1.3 Construction
Works Programme and Construction Works Area
1.4 Summary
of Environmental Status
2.3 Monitoring
Parameter and Frequency and Duration
2.5 Monitoring
Methodology and QA/QC Procedure. 29
2.6 Action
and Limit Level for Air Quality Monitoring
3 Construction
Noise Monitoring
3.3 Noise
Monitoring Parameter, Frequency and Duration
3.4 Monitoring
Equipment, Methodology and QA / QC Procedure
3.5 Maintenance
and Calibration
8 Land
Contamination (Ambient Arsenic Monitoring)
8.4 Monitoring
Parameters, Frequency and Duration
8.5 Monitoring
Methodology and QA/QC Procedure. 59
8.7 Laboratory
Measurement / Analysis
9.2 Monitoring
Parameters and Frequency
10.3 Monitoring
Parameters and Frequency
11 Environmental Site Inspection and Audit
11.1 Implementation
Status of Environmental Mitigation Measures
12 Summary
of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions
12.2 Summary
of Environmental Non-Compliance. 73
12.3 Summary
of Environmental Complaint
12.4 Summary
of Environmental Summon and Successful Prosecution
13.1 Works
and Potential Environmental Issues in the next Reporting Period
14.2 Comments/
Recommendations
Figures
Figure
1.1 Location and Site Layout
Plan (KTN)
Figure
1.2 Location and Site Layout
Plan (FLN)
Figure 2.1
Location of Air Quality Monitoring Stations for
KTN NDA
Figure
2.2 Location of Air Quality
Monitoring Stations for FLN NDA
Figure
3.1 Location of Noise
Monitoring Stations for KTN NDA
Figure
3.2 Location of Noise
Monitoring Stations for FLN NDA
Figure
8.1 Location of Ambient Arsenic
Monitoring Stations for KTN NDA
Appendix
1.1 Construction Programme
Appendix
1.2 Project Organization Chart
Appendix
1.3 Implementation Status of Environmental Mitigation Measure
Appendix
2.1 Impact Monitoring Schedule during the reporting period
Appendix
2.2 Impact Air Quality Monitoring Data & Graphical
Presentations & Calibration Certificates
Appendix
2.3 Weather Information during the Reporting Period
Appendix
2.4 Event and Action Plan for Construction Dust
Appendix
3.1 Impact Noise Monitoring Data & Graphical
Presentations & Calibration Certificates
Appendix
3.2 Event and Action Plan for Construction Noise
Appendix
5.1 Summary of Monthly Waste Flow Table
Appendix
6.1 Detailed Results of the Ecological Waterbird Monitoring
during this Reporting Period
Appendix
6.2 Detailed Results of the Ecological Non-aquatic Monitoring
during this Reporting Period
Appendix
6.3 Event and Action Plan for Ecological Monitoring
Appendix
7.1 Event and Action Plan for Landscape and Visual
Appendix
8.2 Event and Action Plan for Ambient Arsenic Monitoring
Appendix
12.1 Statistical Summary of Environmental
Complaints, Summons and Prosecution
Appendix
13.1 Impact Monitoring Schedule of Next
Reporting Month
A1. This is the 14th Monthly Environment
Monitoring and Audit (EM&A) Report for Remaining Phase Development of Kwu Tung North and Fanling North
New Development Areas (the Project) for the reporting period between 1 and 28
February 2026. This report was prepared by Aurecon Hong Kong Limited (Aurecon)
under Service Contract No. NDO 05/2024 Remaining Phase Development of Kwu Tung North and Fanling North
New Development Areas - Environmental Team (hereinafter called the Service
Contract).
A2. Since only construction works were undertaken
under Works Contract No. ND/2024/01, Works Contract No. ND/2024/02, Works
Contract No. ND/2024/03, Works Contract No. ND/2024/04, Works Contract No.
ND/2024/06 and Works Contract No. ND/2024/07 during the reporting month, this
report documents the findings of EM&A works at Works Contract No.
ND/2024/01, Works Contract No. ND/2024/02, Works Contract No. ND/2024/03, Works
Contract No. ND/2024/04, Works Contract No. ND/2024/06 and Works Contract
No. ND/2024/07 under the Project during the reporting period only. No
construction works occurred in the remaining contracts during the reporting
period for Works Contract ND/2024/05 and ND/2024/08.
A3. This Project involves eight (8) Environmental
Permits (EPs) (i.e. EP-465/2013/A, EP-466/2013/A, EP-467/2013/A, EP-468/2013/A,
EP-470/2013/A, EP-471/2013/A, EP-472/2013/A and EP-476/2013). Details of each
EPs are summarised in Table A1.
