1.1 Parties Involved in Project Organization for all Works Contracts
|
|
Works Contract(s) |
||||||||
|
Parties |
ND/2024/01 |
ND/2024/02 |
ND/2024/03 |
ND/2024/04 |
ND/2024/05 |
ND/2024/06 |
ND/2024/07 |
ND/2024/08 |
|
|
Project Proponent |
CEDD |
||||||||
|
Supervisor / Engineers Representative (ER) |
AECOM Asia Co. Ltd. |
- |
AECOM Asia Co. Ltd |
AECOM Asia Co. Ltd |
- |
Binnies Hong Kong Limited |
AtkinsRιalis |
- |
|
|
Contractor |
Build King Richwell Engineering Joint Venture (BKJV) |
- |
China State STEC Joint Venture |
CW CRCC (ND202404) Joint Venture |
- |
Wo Hing-Tsun Yip Joint Venture |
Build King Richwell Engineering Joint Venture (BKJV) |
- |
|
|
ET |
Aurecon Hong Kong Limited |
||||||||
|
Independent Environmental Checker (IEC) |
Mott MacDonald Hong Kong Limited |
||||||||
Works Contract No. ND/2024/01:
· All Site Resumption Area(s)
1. Tree survey
2. Site Clearance
· Portion I (1)
1. Asbestos Abatement Works
· Portion IX (9)
1. Demolition Works
· Portion VI (6), XXXVIII (38)
1. Demolition Works
· Portion XI (11), XXIII (23)
1. Asbestos Abatement Works
· Portion XL (40)
1. Excavation, Mixing with General fill & Backfilling
· Portion XLIV (44)
1. Asbestos Abatement Works
· Portion LIX (59)
1. Setting Up of High Arsenic-Containing Soil (HAS) Treatment Plant
Works Contract No. ND/2024/03:
· Kwu Tung Road Bridge
· Site Clearance and Tree Works
· Site formation and cutback the existing slope
· Predrilling
Works Areas WA1, WA2, WA3, WA4 & WA5
· Hoarding Works
Portion XI East Abutment
· Trial Pits for UUs
· Predrilling
Works Contract No. ND/2024/04:
· Site Clearance
· Site Establishment
· Tree felling
· Trial Pit
· Ground Investigation
· Pre-drilling
· Hau Road Construction
· Hoarding Erection
· Demolition Works
Works Contract No. ND/2024/06:
· Excavation to +108 mPD of Portion A;
· Backfill and reinstatement of Portion C;
· Watermains laying works of Portion D
· Demolition of DN2000 pipes and associated thrust blocks of Portion D
Work Contract No. ND/2024/07:
· Site Clearance
· Site Formation
· Ground Investigation
· Pre-bored Socketed H Pile Construction
· Sheet Piling
· Pile Cap Construction
· Pier Construction
· UU Diversion
· Sewerage Construction
· Tree Felling
· Asbestos Containing Materials Survey
· Asbestos Containing Materials Removal
· Archaeological Impact Assessment
· Land Contamination Investigation
· Internal Movement, Importation & Exportation of C&D materials
Table 1.2 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/01
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10008709 |
02/09/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7052236 |
20/09/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN: 5213-548-B2781-01 |
06/12/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00045924-2024 |
15/01/2025 |
31/01/2030 |
Valid |
|
WT00046627-2025 |
03/06/2025 |
30/06/2030 |
Valid |
|
WT00046736-2025 |
10/06/2025 |
30/06/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0966-25 |
22/08/2025 |
11/02/2025 |
Valid |
|
GW-RN0757-25 |
09/07/2025 |
31/12/2025 |
Valid |
Table 1.3 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/03
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-465/2013/A |
20/01/2017 |
N/A |
Valid |
|
EP-466/2013/A |
18/08/2022 |
N/A |
Valid |
|
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10008101 |
16/08/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7052008 |
21/08/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-548-C5047-01 |
22/01/2025 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00046044-2025 |
16/04/2025 |
28/02/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0800-25 |
16/07/2025 |
03/01/2026 |
Valid |
|
GW-RN0703-25 |
02/07/2025 |
30/09/2025 |
Valid |
Table 1.4 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/04
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-465/2013/A |
20/01/2017 |
N/A |
Valid |
|
EP-471/2013/A |
10/10/2022 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10012919 |
N/A |
N/A |
Under Application |
|
Billing Account for Disposal of Construction Waste |
|||
|
7053746 |
13/02/2025 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-626-C5043-25 |
28/01/2025 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
10017727 |
N/A |
N/A |
Under Application |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0632-25 |
13/06/2025 |
30/11/2025 |
Valid |
|
GW-RN0667-25 |
18/06/2025 |
30/09/2025 |
Valid |
|
GW-RN0709-25 |
23/06/2025 |
22/09/2025 |
Valid |
|
GW-RN0947-25 |
24/08/2025 |
23/11/2025 |
Valid |
|
GW-RN0948-25 |
20/08/2025 |
31/01/2026 |
Valid |
Table 1.5 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/06
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-470/2013/A |
13/05/2022 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10007695 |
06/08/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7051899 |
28/08/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-624-W3824-01 |
04/09/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00046560-2025 |
15/05/2025 |
31/05/2030 |
Valid |
|
WT00046847-2025 |
29/05/2025 |
31/05/2030 |
Valid |
|
WT00046588-2025 |
11/07/2025 |
31/07/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
Kong Nga Po Road |
15/08/2025 |
28/02/2026 |
Valid |
Table 1.6 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/07
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-476/2013 |
21/11/2013 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10007874 |
09/08/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7051974 |
20/08/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-625-B2775-01 |
19/08/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00045532-2024 |
10/12/2024 |
31/12/2029 |
Valid |
|
WT00046059-2025 |
14/02/2025 |
28/02/2030 |
Valid |
|
WT00046059-2025 |
17/06/2025 |
28/02/2030 |
Valid |
|
WT00046342-2025 |
15/05/2025 |
31/05/2030 |
Valid |
|
WT00046692-2025 |
29/05/2025 |
31/05/2030 |
Valid |
|
WT00046655-2025 |
03/06/2025 |
30/06/2030 |
Valid |
|
WT00046819-2025 |
31/07/2025 |
31/07/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0448-25 |
24/04/2025 |
31/10/2025 |
Valid |
|
GW-RN0570-25 |
16/05/2025 |
22/08/2025 |
Valid |
|
GW-RN0565-25 |
26/05/2025 |
30/11/2025 |
Valid |
|
GW-RN0671-25 |
06/06/2025 |
12/09/2025 |
Valid |
|
GW-RN0859-25 |
23/07/2025 |
11/11/2025 |
Valid |
|
GW-RN0975-25 |
15/08/2025 |
22/02/2026 |
Valid |
Table 2.1 Summary of Impact Air Quality Monitoring Stations in related to the Works Contracts in the Reporting Period
|
Monitoring Station(s) |
Works Contract(s) |
ASR ID in EIA |
Planned(3) or Existing |
Monitoring Location(s) |
|
KTN-DMS1 |
ND/2024/01, ND/2024/03 |
KTN-19 |
Planned |
Nursery Classes and Kindergarten; Post Offices |
|
KTN-DMS2 |
ND/2024/01 |
KTN-90 |
Planned |
Nursery Classes and Kindergarten (2 nos); District Elderly Community Centre |
|
KTN-DMS3 |
ND/2024/01, ND/2024/03 |
KTN-326 |
Planned |
Village Resite |
|
KTN-DMS4(B)(1)(2) |
ND/2024/01, ND/2024/03 |
KTN-E70 |
Existing |
Temporary Structure at Pak Shek Au |
|
FLN-DMS1 |
ND/2024/07 |
FLN-E62 |
Existing |
Scattered Village Houses North of Proposed Potential Ecopark |
|
FLN-DMS2 |
ND/2024/06, ND/2024/07 |
FLN-E243 |
Planned |
Residential Building, Nursery Classes and Kindergartens, Neighbourhood Elderly Community Centre, Residential Home for the Elderly, Post Office |
|
FLN-DMS5, FLN-DMS5(A) |
ND/2024/07 |
FLN-E124 |
Existing |
Noble Hill / Good View New Village |
|
FLN-DMS6(A) |
ND/2024/03, ND/2024/04 |
DMS-10 |
Existing |
Choi Ngan House, Choi Po Court |
|
FLN-DMS7 |
ND/2024/06, ND/2024/07 |
FLN-20 |
Planned |
Planned premise for Weapon Training Division |
Remarks:
(1) KTN-DMS4(B) is the alternative air monitoring stations proposed to replace KTN-DMS4.