Table A1 Works Contracts under relevant Environmental Permits in the
Reporting Month
|
Environmental Permit No. |
Works Contracts |
Title of Designated Project |
Designated Project (DP) |
|
EP-465/2013/A |
ND/2024/03 |
San Tin Highway and Fanling Highway Kwu Tung Section Widening (Between San Tin Interchange and Po Shek Wu Interchange) |
DP1 |
|
EP-466/2013/A |
ND/2024/03 |
Castle Peak Road Diversion |
DP2 |
|
EP-467/2013/A |
ND/2024/01 |
Kwu Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange Improvement |
DP3 |
|
EP-468/2013/A |
ND/2024/01 |
Kwu Tung North New Development Area Road D1 to D5 |
DP4 |
|
EP-469/2013 |
- |
Sewage Pumping Stations in Kwu Tung North New Development Area |
DP5 |
|
EP-470/2013/A |
ND/2024/06 |
Utilization of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment Works |
DP7 |
|
EP-471/2013/A |
ND/2024/04 |
Po Shek Wu Interchange Improvement |
DP8 |
|
EP-472/2013/A |
ND/2024/08 |
Fanling Bypass Western Section |
DP9 |
|
EP-473/2013/A |
- |
Fanling Bypass Eastern Section |
DP10 |
|
- |
Shek Wu Hui Sewage Treatment Works - Further Expansion at Fanling North New Development Area |
DP11 |
|
|
ND/2024/07 ND/2024/08 |
Sewage Pumping Stations in Fanling North New Development Area (FLNDA) |
DP13 |
A4. Apart from the construction works undertaken
under Works Contract No. ND/2024/01 since 20 January 2025, construction works
under Works Contract No. ND/2024/07 commenced since 27 February 2025,
construction works under Works Contract No. ND/2024/06 commenced since 10 March
2025, construction works under Works Contract No. ND/2024/04 commenced since 10
May 2025, construction works under Works Contract No. ND/2024/03 commenced
since 2 June 2025, construction works under Works Contract No. ND/2024/02 has
also been commenced since 9 February 2026. No construction works occurred in
the remaining Works Contracts (i.e. Works Contract ND/2024/05 and ND/2024/08)
during the reporting period. The commencement dates of each Works Contracts are
summarized in Table A2.
Table A2 Commencement Dates of Each Works Contracts
|
Works Contracts |
Commencement Dates |
|
ND/2024/01 |
20 January 2025 |
|
ND/2024/02 |
9 February 2026 |
|
ND/2024/03 |
2 June 2025 |
|
ND/2024/04 |
10 May 2025 |
|
ND/2024/05 |
Not Yet Commenced |
|
ND/2024/06 |
10 March 2025 |
|
ND/2024/07 |
27 February 2025 |
|
ND/2024/08 |
March 2026 (Tentative) |
A5. A summary of construction activities undertaken
during the reporting period is presented below:
Works
Contract No. ND/2024/01:
· All Site
Resumption Area(s)
1. Tree
survey
2. Site
Clearance
· Portion
III (3), IV (4), V (5), VII (7) and XXXV (35)
1. Site
Clearance & Demolition
2. Asbestos
Abatement Works
3. Construction
of Temporary Drainage Diversion
· Portion
VIII (8)
1. Site
Clearance & Demolition
2. Asbestos
Abatement Works
· Portion VI (6), XVIII (18), XXXVIII (38)
1. Site Clearance
2. Excavation works
· Portion
XI (11), XXIII (23)
1. Formwork
Erection, Rebar Fixing, Concreting Works
· Portion
XL (40)
1. Retaining Wall Construction
2. Drainages System Construction
3. ELS work
· Portion
LIX (59)
1. Treatment
of High Arsenic-Containing Soil (HAS)
· Portion
XVII (17), XVII (18), XXI (21), XXXIV (34), XXXV (35), XLI (41), XLII (42)
1. Excavation
works
2. Drainage
Pipe Installation
Works Contract No. ND/2024/02:
· Site
clearance in Area B, D, L
· Site
formation works in Area D
· Temporary
storage fill bank in Kwu Tung Grass Soccer Pitch
Works
Contract No. ND/2024/03:
Fanling Highway & Castle Peak Road area
· Pak Sau
Road Po Lau Road
1. Relocation/Reprovision/Removal
of Existing TCSS, Fire Hydrant, Signage & Streetlighting
2. Tree
Works
· Po Lau
Road Sheung Yue River
1. Asbestos
Removal Works at Portion IX
2. Box
Culvert Bay 37 Bay 42 ELS
· TTA Stage
1 Works
1. Tree
Works
2. Removal
or relocation of directly impacted Shrine/historical building at HKT08 &
KT72
3. Demolish
of Central Divider & Barrier along FL Highway E/B
· Box
culvert Bay 10 to 12, 14 to 16 Drainage/Watermains
1. Drainage,
Sewerage & Watermain with Backfilling at Box Culvert Bay 15 & 16
2. Box
Culvert Bay 14 ELS
· Box
culvert Bay 17 to 19 & Drainage/Watermains
1. Box
Culvert Bay 17 to 19 ELS, Base Slab, Wall and Top Slab
· Retaining
Wall RW05A
1. RW05A
ELS
· Kwu Tung Road Bridge
1.
Site Clearance and Tree Works
2. Site
formation and cutback the existing slope
3. Predrilling
4. Foundation
& Piling
· Works
Areas WA1, WA2, WA3, WA4 & WA5
1. Site
Clearance and Site Formation at PMs Site Office
2. Temporary
Drainage
3. Asbestos
removal
Fanling Highway Cross River Bridge (along Sheung Yue
River)
· Portion
XI East Abutment & pier foundation
1. Trial
Pits for UUs
2. Piling
Works
1. Piling
Works
2. Pile
Cap L3A-02
· Kwu Tung Interchange Foundation & Substructure
- Bridge B1 & C1
1. Piling
Works
Works Contract No. ND/2024/04:
1.
Site Clearance
2.
Site Establishment
3.
Tree Felling
4.
Trial Pit
5.
Pre-drilling
6.
Ground Investigation
7.
Existing Sewage Diversion
8.
Demolition of Existing Structures
9.
Bored Piling
10.Sheet Piling
11.Soil Nailing
12.Shotcreting
Works Contract No. ND/2024/06:
· Portion A
1.
Excavation to +95 mPD of Portion A
2.
Forming Haul Road from Area C to
Portion A
· Portion C
1.
Trench and Watermains Laying Works
of Portion C
· Portion D
1.
Trench and Watermains Laying Works
of Portion D
2.
Demolition of DN2000 Pipes and
Associated Thrust Block of Portion D
· Portion E
& F
1. Trench
and Watermains of Portion E & F
Works Contract No. ND/2024/07:
1. Site Clearance
2. Site Formation
3. Pier Construction
4. Lift Tower Construction
5. Steel Works
6. ABWF Works
7. Drainage Construction
8. Storm Pipe Construction
9. Assembly Yard for Bridge
10.Storage Yard for Concrete Pipe
11.Rebar Yard
12.Sewage Construction
13.New Shine Construction
14.Improvement of Junction
15.Road Improvement
16.Temporary Road Construction
17.Asbestos Containing Materials Survey & Removal
18.Internal Movement / Importation & Exportation of C&D
materials
Works
Contract No. ND/2024/05 and ND/2024/08:
1.
No construction work during the
reporting period.
A6. The environmental monitoring activities,
including 1-hour Total Suspended Particulates (TSP) monitoring, 24-hour TSP
monitoring, noise monitoring, ecological survey, 24-hour Respirable Suspended
Particulates (RSP) (Ambient Arsenic) monitoring for land contamination and
environmental site inspection, were undertaken by Environmental Team (ET) under
Service Contract No. NDO 04/2019 (i.e. First Phase ET Wellab)
and under Service Contract No. NDO 05/2024 (i.e. Remaining Phase ET - Aurecon)
during the reporting period in accordance with the approved Updated EM&A
Manual. A summary of the monitoring and audit activities during the reporting
period is presented in Table A3.
Table A3 Summary of EM&A Activities in the Reporting Period
|
EM&A |
Monitoring Station(s) |
Works Contract(s)(5) |
|||||||
|
ND/2024/01 |
ND/2024/02 |
ND/2024/03 |
ND/2024/04 |
ND/2024/05 |
ND/2024/06 |
ND/2024/07 |
ND/2024/08 |
||
|
1-hour TSP Monitoring(1) |
KTN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS4(B)(2)(3) |
3, 9, 14, 20, 25 February 2026 |
N/A |
3, 9, 14, 20, 25 February 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
4, 10, 16, 21, 26 February 2026 |
N/A |
|
|
FLN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
3, 9, 14, 20, 25 February 2026 |
N/A |
|
|
FLN-DMS6(A)(2)(3) |
N/A |
N/A |
2, 7, 13,16, 21, 27 February 2026(6) |
N/A |
N/A |
N/A |
N/A |
||
|
FLN-DMS7(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
24-hour TSP Monitoring(1) |
KTN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS4(B)(2)(3) |
3, 9, 14, 20, 25 February 2026 |
N/A |
3, 9, 14, 20, 25 February 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
3, 9, 14, 20, 25 February 2026 |
N/A |
|
|
FLN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS5(A)(2)(3) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
3, 9, 14, 20, 25 February 2026 |
N/A |
|
|
FLN-DMS6(A)(2)(3) |
N/A |
N/A |
2, 7, 13,16, 21, 27 February 2026(6) |
N/A |
N/A |
N/A |
N/A |
||
|
FLN-DMS7(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Noise Monitoring(1) |
CP-KTN-NMS1(2) |
2, 13, 16, 27 February 2026(6) |
2, 13, 16, 27 February 2026(6) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
CP-KTN-NMS2(2) |
3, 9, 20, 25 February 2026 |
3, 9, 20, 25 February 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS3(2) |
3, 9, 20, 25 February 2026 |
3, 9, 20, 25 February 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
3, 9, 20, 25 February 2026 |
N/A |
N/A |
|
|
CP-KTN-NMS6(2) |
3, 9, 20, 25 February 2026 |