(2) As KTN-DMS4 - Temporary structure near Fanling Highway (near Pak Shek Au) is no longer as existing ASR, air quality monitoring station should be relocated to the alternative dust monitoring location according to the updated EM&A Manual, Section 2.6.2. According to Figure 3.1 of Approved EIA report and site visits conducted in June 2022, ASR at near KTN-E70 Temporary Structure near Fanling Highway near Pak Shek Au is considered as the most representative alternative station KTN-DMS4(B) for air quality monitoring for KTN-DMS4 (i.e. KTN-E162).
(3) Impact monitoring will be carried out when the planned sensitive receivers are commissioned.
Table 2.2 Parameters Measured in the Impact Air Quality Monitoring
|
Parameter(s) |
Frequency(1)(2) |
|
1-hour TSP |
Three times / 6 days |
|
24-hour TSP |
Once / 6 days |
Remark:
(1) The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.
(2) The air quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the reporting period.
Table 2.3 Air Quality Monitoring Equipment
|
Monitoring Station(s) |
Equipment |
Model |
Manufacturer |
Quantity |
|
KTN-DMS4(B)(1), FLN-DMS5(1), FLN-DMS5(A)(1) |
Dust Monitor (1-hour and 24-hour TSP) |
AEROCET-831 |
Met One Instruments |
5 |
|
FLN-DMS1(1) |
Dust Monitor (1-hour TSP) |
|||
|
HVS Sampler (24-hour TSP) |
TE-5170 |
Tisch |
1 |
|
|
FLN-DMS6(A)(2) |
Dust Monitor (1-hour and 24-hour TSP) |
LD-5R |
Sibata |
1 |
Remark:
(1) The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.
(2) The air quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the reporting period.
Instrumentation
(AEROCET-831)
· Place the dust meter at least 1.3 meters above ground;
· Press and hold the Power key momentarily to power on the unit and make sure that the battery level was not flash or in low level;
· Allow the instrument to stand for about 3 second to display the Sample Screen minutes;
· Press the START / STOP key to run the internal vacuum pump for 1 minute and be ready to use;
· Use the select dial to select the PM range and press the START / STOP key to start a measurement;
· Finally, push the START/STOP key to stop the measurement after 24-hour sampling;
· Information such as sampling date, time, value and site condition were recorded during the monitoring period; and
· All data were recorded in the data logger for further data processing.
Maintenance/Calibration
· Check and calibrate the meters by High Volume Sampler (HVS) to check the validity and accuracy of the results measured by direct reading method at 2-month intervals throughout all stages of the air quality monitoring.
Instrumentation
(TISCH Model: TE-5170 / TE-5170X)
· A horizontal platform with appropriate support was provided to secure the samplers against gusty wind. the dust meter at least 1.3 meters above ground;
· No two samplers were placed less than 2 metres apart.
· The distance between the sampler and an obstacle, such as buildings, was at least twice the height that the obstacle protrudes above the sampler.
· A minimum of 2 metres of separation from walls, parapets and penthouses was required for rooftop samples.
· A minimum of 2 metres separation from any supporting structure, measured horizontally was required.
· No furnaces or incineration flues were nearby.
· Airflow around the sampler was unrestricted.
· The sampler were more than 20 metres from the drip line.
· Any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring.
· Permission and access to monitoring stations have been obtained to set up the samplers.
· A secured supply of electricity was provided to operate the samplers.
Filters Preparation
Operating/Analytical Procedures
· Prior to the commencement of dust sampling, the flow rate of the HVS was properly set (between 1.1 m3 /min. and 1.4 m3 /min.) in accordance with the manufacturer's instruction to within the range recommended in USEPA Standard Title 40, CFR Part 50;
· The power supply was checked to ensure the sampler worked properly;
· On sampling, the sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter media at the designated air quality monitoring station;
· The filter holding frame was then removed by loosening the four nuts and carefully a weighted and conditioned filter was centered with the stamped number upwards, on a supporting screen;
· The filter was aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter. The filter holding frame was then tightened to the filter holder with swing bolts. The applied pressure should be sufficient to avoid air leakage at the edges;
· The shelter lid was closed and secured with the aluminum strip;
· The timer was then programmed. Information was recorded on the record sheet, which included the starting time, the weather condition and the filter number (the initial weight of the filter paper can be found out by using the filter number);
· After sampling, the filter was removed and kept in a clean and tightly sealed plastic bag. The filter paper was then returned to the HOKLAS accredited laboratory (Wellab Ltd.) for reconditioning in the humidity-controlled chamber followed by accurate weighting by an electronic balance with a readout down to 0.1mg. The elapsed time was also recorded; and
· Before weighing, all filters were equilibrated in a conditioning environment for 24 hours. The conditioning environment temperature should be between 25°C and 30°C and did not vary by more than ±3°C; the RH should be < 50% and did not vary by more than ±5%. A convenient working RH is 40%. Weighing results were returned for further analysis of TSP concentrations collected by each filter
Maintenance/Calibration
· The high-volume motors and their accessories were properly maintained. Appropriate maintenance such as routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power supply are in good working conditions; and
· All HVS were calibrated (five point calibration) using Calibration Kit prior to the commencement of baseline monitoring and thereafter at bi-monthly intervals.
Instrumentation
(Sibata Model: LD5R)
· Placed the dust meters at least 1.5m above ground
· Set POWER to ON and make sure that the battery level not flashed or in low level;
· Pulled the air sampling inlet cover up;
· Pushed the knob at MEASURE position;
· Set time/mode setting to [BG] by pushing the time setting switch. Then, started the background measurement by pushing the start/stop switch once. It took 6 sec. to complete the background measurement;
· Turned knob to SENSI. ADJ position and pressed in;
· Pushed Start/Stop switch once;
· Gently returned knob to the MEASURE position;
· Pushed the time setting switch to change the time setting display to [LOG] at the bottom left of the liquid crystal display;
· Removed the cap and started measurement; and
· Information such as sampling date, time, count value and site condition were recorded during the monitoring period.