3, 9, 20, 25 February 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS7(2) |
2, 13, 16, 27 February 2026(6) |
2, 13, 16, 27 February 2026(6) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
4, 10, 16, 26 February 2026 |
N/A |
||
|
CP-FLN-NMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS4(A)(2)(3) |
N/A |
N/A |
N/A |
4, 10, 21, 23 February 2026(6) |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
4, 10, 21, 23 February 2026(6) |
N/A |
|
|
CP-FLN-NMS6(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
4, 10, 21, 23 February 2026(6) |
N/A |
|
|
Ecological Monitoring (4) |
Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley |
Weekly Monitoring: 3, 5, 10, 12, 16, 20, 24, 26 February 2026 (Transect T1, T2, T3 and T5)
|
Weekly Monitoring: 2, 3, 5, 10, 12, 16, 20, 24, 26 February 2026 (Transect T1, T2, T3, T4 and T5)
|
Weekly Monitoring: 3, 5, 10, 12, 16, 20, 24, 26 February 2026 (Transect T1, T2, T3 and T5)
|
Weekly Monitoring: 2, 5, 10, 12, 16, 20, 24, 26 February 2026 (Transect T4) |
N/A |
Weekly Monitoring: 3, 5, 10, 12, 16, 20, 24, 26 February 2026 (Transect T1, T2, T3 and T5)
|
Weekly Monitoring: 2, 3, 5, 10, 12, 16, 20, 24, 26 February 2026 (Transect T1, T2, T3 and T4) |
Weekly Monitoring: 2, 3, 5, 10, 12, 16, 20, 24, 26 February 2026 (Transect T1, T2, T3 and T4) |
|
Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution |
Monthly Monitoring: 25 February 2026 (Transect T1) |
Monthly Monitoring: 25 February 2026 (Transect T1 and T6) |
Monthly Monitoring: 9 February 2026 (Transect T4) |
N/A |
N/A |
Monthly Monitoring: 25 February 2026 (Transect T2) |
Monthly Monitoring: 9 February 2026 (Transect T3) |
Monthly Monitoring: 9 February 2026 (Transect T3) |
|
|
24-hour RSP (Ambient Arsenic) Monitoring for Land Contamination (1) |
KTN-DMS-4A(2)(3) |
3, 9, 14, 20, 25 February 2026 |
N/A |
3, 9, 14, 20, 25 February 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Water Quality Monitoring(1) |
KTN-IS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-CS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-IS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-CS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Landfill Gas Monitoring |
250m Landfill Consultation Zone of Ma Tso Lung Landfill |
N/A(7) |
N/A(7) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Environmental Site Inspection |
Site Area under Works Contract No. ND/2024/01 |
3, 12, 16, 24 February 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Site Area under Works Contract No. ND/2024/02 |
N/A |
12,16,27 February 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/03 |
N/A |
N/A |
2, 12, 16, 25 February 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/04 |
N/A |
N/A |
N/A |
6, 13, 26 February 2026 (8) |
N/A |
N/A |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/06 |
N/A |
N/A |
N/A |
N/A |
N/A |
2, 9, 23 February 2026 (8) |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/07 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
5, 12, 26 February 2026 (8) |
N/A |
|
Remarks:
(1) For 1-hour and 24-hour TSP
& 24-hour RSP (Ambient Arsenic) monitoring, monitoring stations that are
specifically within the 500m buffer area projected from the site boundary of
works contract(s) will be considered being the representative monitoring
stations for the corresponding works contract(s) and the associated impact
monitoring exercises will be kicked off once the nearest works contracts have
been commenced and undertaken during the reporting period/month.
For Noise Monitoring, monitoring stations that are
specifically within the 300m buffer area projected from the site boundary of
works contract(s) will be considered being the representative monitoring
stations for the corresponding works contract(s) and the associated impact
monitoring exercises will be kicked off once the nearest works contracts have
been commenced and undertaken during the reporting period/month.
(2) New monitoring
station IDs are presented. The corresponding monitoring station IDs are as
follows:
|
1-hour and 24-hour TSP / 24-hour RSP (Ambient Arsenic) KTN-DMS1 =
DMS1 |
Noise CP-KTN-NMS1
= CP-NMS1 CP-KTN-NMS7 = CP-NMS4 |
(3) Alternative monitoring stations
to the corresponding original monitoring stations.
(4) The monitoring date for the
reporting month was conducted by the ET from the First Phase of KTN/FLN NDAs
Project, except Transect T4 for the ecological monitoring item Monitoring of
Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue
River, and Long Valley, and Transect T2 for the ecological monitoring item
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats
from Disturbance and Pollution. No ecological monitoring was conducted for the
Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang
San Tsuen Stream for this reporting month as this monitoring is only conducted
during wet season (April October). Detailed divisions of work between First
Phase ET and Remaining Phase can be referred to Section 6 and relevant
appendix.
(5) N/A No relevant monitoring is
required according to the approved updated EM&A Manual.
(6)
The monitoring date for the
reporting month was conducted by the ET from the Remaining Phase of KTN/FLN
NDAs Project.
(7) As confirmed by the Supervisor
Team, no ground disturbance works were carried out in the work area within 250m
Landfill Consultation Zone of Ma Tso Lung Landfill including construction of
the infrastructure, development works, excavation works and works involve
confined spaces. Routine gas monitoring should be undertaken during groundwork
construction and in all excavations.
(8) No site inspections were
arranged for the week ending 21 February 2026 owing to the closure of
construction sites over Lunar New Year holidays as advised by respective
Supervisor Teams to works contracts.
A7. Summary of the environmental exceedances of the
reporting period is tabulated in Table A4.
Table A4 Summary of Exceedances in the Reporting Period
|
Environmental Monitoring |
Parameter(s) |
No. of Exceedances |
Total No. of Exceedances |
No. of Non-project Related Exceedances |
Total No. of Non-project Related Exceedances |
No. of Exceedances Related to the Project |
Total No. of Exceedances Related to the Project |
|||
|
AL |
LL |
AL |
LL |
AL |
LL |
|||||
|
Air Quality |
1-hour TSP |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
24-hourTSP |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
24-hour RSP (Ambient Arsenic) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
Noise |
Leq(30mins) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Ecological Monitoring |
Avifauna |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Non-aquatic fauna |
0 |
3 |
3 |
0 |
3 |
3 |
0 |
0 |
0 |
|
Air Quality
A8.
No AL or LL exceedance
was recorded for air quality monitoring in the reporting period.
Noise
A9.
No AL or LL exceedance
was recorded for construction noise monitoring in the reporting period.
Ambient Arsenic
A10. No AL or LL exceedance was recorded
for ambient arsenic monitoring in the reporting period.
Ecological
Monitoring
A11. 3 LL exceedances were recorded for the
monitoring of measures to minimise impacts on ecological sensitive habitats
from disturbance and pollution. All exceedances were deemed as non-project
related with potential influences by abiotic factors.
Built
Heritage Monitoring (Vibration Monitoring)
A12. No exceedance of limits was recorded
for vibration monitoring in the reporting period.
A13. There was a total of 1 complaint
received during the reporting period. The environmental complaint related to
construction dust generated from KTN NDA constructions sites, particularly near
Ma Tso Lung Tsuen on 21 January 2026 under works contract ND/2024/01. The
complaint was referred to EPD by Chief Executives Office on 21 January 2026
and referred to Engineers Representative and ET on 4 February 2026. The
complaint case has been investigated by the Contractor and ET,
investigation was closed out on 16 February 2026. The investigation findings
indicate the complaint was not project related. The details of the complaint
and investigation result are shown in Appendix 12.1.
A14. No notification of summons or successful prosecutions was received in
the reporting period.
A15. There was no change to be reported that may affect the on-going EM&A
programme.
A16. The major site activities for the next reporting period are summarized
below and shown in Appendix 1.1:
Works
Contract No. ND/2024/01:
· All Site
Resumption Area(s)
1. Tree
survey
2. Site
Clearance
· Portion
III (3), IV (4), V (5), VII (7) and XXXV (35)
1. Site
Clearance and Demolition
2. Site
Formation
3. Asbestos
Abatement Works
4. Construction
of Temporary Drainage Diversion
· Portion
VIII (8)
1. Site Clearance & Demolition
2. Asbestos Abatement Works
· Portion
XVIII (18), XXXVIII (38)
1. Excavation works
2. Construction of CHC Box Culvert