Maintenance/Calibration
· Direct reading dust meter shall be used in determining 1-hr TSP and 24-hr TSP at air quality monitoring points. The direct reading dust meters have been calibrated against high volume samplers (HVSs) bi-monthly. A 2-day, three 3-hour measurement results per day from direct reading dust meters were taken to compare with the sampling results from the HVSs. The correlation between the direct reading dust meters and the HVSs were then concluded. By accounting for the correlation factor, the direct reading dust meters are considered to achieve comparable results as that of the HVSs.
· The HVS used to calibrate the direct dust monitor will need to be calibrated bi-monthly. Details of maintenance and calibration for the HVS refers to Section 2.5.8. Calibration for the air quality monitoring equipment is attached to the Appendix 2.2.
Table 2.4 Action and Limit Levels for 1-hour TSP Air Quality Monitoring
|
Monitoring Station |
AL (μg/m3) |
LL (μg/m3) |
|
KTN-DMS4(B) |
297 |
500 |
|
FLN-DMS1 |
303 |
500 |
|
FLN-DMS5 |
279 |
500 |
|
FLN-DMS6(A) |
286 |
500 |
Table 2.5 Action and Limit Levels for 24-hour of TSP Air Quality Monitoring
|
Monitoring Station |
AL (μg/m3) |
LL (μg/m3) |
|
KTN-DMS4(B) |
192 |
260 |
|
FLN-DMS1 |
150 |
260 |
|
FLN-DMS5(A) |
153 |
260 |
|
FLN-DMS6(A) |
157 |
260 |
Table 2.6 Summary Table of 1-hour TSP Monitoring Result during the Reporting Month
|
Monitoring Station |
Averaged Measured Value (μg/m3) |
Minimum Measured Value (μg/m3) |
Maximum Measured Value (μg/m3) |
Action Level (μg/m3) |
Limit Level, (μg/m3) |
|
KTN-DMS4(B)(1) |
62 |
44 |
77 |
297 |
500 |
|
FLN-DMS1(1) |
66 |
33 |
93 |
303 |
500 |
|
FLN-DMS5(1) |
54 |
39 |
75 |
279 |
500 |
|
FLN-DMS6(A)(2) |
49 |
15 |
122 |
286 |
500 |
(1) The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.
(2) The air quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the reporting period.
Table 2.7 Summary Table of 24-hour TSP Monitoring Result during the Reporting Month
|
Monitoring Station |
Averaged Measured Value (μg/m3) |
Minimum Measured Value (μg/m3) |
Maximum Measured Value (μg/m3) |
Action Level (μg/m3) |
Limit Level, (μg/m3) |
|
KTN-DMS4(B)(1) |
64 |
48 |
71 |
192 |
260 |
|
FLN-DMS1(1) |
50 |
13 |
96 |
150 |
260 |
|
FLN-DMS5(A) (1) |
69 |
51 |
87 |
153 |
260 |
|
FLN-DMS6(A)(2) |
23 |
14 |
39 |
157 |
260 |
Remark:
(1) The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.
(2) The air quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the reporting period.
Table 3.1 Construction Noise Monitoring Stations near in related to the Works Contracts in the Reporting period
|
Monitoring Station(s) |
Works Contract(s) |
NSR EIA ID(s) |
Location(s) |
Planned(2) Or Existing |
Type of Measurement |
|
CP-KTN-NMS1 |
ND/2024/01 |
CP-NMS1 |
Residential Building at Ma Tso Lung |
Existing |
Free-Field(1) |
|
CP-KTN-NMS2 |
ND/2024/01 |
CP-NMS2 |
Residential Building at Ma Tso Lung |
Existing |
Free-Field(1) |
|
CP-KTN-NMS3 |
ND/2024/01 |
CP-NMS3 |
Fung Kong Garden |
Existing |
|
|
CP-KTN-NMS4(3) |
ND/2024/01, ND/2024/03 |
CP-NMS5 |
Primary School |
Planned |
|
|
CP-KTN-NMS5 |
ND/2024/06 |
CP-NMS7 |
N/A |
Planned |
Free-Field(1) |
|
CP-KTN-NMS6 |
ND/2024/01 |
N/A |
Ho Sheung Heung, Hau Ku ShekAncestral Hall, Hung Shing Temple & Pai Fung Temple and Sin Wai Nunnery |
Existing |
Faηade |
|
CP-KTN-NMS7 |
ND/2024/01 |
CP-NMS4 |
Oi Lok Home |
Existing |
Free-Field(1) |
|
CP-FLN-NMS4(A)(4) |
ND/2024/04 |
CP-NMS6 |
Choi Ying House, Choi Po Court (Choi Yuen Estate) |
Existing |
Free-Field(1) |
|
CP-FLN-NMS1 |
ND/2024/06, ND/2024/07 |
CP-NMS10 |
Belair Monte |
Existing |
Facade |
|
CP-FLN-NMS3(3) |
ND/2024/06, ND/2024/07 |
CP-NMS12 |
Secondary School |
Planned |
Free-Field(1) |
|
CP-FLN-NMS5 |
ND/2024/07 |
CP-NMS8 |
Man Kok Village |
Existing |
Free-Field(1) |
|
CP-FLN-NMS6 |
ND/2024/07 |
CP-NMS9 |
Woodland Crest |
Existing |
Faηade |
Remarks:
(1) For Free Field measurement, +3 dB(A) should be added to the measured results.
(2) Impact monitoring will be carried out when the planned sensitive receivers are commissioned.
(3) As confirmed with Engineer Representative, the planned school at CP-KTN-NMS4 and CP-FLN-NMS3 are not constructed yet. Thus, the impact noise monitoring will be carried out at monitoring station CP-KTN-NMS4 and CP-FLN-NMS3 after the construction and occupation of the planned school. No noise monitoring of the mentioned station was carried out in this reporting period.
(4) Alternative monitoring stations to the corresponding original monitoring stations.
Table 3.2 Construction Noise Monitoring Parameter, Frequency and Duration
|
Monitoring Station |
Parameter |
Frequency and Duration |
|
CP-KTN-NMS1(2), CP-KTN-NMS2(1), CP-KTN-NMS3(1), CP-KTN-NMS5(1), CP-KTN-NMS6(1),CP-KTN-NMS7(2),CP-FLN-NMS1(1), CP-FLN-NMS4(A)(2), CP-FLN-NMS5(2), CP-FLN-NMS6(2) |
Leq(30mins), L10 and L90 (as six consecutive Leq,5min readings) |
Once every week throughout the construction phase |
Remark:
(1) The noise monitoring was conducted by First Phase ET during the reporting period.
(2) The noise monitoring was conducted by Remaining Phase Environmental Team during the reporting period.
· For faηade measurement, the monitoring station was set at a point 1 m from the exterior of the sensitive receivers building faηade and set at a position 1.2 m above the ground. For free-field measurement, the monitoring station was set at a position 1.2 m above the ground.
· The battery condition was checked to ensure good functioning of the meter.