· Portion
XI (11), XXIII (23)
1. Formwork Erection, Rebar Fixing, Concreting Works
· Portion
XL (40)
1. Retaining
Wall Construction
2. Drainages
System Construction
3. ELS
work
· Portion
LIX (59)
1. Treatment
of High Arsenic-Containing Soil (HAS)
· Portion
XVII (17), XVII (18), XXI (21), XXXIV (34), XXXV (35), XLI (41), XLII (42)
1. Excavation
Works
2. Drainage
Pipe Installation
3. ELS
Works
· Portion XXV (25), XXVII (27), XXXIII (33),
XLII (42) and XLIV (44)
1. Site Clearance
2. Site Formation
3. Construction of Box Culvert
Works Contract
No. ND/2024/02:
· Site clearance in Area B, D, L
· Site formation works in Area D
· Temporary storage fill bank in Kwu
Tung Grass Soccer Pitch
· Demolition works for Community Sports in Area J
Works
Contract No. ND/2024/03:
Fanling Highway & Castle Peak Road area
· Pak Sau
Road Po Lau Road
1. Relocation/Reprovision/Removal
of Existing TCSS, Fire Hydrant, Signage & Streetlighting
2. Tree
Works
· Po Lau
Road Sheung Yue River
1. Asbestos
Removal Works at Portion IX
2. Box
Culvert Bay 37 Bay 42 ELS
· TTA Stage
1 Works
1. Tree
Works
2. Removal
or relocation of directly impacted Shrine/historical building at HKT08 &
KT72
3. Demolish
of Central Divider & Barrier along FL Highway E/B
New Tsung Pak Long Road
· Box
culvert Bay 10 to 12, 14 to 16 Drainage/Watermains
1. Drainage,
Sewerage & Watermain with Backfilling at Box Culvert Bay 15 & 16
2. Box
Culvert Bay 10-13 & 14 ELS
3. Removal
of ELS and Temp Road Diversion
· Box
culvert Bay 17 to 19 & Drainage/Watermains
1. Box
Culvert Bay 17 to 19 ELS, Base Slab, Wall and Top Slab
· TTA Stage
1B
1. Box
Culvert Bay 3, 5 to 7, 7A ELS
2. Box
Culvert Base Slab
· Retaining
Wall RW05A
1. RW05A
ELS
2. Base
Slab and Wall
· Kwu Tung Road Bridge
1. Site
Clearance and Tree Works
2. Site
formation and cutback the existing slope
3. Foundation
& Piling
· Works
Areas WA1, WA2, WA3, WA4 & WA5
1. Site
Clearance and Site Formation at PMs Site Office
2. Temporary
Drainage
3. Asbestos
removal
Fanling Highway Cross River Bridge (along Sheung Yue
River)
· Portion
XI East Abutment & pier foundation (No Work: Wet Season (1 Apr 31 Oct))
1. Trial
Pits for UUs
2. Piling
Works
· Road L3
Viaduct
1. Piling
Works
2. Pile
Cap L3A-02
· Kwu Tung Interchange Foundation & Substructure
Bridge B1 & C1
1. Piling
Works
2. ELS
· Bridge B2
& C2
1. Piling
Work
· Footbridges
No. 4 at TTA Stage 1
1. Ground
Investigation
2. Underground
Utilities Works
· Footbridges
No. 5 at TTA Stage 2
1. Predrilling
· Widening
of Existing Bridge No.N526
1. Tree
Works
2. ELS
3. Piling
Works
Contract No. ND/2024/04:
1. Site
Clearance
2. Site
Establishment
3. Tree
Felling
4. Existing
Sewage Diversion
5. Trial
Pit
6. Predrilling
7. Ground
Investigation
8. Demolition
of Existing Structures
9. Bored
Piling
10.Pier Cap Construction
11.Sheet Piling
12.Soil Nailing
13.Shotcreting
Works Contract No. ND/2024/06:
· Portion A
1. Excavation to +90 mPD of Portion
A
2. Forming Haul Road form
Area C to Portion A
· Portion C
1.
Trench and Watermans
Laying Works of Portion C
· Portion D
1.
Trench and Watermans
Laying Works of Portion D
2.
Demolition of Thrust Blocks of
Portion D
· Portion E
& F
1.
Trench and Watermans
Laying Works of Portion E & F
· Area N
1. Jacking Pit
Excavation
Works
Contract No. ND/2024/07:
1. Site Clearance
2. Site Formation
3. Ground Investigation
4. Pre-bored Socketed H Pile
Construction
5. Pier Construction
6. Lift Tower Construction
7. ABWF Works
8. Bridge Deck Connection (Footbridge
FB5)
9. Drainage Construction
10.Storm Pipe Construction
11.Improvement of Junction
12.Road Improvement & Works
13.Open Landscaping Works
14.Assembly Yard for Bridge Construction
15.Storage Yard for Concrete Pipe
16.Sewage Construction
17.Drainage Construction
18.New Shrine Construction
19.Rebar Yard
20.Tree Felling
21.Asbestos Containing Materials Survey & Removal
22.Old Shine Removal
23.Temporary Road Construction
24.Box Culvert 5 Construction
25.Land Contamination (Environmental Ground Investigation)
26.Internal Movement, Importation & Exportation of C&D materials
Works
Contract No. ND/2024/08:
1.
The construction work will be
commenced in March 2026.
1.1.1 The Kwu
Tung North and Fanling North New Development Areas
(KTN and FLN NDAs) development are implemented in two phases, comprising First
Phase and Remaining Phase developments. The construction works for the
First Phase development commenced in December 2019. The construction works for
the Remaining Phase development (the Project), including site clearance and
formation, roads, drainage, sewerage and water supply systems, commenced
progressively from the January 2025.
1.1.2 The Project is delivered under eight (8) Works Contracts as below.
· Contract No. ND/2024/01: Site
Formation and Infrastructure Works (South);
· Contract No. ND/2024/02: Site
Formation and Infrastructure Works (North);
· Contract No. ND/2024/03: Improvement
Works of Fanling Highway (Kwu
Tung Portion) and Associated Works;
· Contract No. ND/2024/04: Improvement
Works of Tai Tau Leng Roundabout and Po Shek Wu Road and Associated Works;
· Contract No. ND/2024/05: Improvement
Works of Fanling Highway (Pak Shek Au Portion) and
Associated Works;
· Contract No. ND/2024/06: Fresh Water
and Flushing Water Service Reservoirs and Associated Works;
· Contract No. ND/2024/07: Site
Formation and Infrastructure Works (East); and
· Contract No. ND/2024/08: Site
Formation and Infrastructure Works (West).
1.1.3 The EIA Report (AEIAR-175/2013) for
NENT NDA was approved with conditions under EIAO in 2013. The Environmental
Permits for corresponding Designated Projects were also issued by DEP in
November 2013. Subsequent to the findings of preliminary design and P&E
Review for accommodating additional population in KTN and FLN NDAs, VEP were
subsequently applied for eight EPs under the Project (i.e. EP-465/2013/A,
EP-466/2013/A, EP-467/2013/A, EP-468/2013/A, EP-470/2013/A, EP-471/2013/A,
EP-472/2013/A and EP-476/2013).
1.1.4
Aurecon was
commissioned by Civil
Engineering and Development Department (CEDD) to provide EM&A services for the
works contracts in relation to the Project pursuant to the requirements as
specified in relevant EPs, the EM&A Manual issued in the EIA stage, the
Updated EM&A Manual prepared for Contract No. NDO 14/2018 and the approved
EIA Report for the Project to discharge the duties of the ET for the Project.
1.1.5
This is the 14th Monthly EM&A
Report summarizing the findings of EM&A works at Works Contract No.
ND/2024/01 under the Project with EP-467/2013/A and EP-468/2013/A, Works
Contract No. ND/2024/02 under the Project with EP-467/2013/A and EP-468/2013/A,
Works Contract No. ND/2024/03 under the Project with EP-465/2013/A,
EP-466/2013/A and EP-467/2023/A, Works Contract No. ND/2024/04 under the
Project with EP-465/2013/A and EP-471/2013/A, Works Contract No. ND/2024/06
under Environmental Permit No. EP-470/2013/A and for Contract No. ND/2024/07
under Environmental Permit No. EP-476/2013 during the reporting period from 1
to 28 February 2026. No construction works occur in the remaining contracts
during the reporting period for Contract No. ND/2024/05 and ND/2024/08.
Table 1.1 Parties Involved in Project Organization for all Works
Contracts
|
|
Works Contract(s) |
||||||||
|
Parties |
ND/2024/01 |
ND/2024/02 |
ND/2024/03 |
ND/2024/04 |
ND/2024/05 |
ND/2024/06 |
ND/2024/07 |
ND/2024/08 |
|
|
Project Proponent |
CEDD |
||||||||
|
Supervisor / Engineers Representative (ER) |
AECOM Asia Co. Ltd. |
AECOM Asia Co. Ltd. |
AECOM Asia Co. Ltd |
AECOM Asia Co. Ltd |
AECOM Asia Co. Ltd |
Binnies Hong Kong Limited |
AtkinsRιalis |
AtkinsRιalis |
|
|
Contractor |
Build King - Richwell Engineering Joint Venture |
Build King Richwell Civil Joint Venture
|
China State - STEC Joint Venture |
CW CRCC (ND202404) Joint Venture |
Lanon Sinohydro Excel JV |
Wo Hing-Tsun Yip Joint Venture |
Build King Richwell Civil Joint Venture |
Gammon - STEC Joint Venture |
|
|
ET |
Aurecon Hong Kong Limited |
||||||||
|
Independent Environmental Checker (IEC) |
Mott MacDonald Hong Kong Limited |
||||||||
Works
Contract No. ND/2024/01:
· All Site
Resumption Area(s)
1. Tree
survey
2. Site
Clearance
· Portion
III (3), IV (4), V (5), VII (7) and XXXV (35)
1. Site
Clearance & Demolition
2. Asbestos
Abatement Works
3. Construction
of Temporary Drainage Diversion
· Portion
VIII (8)
1. Site
Clearance & Demolition
2. Asbestos
Abatement Works
· Portion VI (6), XVIII (18), XXXVIII (38)
1. Site Clearance
2. Excavation works
· Portion XI
(11), XXIII (23)
1. Formwork
Erection, Rebar Fixing, Concreting Works
· Portion
XL (40)