· Parameters such as frequency weighting, the time weighting and the interval were set as follows:
- Frequency weighting: A
- Time weighting: Fast
- Interval: 30 minutes (Leq(30mins))
· Prior to and after each noise measurement, the meter was calibrated using an acoustic calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration level before and after measurement is more than 1.0 dB, the measurement was considered invalid and repeat of noise measurement will be required after re-calibration or repair the equipment.
· At the end of the monitoring period, the values of Leq, L10 and L90 were recorded. In addition, noise sources were recorded on a standard record sheet.
Table 3.3 Construction Noise Monitoring Equipment
|
Equipment |
Manufacturer |
Model |
No. of Equipment |
Serial No. |
|
|
Sound Level Meter |
NTi Audio(2) |
XL2 |
1 |
A2A-17638-E0
A3A-01230-F0 A3A-01235-F0 |
|
|
XL3 |
2 |
||||
|
BSWA(1) |
BSWA 308 |
4 |
580005 580007 580008 580013 |
||
|
|
|||||
|
Acoustic Calibrator |
RION(2) |
NC-75 |
3 |
34724244 34724245 35124529 |
|
|
SVANTEK(1) |
SV30A |
2 |
24803 24780 |
Remark:
(1) The noise monitoring equipment was used by First Phase ET during the reporting period.
(2) The noise monitoring equipment was used by Remaining Phase Environmental Team during the reporting period.
· The microphone head of the sound level meter and calibrator were regularly cleaned with a soft cloth;
· The sound level meter and acoustic calibrator were calibrated annually; and
· The accuracy of the sound level meter was checked using an acoustic calibrator generating a known sound pressure level at a known frequency immediately prior to and following each noise measurement. Measurements were accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.
Table 3.4 Action and Limit Levels for Construction Noise Monitoring
|
Time Period |
Action |
Limit Level |
|
07:00 19:00 on normal weekdays |
When one or more documented complaints are received |
75 dB(A) |
Table 3.5 Summary of Construction Noise Monitoring Results during the Reporting Month
|
Works Contracts |
Monitoring Stations |
Noise Levels, Leq(30min), dB(A) |
Baseline Levels, dB(A) |
Limit Levels, dB(A) |
|
ND/2024/01 |
CP-KTN-NMS1(1)(3) |
54.9 61.7 |
65.7 |
75 |
|
CP-KTN-NMS2(1)(2) |
56.2 63.4 |
58.6 |
||
|
CP-KTN-NMS3(1)(2) |
52.3 59.2 |
51.6 |
||
|
CP-KTN-NMS6(2) |
60.0 64.0 |
55.1 |
||
|
CP-KTN-NMS7(1)(3) |
62.8 68.8 |
65.3 |
||
|
ND/2024/04 |
CP-FLN-NMS4(A)(1)(3)(4) |
69.1 74.6 |
72.0 |
|
|
ND/2024/06 |
CP-KTN-NMS5(1)(2) |
57.9 64.2 |
57.2 |
|
|
ND/2024/06, ND/2024/07 |
CP-FLN-NMS1(2) |
63.8 69.2 |
69.9 |
|
|
ND/2024/07 |
CP-FLN-NMS5(1)(3) |
66.5 67.9 |
69.7 |
|
|
CP-FLN-NMS6(3) |
52.5 58.1 |
54.9 |
Remarks:
(1) For Free Field measurement, +3 dB(A) was added to the measured results.
(2) The noise monitoring was conducted by First Phase ET during the reporting period.
(3) The noise monitoring was conducted by Remaining Phase Environmental Team during the reporting period.
(4) Alternative monitoring stations to the corresponding original monitoring stations.
Table 3.6 Summary of Observations at Noise Monitoring Stations
|
Works Contracts |
Monitoring Stations |
Location |
Major Noise Sources |
|
|
ND/2024/01 |
CP-KTN-NMS1 |
Residential Building at Ma Tso Lung |
Household noise from nearby village house |
|
|
CP-KTN-NMS2 |
Residential Building at Ma Tso Lung |
Road Traffic Noise, Excavator, Mobile crane |
||
|
CP-KTN-NMS3 |
Fung Kong Garden |
Road Traffic Noise, Excavator, Crane |
||
|
CP-KTN-NMS4 |
Primary School |
N/A(1) |
||
|
CP-KTN-NMS6 |
Ho Sheung Heung, Hau Ku ShekAncestral Hall, Hung Shing Temple & Pai Fung Temple and Sin Wai Nunnery |
Road Traffic Noise, Excavator |
||
|
CP-KTN-NMS7 |
Oi Lok Home |
Road Traffic Noise |
||
|
ND/2024/04 |
CP-FLN-NMS4(A)(2) |
Choi Ying House, Choi Po Court (Choi Yuen Estate) |
Road Traffic Noise |
|
|
ND/2024/06 |
CP-KTN-NMS5 |
N/A |
Road Traffic Noise, Excavator, Train noise |
|
|
ND/2024/06, ND/2024/07 |
CP-FLN-NMS1 |
Belair Monte |
Road Traffic Noise, Excavator, Dump Truck, Crane |
|
|
CP-FLN-NMS3 |
Secondary School |
N/A(1) |
||
|
ND/2024/07 |
CP-FLN-NMS5 |
Man Kok Village |
Road Traffic Noise |
|
|
CP-FLN-NMS6 |
Woodland Crest |
Road Traffic Noise |
||
Remarks:
(1) No impact noise monitoring was carried out at the monitoring station. Thus, not applicable (N/A).
(2) Alternative monitoring stations to the corresponding original monitoring stations.
Table 4.1 Summary of Water Quality Monitoring Locations
|
New Monitoring Station(s) |
Original Monitoring Station ID(s) |
Description |
Location(s) |
Measurement Period |
|
KTN NDA |
||||
|
KTN-CS1 |
CS1 |
Control Station for KTN NDA |
Centreline of river, upstream of the channel |
During construction of channel |
|
KTN-IS1 |
IS1 |
Impact Station for KTN NDA |
Centreline of river, downstream of the channel |
During construction of channel |
|
FLN NDA |
||||
|
FLN-CS1 |
CS2 |
Control Station for FLN NDA |
Centreline of river, upstream of the channel |
During construction of channel |
|
FLN-IS1 |
IS2 |
Impact Station for FLN NDA |
Centreline of river, downstream of the channel |
During construction of channel |
Table 5.1 Summary of Waste Generated by the Construction Works from Works Contracts in the Reporting Period
|
Works Contract(s) |
Month |
Actual Quantalities of Inert C&D Materials Generated Monthly |
Actual Quantities of C&D Wastes Generated Monthly |
||||||||||
|
Total Quantity Generated |
Hard Rock and Lage Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
Metals |
Paper / Carboard Packing |
Plastics |
Chemical Waste |
Yard Waste recycled in Shredding Facility |
Others e.g., general refuse |
||
|
(in 000m3) |
(in 000m3) |
(in 000m3) |
(in 000m3) |
(in 000m3) |
(in 000m3) |
(in 000kg) |
(in 000kg) |
(in 000kg) |
(in 000kg) |
(in 000kg) |
(in 000m3) |
||
|
ND/2024/01 |
August 2025 |
3.754 |
0.000 |
0.000 |
3.126 |
0.628 |
2.921 |
0.001 |
0.038 |
0.000 |
283.500 |
0.000 |
0.398 |
|
ND/2024/03 |
August 2025 |
0.201 |
0.000 |
0.000 |
0.000 |
0.201 |
0.000 |
113.130 |
0.000 |
0.000 |
0.000 |
0.000 |
1.001 |
|
ND/2024/04 |
August 2025 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
0.018 |
0.000 |
0.000 |
0.000 |
0.000 |
37.200 |
0.078 |
|
ND/2024/06 |
August 2025 |
19.835 |
3.080 |
1.322 |
9.125 |
9.388 |
0.000 |
0.008 |
0.030 |
0.005 |
1.000 |
0.000 |
0.108 |
|
ND/2024/07 |
August 2025 |
15.199 |
0.000 |
4.363 |
0.000 |
0.000 |
10.258 |
0.000 |
0.000 |
0.000 |
0.000 |
0.006 |
0.642 |
Table 6.1 Summary of Monitoring Activities, Relevant Contracts, and Corresponding Transects
|
Monitoring Activity |
Relevant Works Contract(s) |
Relevant Transect(s)/Monitoring Station(s) |
|
|
First Phase ET |
Remaining Phase ET |
||
|
Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung, Sheung Yue, and Shek Sheung Rivers and Long Valley |
ND/2024/01* |
T1, T2, T3, T5 |
- |
|
ND/2024/02 |
T1, T2, T3, T5 |
T4 |
|
|
ND/2024/03* |
T1, T2, T3, T5 |
- |
|
|
ND/2024/04* |
- |
T4 |
|
|
ND/2024/05 |
N/A(1) |
N/A(1) |
|
|
ND/2024/06* |
T1, T2, T3 |
- |
|
|
ND/2024/07* |
T1, T2, T3 |
T4 |
|
|
ND/2024/08 |
T1, T2, T3 |
T4 |
|
|
Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream, and Long Valley |
ND/2024/01*^ |
MS_01, MS_02, MS_03, MS_04, MS_05, MS_06, MS_07, MS_08, MS_09, MS_10 |
- |
|
ND/2024/02 |
MS_01, MS_02, MS_03, MS_04, MS_05, MS_06, MS_07, MS_08, MS_09, MS_10 |
- |
|
|
ND/2024/03* |
N/A(2) |
N/A(2) |
|
|
ND/2024/04* |
N/A(2) |
N/A(2) |
|
|
ND/2024/05 |
N/A(2) |
N/A(2) |
|
|
ND/2024/06* |
N/A(2) |
N/A(2) |
|
|
ND/2024/07*^ |
MS_11, MS_12, MS_13, MS_14, MS_15 |
- |
|
|
ND/2024/08 |
MS_11, MS_12, MS_13, MS_14, MS_15 |
N/A(2) |
|
|
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution |
ND/2024/01* |
T1 |
- |
|
ND/2024/02 |
T1, T6 |
- |
|
|
ND/2024/03* |
T4 |
- |
|
|
ND/2024/04* |
N/A(3) |
N/A(3) |
|
|
ND/2024/05 |
T4, T6 |
- |
|
|
ND/2024/06* |
- |
T2 |
|
|
ND/2024/07* |
T3 |
- |
|
|
ND/2024/08 |
T3 |
- |
|
Remarks:
(1) Contracts that are located relatively far from river channels.
(2) Contracts that are located relatively far from Ma Tso Lung and Siu Hang San Tsuen streams.
(3) Contracts that are located relatively far from the Ecological Sensitive Habitats as identified in the EIA.
(4) * = active works contracts (ND/2024/01, ND/2024/03, ND/2024/04, ND/2024/06 and ND/2024/07); ^ = monitoring only in April October.
Monitoring Methodology
Monitoring Parameters
· Abundance of birds;
· Types of habitats utilized by birds; and
· Notable bird behaviours such as roosting, feeding, nesting and presence of juveniles.
Monitoring Location
Table 6.2 Summary of Active Works Contracts and Corresponding Transects
|
Monitoring Transect(s) |
Relevant Works Contract(s) |
||||
|
ND/2024/01 |
ND/2024/03 |
ND/2024/04 |
ND/2024/06 |
ND/2024/07 |
|
|
T1. Ng Tung River |
✓ |
✓ |
|
✓ |
✓ |
|
T2. Ng Tung River |
✓ |
✓ |
|
✓ |
✓ |
|
T3. Sheung Yue River |
✓ |
✓ |
|
✓ |
✓ |
|
T4. Shek Sheung River |
|
|
✓ |
|
✓ |
|
T5. Long Valley |
✓ |
✓ |
|
|
|
Monitoring Frequency
Table 6.3 Monitoring Programme for Waterbirds Monitoring, August 2025
|
Week |
Date |
Transect(1) |
|
1 |
4 August |
T4 |
|
7 August |
T3, T5 |
|
|
8 August |
T1, T2, T4 |
|
|
2 |
12 August |
T4 |
|
14 August |
T1, T2 |
|
|
15 August |
T3, T4, T5 |
|
|
3 |
19 August |
T1, T2 |
|
20 August |
T4 |
|
|
21 August |
T3, T5 |
|
|
22 August |
T4 |
|
|
4 |
25 August |
T4 |
|
26 August |
T1, T2 |
|
|
28 August |
T4 |
|
|
29 August |
T3, T5 |
Remarks:
(1) Transects T1, T2, T3, and T5 are relevant to Works Contract ND/2024/01 and ND/2024/03; Transect T4 is relevant to Works Contract ND/2024/04; Transects T1, T2, and T3 are relevant to Works Contract ND/2024/06; Transects T1, T2, T3 and T4 are relevant to Works Contract ND/2024/07.
Monitoring Results
Table 6.4 Summary Table of Waterbird Monitoring Results Relative to Corresponding Action and Limit Levels, August, Transects T1, T2, T3, T4 and T5
|
Monitoring Parameter |
Result in Reporting
Month |
Baseline Level in
Corresponding Month |
Action |
Limit |
|
|
T1, T2 and T3 |
|||||
|
Mean abundance of large waterbirds using Ng Tung River, Sheung Yue River and Shek Sheung River (3) |
73 |
17 |
12 |
8 |
|
|
Mean abundance of Chinese Pond Heron using Ng Tung River, Sheung Yue River and Shek Sheung River |
20 |
13 |
9 |
7 |
|
|
T4 |
|||||
|
Mean abundance of large waterbirds using Shek Sheung River (3) |
6 |
5 |
4 |
3 |
|
|
Mean abundance of Chinese Pond Heron using Shek Sheung River |
4 |
4 |
3 |
2 |
|
|
T5 Long Valley |
|||||
|
Mean Abundance of birds (all species) recorded in LVNP |
527 |
592 |
414 |
296 |
|
|
Mean abundance of the Chinese Pond Heron |
20 |
27 |
19 |
13 |
|
|
Environmental disturbance and damage from activities in LVNP |
- |
- |
Activity likely to cause unacceptable environmental disturbance or damage noted in LVNP. |
Activity likely to cause unacceptable environmental disturbance or damage noted in LVNP. |
|
Remarks:
(1) Exceedance of Action Level occurs when the monitoring result is lower than the Action Level.
(2) Exceedance of Limit Level occurs when the monitoring result is lower than the Limit Level.
(3) Large waterbird species for mean abundance calculation include Great Cormorant (Phalacrocorax carbo); Grey Heron (Ardea cinerea); Great Egret (Ardea alba); Intermediate Egret (Ardea intermedia); Little Egret (Egretta garzetta) and Chinese Egret (Egretta eulophotes).
Monitoring Methodology
Monitoring Parameters
· Species composition and abundance;
· Distribution of invertebrates and fish fauna; and
· Specify species of conservation importance, if any.
Monitoring Locations
|
· MS_01 |
· MS_02 |
· MS_03 |
· MS_04 |
· MS_05 |
|
· MS_06 |
· MS_07 |
· MS_08 |
· MS_09 |
· MS_10 |
And the relevant monitoring stations for Works Contract ND/2024/07 are:
|
· MS_11 |
· MS_12 |
· MS_13 |
· MS_14 |
· MS_15 |
Monitoring Frequency
Monitoring Results
Table 6.5 Summary Table of Monitoring Results for Aquatic Invertebrates Relative to Action and Limit Levels, August, Monitoring Station MS_01 MS_15
|
Monitoring Station |
Result in Reporting Month (August 2025) (1) |
Baseline Level in Corresponding Month (August 2019) (1) |
Action Level(2) |
Limit Level(3) |
|
MS_01 |
0 |
0 |
N/A |
N/A |
|
MS_02 and MS_03 |
4 |
1 |
N/A |
N/A |
|
MS_04, MS_06 and MS_07 |
4 |
1 |
N/A |
N/A |
|
MS_05 |
0 |
0 |
N/A |
N/A |
|
MS_08, MS_09 and MS_10 |
5 |
0 |
N/A |
N/A |
|
MS_11 |
1 |
1 |
N/A |
N/A |
|
MS_12 |
1 |
0 |
N/A |
N/A |
|
MS_13 and MS_14 |
3 |
1 |
N/A |
N/A |
|
MS_15 |
1 |
0 |
N/A |
N/A |
Remarks:
(1) Number of native species (species richness) recorded.
(2) Exceedance of Action Level occurs when the monitoring result is lower than the Action Level.
(3) Exceedance of Limit Level occurs when the monitoring result is lower than the Limit Level.
Table 6.6 Summary Table of Monitoring Results for Fish Species Relative to Action and Limit Levels, August, Monitoring Station MS_01 MS_15
|
Monitoring Station |
Result in Reporting Month (August 2025) (1) |
Baseline Level in Corresponding Month (August 2019) (1) |
Action Level(2) |
Limit Level(3) |
|
MS_01 |
0 |
0 |
N/A |
N/A |
|
MS_02 and MS_03 |
0 |
1 |
N/A |
N/A |
|
MS_04, MS_06 and MS_07 |
1 |
1 |
N/A |
N/A |
|
MS_05 |
0 |
0 |
N/A |
N/A |
|
MS_08, MS_09 and MS_10 |
1 |
1 |
N/A |
N/A |
|
MS_11 |
0 |
0 |
N/A |
N/A |
|
MS_12 |
0 |
0 |
N/A |
N/A |
|
MS_13 and MS_14 |
0 |
0 |
N/A |
N/A |
|
MS_15 |
1 |
2 |
N/A |
1 |
Remarks:
(1) Number of native species (species richness) recorded.
(2) Exceedance of Action Level occurs when the monitoring result is lower than the Action Level.
(3) Exceedance of Limit Level occurs when the monitoring result is lower than the Limit Level.
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance
Monitoring Methodology
Terrestrial Mammal
Herpetofauna (Amphibians and Reptiles)
Butterfly and Odonates
Monitoring Parameters
· Species composition;
· Abundance;
· Distribution for fauna observed; and
· Species of conservation importance would be specified.
Monitoring Location
· T1. Ma Tso Lung riparian zone and associated wetland habitats; green belt areas E1-8, D1-8 and G1-3 in KTN NDA; AGR zone C2-4 and C2-2 in KTN NDA, and area north of Ng Tung River;
· T2. Fanling North Freshwater Service Reservoir
· T3. Area west of Siu Hang San Tsuen Stream;
· T4. South side of Fanling Highway and Castle Peak Road in the vicinity of Pak Shek Au;
· T5. Area west and east of the southern limit of the FLN NDA work area; and
· T6. Areas in the western part of KTN.
Monitoring Frequency
|
Responsible ET |
Date |
Transect(1) |
|
|
First Phase ET |
19 August |
T1 |
|
|
12 August |
T3 |
||
|
12 August |
T4 |
||
|
Remaining Phase ET |
27 August |
T2 |
|
Remarks:
(1) Transect T1 is relevant to Works Contract ND/2024/01; Transect T2 is relevant to Works Contract ND/2024/06; Transect T3 is relevant to Works Contract ND/2024/07; Transect T4 is relevant to Works Contract ND/2024/03.
Monitoring Results
Terrestrial Mammals
Herpetofauna (Amphibians and Reptiles)
Butterfly and Odonates
Summary of Monitoring Results
Table 6.8 Summary Table of Monitoring Results for Non-aquatic Fauna Relative to Action and Limit Levels, August, Transect T1, T2, T3 and T4
|
Monitoring Parameter |
Result in Reporting Month (August 2025) (1) |
Baseline Level in Corresponding Month (August 2019) (1) |
Action Level(2) |
Limit Level(3) |
|
T1 |
||||
|
Terrestrial Mammals |
1 |
2 |
N/A |
1 |
|
Herpetofauna |
8 |
9 |
6 |
5 |
|
Odonates |
8 |
17 |
12 |
9 |
|
Butterflies |
21 |
23 |
16 |
12 |
|
T2 |
||||
|
Terrestrial Mammals |
6 |
1 |
N/A |
N/A |
|
Herpetofauna |
8 |
4 |
3 |
2 |
|
Odonates |
4 |
5 |
4 |
3 |
|
Butterflies |
17 |
17 |
12 |
9 |
|
T3 |
||||
|
Terrestrial Mammals |
1 |
1 |
N/A |
N/A |
|
Herpetofauna |
5 |
7 |
5 |
4 |
|
Odonates |
2 |
13 |
9 |
7 |
|
Butterflies |
11 |
10 |
7 |
5 |
|
T4 |
||||
|
Terrestrial Mammals |
1 |
1 |
N/A |
N/A |
|
Herpetofauna |
4 |
6 |
4 |
3 |
|
Odonates |
6 |
2 |
N/A |
1 |
|
Butterflies |
17 |
13 |
9 |
7 |
Remarks:
(1) Number of species (species richness) recorded; the results in the reporting month for terrestrial mammals, herpetofauna and odonates are calculated based on the number of native species recorded along the transects.
(2) Exceedance of Action Level occurs when the monitoring result is lower than the Action Level.
(3) Exceedance of Limit Level occurs when the monitoring result is lower than the Limit Level.
Details of the Influencing Factors
Survey Summary
· Compendium Method 1O-3.1 Selection, Preparation and Extraction of Filter Material, Center for Environmental Research Information, Office of Research and Development, USEPA, June 1999; and Compendium Method 1O-3.5 determination of Metals in Ambient Particulate Matter using Inductively Coupled Plasma/Mass Spectrometry (ICP/MS., Center for Environmental Research Information, Office of Research and Development, USEPA, June 1999.
Table 8.1 Location of Ambient Arsenic Monitoring station
|
Monitoring Station(s) |
Location(s) |
Works Contract(s) |
|
KTN-DMS-4A(1)(2) |
Temporary Structure at Pak Shek Au |
ND/2024/01 |
Remarks:
(1) Monitoring at the original location of KTN-DMS-4 (originally proposed in the approved EM&A Manual) was denied as there was no electricity supply. An alternative location (KTN-DMS-4A) was proposed by First Phase ET.
(2) The ambient arsenic monitoring was conducted by First Phase ET during the reporting period.
Table 8.2 Ambient Arsenic Monitoring Equipment
|
Monitoring Station |
Equipment |
Manufacturer |
Model |
No. of Equipment |
|
KTN-DMS-4A(1)(2) |
Calibrator |
TISCH |
TE-5025A |
1 |
|
HVS Sampler (RSP) |
TISCH |
TE-6070X |
1 |
Remarks:
(1) Monitoring at the original location of KTN-DMS-4 (originally proposed in the approved EM&A Manual) was denied as there was no electricity supply. An alternative location (KTN-DMS-4A) was proposed by First Phase ET.
(2) The ambient arsenic monitoring was conducted by First Phase ET during the reporting period.
Table 8.3 Impact Ambient Arsenic Monitoring Parameters, Frequency and Duration
|
Parameters |
Frequency(1) |
|
24-hr RSP (Ambient Arsenic) |
Once/ 6 days |
Remark:
1. The ambient arsenic monitoring was conducted by First Phase ET during the reporting period.
Instrumentation
· a horizontal platform with appropriate support to secure the samplers against gusty wind was provided;
· no two samplers was placed less than 2 meters apart;
· the distance between the sampler and an obstacle, such as buildings, was at least twice the height that the obstacle protrudes above the sampler;
· a minimum of 2 meters of separation from walls, parapets and penthouses was required for rooftop samplers;
· a minimum of 2 meters separation from any supporting structure, measured horizontally was required;
· no furnace or incinerator flue was nearby;
· airflow around the sampler was unrestricted;
· the sampler was more than 20 meters from the dripline;
· any wire fence and gate, to protect the sampler, were not cause any obstruction during monitoring;
· permission was obtained to set up the samplers and to obtain access to the monitoring stations; and
· a secured supply of electricity was needed to operate the samplers
Operating/analytical procedures for the operation of HVS
·
Prior to the commencement of the dust sampling, the flow rate of the high volume sampler was properly set (between 1.1 m3 /min.
and 1.4 m3 /min.) in accordance with the manufacturer's instruction to within
the range recommended in USEPA Standard Title 40, CFR Part 50;
· The
power supply was checked to ensure the sampler worked properly. On sampling,
the sampler was operated for 5 minutes to establish thermal equilibrium before
placing any filter media at the designated air monitoring station;
· The filter holding frame was then removed by
loosening the four nuts and a weighted and conditioned filter was carefully centered with the stamped number upwards, on a supporting screen;
· The filter was aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter. The filter holding frame was then tightened to the filter holder with swing bolts. The applied pressure was sufficient to avoid air leakage at the edges;
· The shelter lid was closed and secured with the aluminum strip;
· The timer was then programmed. Information was recorded on the record sheet, which included the starting time, the weather condition and the filter number (the initial weight of the filter paper can be found out by using the filter number);
· After sampling, the filter was removed and sent to the Wellab Ltd. for weighing. The elapsed time was also recorded; and
· Before weighing, all filters were equilibrated in a conditioning environment for 24 hours. The conditioning environment temperature was between 25°C and 30°C and did not vary by more than ±3°C; the relative humidity (RH) was < 50% and did not vary by more than ±5%. A convenient working RH was 40%. Weighing results were further analysis of RSP concentrations collected by each filter.
· The high volume motors and their accessories were properly maintained. Appropriate maintenance such as routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power supply were in good working condition; and
· High volume samplers were calibrated at bi-monthly intervals using TE-5025A Calibration Kit throughout all stages of the ambient arsenic monitoring.
Table 8.4 Result Summary Against Action and Limit Levels for 24-hour RSP Monitoring Results (Ambient Arsenic)
|
Contract No. |
Monitoring Date |
Monitoring Station |
Concentration (ƞg/m3) |
AL (ƞg/m3) |
LL (ƞg/m3) |
|
ND/2024/01 |
06/08/2025 |
KTN-DMS4A* |
3.91 |
9.36 |
11.7 |
|
12/08/2025 |
5.27 |
||||
|
18/08/2025 |
3.68 |
||||
|
22/08/2025 |
5.89 |
||||
|
28/08/2025 |
5.45 |
Remark:
* The 24-hour RSP monitoring for ambient arsenic was conducted by First Phase ET during the reporting period.
Ψ Excavation Locations: N/A
Ψ Manholes and Chambers: N/A
Ψ Relocation of monitoring wells: N/A
Ψ Any other Confined Spaces: N/A
Table 10.1 Site Observations at Works Contract No. ND/2024/01, ND/2024/03, ND/2024/04, ND/2024/06 and ND/2024/07 during the Reporting Period
|
Works Contracts |
Inspection Date |
Key Observations/ Reminders |
Follow-up Action |
|
ND/2024/01 |
06 August 2025 |
Observation:
Nil |
Nil |
|
Reminder:
Nil |
Nil |
||
|
12 August 2025 |
Observation:
Nil |
Nil |
|
|
Reminder:
1. A copy of the Environmental Permit should be displayed on the Project site(s) and other relevant environmental license(s) / permit(s) at all vehicular site entrances/exits or at a convenient location for public information at all times. |
Nil |
||
|
19 August 2025 |
Observation:
1. Proper chemical storage and site practices to minimize the potential for damage and contamination of construction materials at Portion 59. 2. NRMM label should be displayed clearly on the machinery at Portion 59. 3. All drainage facilities and erosion and sediment control structures should be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly following rainstorms at Portion 59. |
1. Chemicals were stored properly at Portion 59. (Rectified on 19 August 2025)
2. NRMM label was displayed clearly at Portion 59. (Rectified on 19 August 2025)
3. Drainage facilities were regularly inspected and maintained at Portion 59. (Rectified on 22 August 2025) |
|
|
Reminder:
Nil |
Nil |
||
|
26 August 2025 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
ND/2024/03 |
04 August 2025 |
Observation:
1. Stagnant water being held inside holes shall be cleared, and the holes should be adequately covered or temporarily sealed so as to avoid stagnant water being accumulated. |
1. Stagnant water being held inside holes were cleared, and the holes were covered or temporarily sealed so as to avoid stagnant water being accumulated. (Rectified on 04 August 2025) |
|
Reminder:
Nil |
Nil |
||
|
12 August 2025 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
18 August 2025 |
Observation:
1. The side edges of the drip tray at Sheung Yue River should be completely sealed to prevent chemicals from spilling and contaminating soil or groundwater at the construction site. |
1. The side edges of the drip tray at Sheung Yue River were completely sealed to prevent chemicals from spilling and contaminating soil or groundwater at the construction site. (Rectified on 18 August 2025) |
|
|
Reminder:
Nil |
Nil |
||
|
25 August 2025 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
ND/2024/04 |
01 August 2025 |
Observation:
Nil |
Nil |
|
Reminder:
Nil |
Nil |
||
|
08 August 2025 |
Observation: Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
13 August 2025 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
22 August 2025 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
29 August 2025 |
Observation:
1. Drip tray should be supplemented for the generator to prevent direct leakage to the soil |
1. Drip tray was supplemented for the generator to prevent direct leakage to the soil (Rectified on 3 September 2025) |
|
|
Reminder:
Nil |
Nil |
||
|
ND/2024/06 |
04 August 2025 |
Observation:
Nil |
Nil |
|
Reminder:
Nil |
Nil |
||
|
11 August 2025 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
18 August 2025 |
Observation:
1. Drip tray should be provided to chemical containers for oil spillage avoidance at Portion D. |
1. Drip tray was provided to chemical containers for oil spillage avoidance at Portion D. (Rectified on 20 August 2025) |
|
|
Reminder:
Nil |
Nil |
||
|
25 August 2025 |
Observation: 1. The Contractor was reminded that NRMM labels shall be affixed to four excavators being utilised in site formation works at Portion A.
|
1. The NRMM label was displayed on the machinery clearly at Portion A. (Rectified on 25 August 2025)
|
|
|
Reminder:
1. The Contractor was reminded to provide watering of optimum amount to haul road at Portion A, especially for the period at which soil will be dried up easily. |
Nil |
||
|
ND/2024/07 |
07 August 2025 |
Observation:
Nil |
Nil |
|
Reminder:
1. Stagnant water should be removed regularly |
Nil |
||
|
15 August 2025 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
21 August 2025 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
28 August 2025 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
Table 10.2 Photographic Records and Implementation Status of Measures
|
Works Contracts |
EP No. |
Photographic Record |
Implementation Status |
|
ND/2024/01 |
EP-467/2013/A
(Condition 2.9) |
To minimise adverse impacts
on habitats of ecological importance in the vicinity of the Project, 2m high
solid dull green site barrier fences shall be erected around all active works
areas. |
^ |
|
EP-468/2013/A (Condition 2.11) |
|||
|
ND/2024/03 |
EP-465/2013/A (Condition 2.9) |
To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas. |
^ |
|
EP-466/2013/A (Condition 2.9) |
|||
|
EP-467/2013/A (Condition 2.11) |
|
Implementation status: |
^ Mitigation measure was fully implemented |
|
* Observation / reminder was made during site audit but improved / rectified by the contractor |
|
|
# Observation / reminder was made during site audit but not yet improved / rectified by the contractor |
|
|
X Non-compliance of mitigation measure |
|
|
Non-compliance but rectified by the contractor |
|
|
|
N/A Not Applicable at this stage as no such site activities were conducted in the reporting period |
· All Site Resumption Area(s)
1. Tree survey
2. Site Clearance
· Portion XI (11), XXIII (23)
1. Asbestos Abatement Works
· Portion XL (40)
1. Excavation, Mixing with General fill & Backfilling
2. Construct Retaining Wall & Backfilling
· Portion LIX (59)
1. Setting Up including T&C of High Arsenic-Containing Soil (HAS) Treatment Plant
Contract No. ND/2024/03
· Portion XVI
1. Site Clearance and Tree Works
2. Watermain and Sewer Pipe Laying
· Portion IX
1. Asbestos Removal Works
· Portion XI
1. Site Clearance and Tree Works
2. Ground Investigation
· TTA stage 1 Works
1. Tree Works
2. Demolish of Central Divider & Barrier
3. Piling Works
· TTA stage 1B
1. Site Clearance
· TTA stage 3
1. Predrilling & Piling Works
· Works Areas WA1, WA2, WA3, WA4 & WA5
1. Site Clearance and Site Formation
2. Hoarding Works
3. Asbestos Removal Works
Contract No. ND/2024/04
· Site Clearance
· Site Establishment
· Tree Felling
· Trial Pit
· Haul Road Construction
· Demolition of Existing Structures
· Existing Sewage Diversion
· Bored Piling
· Ground Investigation
· Pre-drilling
Contract No. ND/2024/06
· Forming Haul Road beside Existing THFWSR For Excavation Works of Portion A;
· Tree falling at Haul Road
· Ground investigation works
· Slope trimming and soil nailing works of cut slope S1 & S2 / access road of Portion A;
· Watermains laying works at Lung Yeuk Tau of Portion F
· Demolition of DN2000 pipes and associated thrust blocks of Portion D
· Watermains laying works at Fu Tei Au Road of Portion D
· Excavation to +102mPD of Portion A
Contract No. ND/2024/07
· Site Clearance
· Site Formation
· Ground Investigation
· Pre-bored Socketed H Pile Construction
· Sheet Piling
· Pile Cap Construction
· Pier Construction
· UU Diversion
· Tree Felling
· Sewerage Construction
· Asbestos Containing Materials Removal
· Asbestos Containing Materials Survey
· Archaeological Impact Assessment
· Land Contamination Investigation
· Internal Movement, Importation & Exportation of C&D materials
Dust
Regular watering to reduce dust emissions from exposed site surface;
Stockpile of dusty materials shall be covered entirely by impervious sheeting;
Provide vehicles washing facilities at all site exits to wash away any dusty materials from vehicle body;
NRMM Labels should be displayed on the applicable equipment on site by the Contractor;
Provision of water sprinklers along the haul road for dust suppression.
Noise
Only well-maintained plant should be operated on-site, and plant should be maintained regularly during the construction programme; and
Quality Powered Mechanical Equipment (QPME) should be adopted as far as possible.
Water Quality
No effluent discharge would be allowed before acquired the effluent discharge license;
Surface run-off from construction sites should be discharged into dedicated discharge point via adequately designed sand/ silt removal facilities;
Channels/ earth bunds/ sandbags barriers should be provided on site to properly direct stormwater to silt removal facilities;
Silt removal facilities, channels and manholes should be maintained, and the deposited silt and grit should be removed regularly;
Open stockpiles of construction materials on sites should be covered with tarpaulin or similar fabric during rainstorms; and
Perimeter channels should be provided on site boundaries where necessary to intercept stormwater run-off from outside the site so that it will not wash across the site.
Waste Management
Provision of sufficient waste disposal points and regular collection of waste;
Regular cleaning and maintenance programme for drainage system; and
Chemical containers shall be stored with drip tray underneath.
Landscape and Visual
Construction activities shall be carefully designed to minimize impact on existing retained trees
Land Contamination
Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be properly covered by impermeable sheeting to reduce dust emission during dry season or contaminated run-off during rainy season. Watering should be avoided on stockpiles of soil to minimise runoff.
Landfill Gas Hazard
No Smoking and No Naked Flame notices in Chinese and English should be posted prominently around the construction site.
Ecology
Properly erect and maintain 2m high solid barriers for protection.