1. Retaining Wall Construction
2. Drainages System Construction
3. ELS work
· Portion
LIX (59)
1. Treatment
of High Arsenic-Containing Soil (HAS)
· Portion
XVII (17), XVII (18), XXI (21), XXXIV (34), XXXV (35), XLI (41), XLII (42)
1. Excavation
works
2. Drainage
Pipe Installation
Works Contract No. ND/2024/02:
· Site
clearance in Area B, D, L
· Site formation
works in Area D
· Temporary
storage fill bank in Kwu Tung Grass Soccer Pitch
Works
Contract No. ND/2024/03:
Fanling Highway & Castle Peak Road area
· Pak Sau
Road Po Lau Road
1. Relocation/Reprovision/Removal
of Existing TCSS, Fire Hydrant, Signage & Streetlighting
2. Tree
Works
· Po Lau
Road Sheung Yue River
1. Asbestos
Removal Works at Portion IX
2. Box
Culvert Bay 37 Bay 42 ELS
· TTA Stage
1 Works
1. Tree
Works
2. Removal
or relocation of directly impacted Shrine/historical building at HKT08 &
KT72
3. Demolish
of Central Divider & Barrier along FL Highway E/B
New Tsung Pak Long Road
· Box
culvert Bay 10 to 12, 14 to 16 Drainage/Watermains
1. Drainage,
Sewerage & Watermain with Backfilling at Box Culvert Bay 15 & 16
2. Box
Culvert Bay 14 ELS
· Box
culvert Bay 17 to 19 & Drainage/Watermains
1. Box
Culvert Bay 17 to 19 ELS, Base Slab, Wall and Top Slab
· Retaining
Wall RW05A
1. RW05A
ELS
· Kwu Tung Road Bridge
1. Site
Clearance and Tree Works
2. Site
formation and cutback the existing slope
3. Predrilling
4. Foundation
& Piling
· Works
Areas WA1, WA2, WA3, WA4 & WA5
1. Site
Clearance and Site Formation at PMs Site Office
2. Temporary
Drainage
3. Asbestos
removal
Fanling Highway Cross River Bridge (along Sheung Yue
River)
· Portion
XI East Abutment & pier foundation
1. Trial
Pits for UUs
2. Piling
Works
· Road L3
Viaduct
1. Piling
Works
2. Pile
Cap L3A-02
· Kwu Tung Interchange Foundation & Substructure
- Bridge B1 & C1
1. Piling
Works
Works Contract No. ND/2024/04:
1.
Site Clearance
2.
Site Establishment
3.
Tree Felling
4.
Trial Pit
5.
Pre-drilling
6.
Ground Investigation
7.
Existing Sewage Diversion
8.
Demolition of Existing Structures
9.
Bored Piling
10.Sheet Piling
11.Soil Nailing
12.Shotcreting
Works Contract No. ND/2024/06:
· Portion A
1.
Excavation to +95 mPD of Portion A
2.
Forming Haul Road from Area C to
Portion A
· Portion C
1.
Trench and Watermains Laying Works
of Portion C
· Portion D
1.
Trench and Watermains Laying Works
of Portion D
2.
Demolition of DN2000 Pipes and
Associated Thrust Block of Portion D
· Portion E
& F
1. Trench and
Watermains of Portion E & F
Works Contract No. ND/2024/07:
1. Site Clearance
2. Site Formation
3. Pier Construction
4. Lift Tower Construction
5. Steel Works
6. ABWF Works
7. Drainage Construction
8. Storm Pipe Construction
9. Assembly Yard for Bridge
10.Storage Yard for Concrete Pipe
11.Rebar Yard
12.Sewage Construction
13.New Shine Construction
14.Improvement of Junction
15.Road Improvement
16.Temporary Road Construction
17.Asbestos Containing Materials Survey & Removal
18.Internal Movement / Importation & Exportation of C&D
materials
Works
Contract No. ND/2024/05 and ND/2024/08.
1.
No Construction Work during
reporting period.
Table 1.2 Status of Environmental License,
Notifications and Permits for Works Contract No. ND/2024/01
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10008709 |
02/09/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7052236 |
20/09/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN: 5213-548-B2781-01 |
06/12/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00045924-2024 |
15/01/2025 |
31/01/2030 |
Valid |
|
WT00046627-2025 |
03/06/2025 |
30/06/2030 |
Valid |
|
WT00046736-2025 |
10/06/2025 |
30/06/2030 |
Valid |
|
WT00046982-2025 |
03/10/2025 |
31/10/2030 |
Valid |
|
WT00047583-2025 |
19/01/2026 |
31/01/2031 |
Valid |
|
WT00048070-2025 |
28/01/2026 |
31/01/2031 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0966-25 |
22/08/2025 |
11/02/2026 |
Valid until 11/02/2026 |
|
GW-RN1540-25 |
26/12/2025 |
25/03/2026 |
Valid |
|
GW-RN1593-25 |
04/01/2026 |
30/06/2026 |
Valid |
|
GW-RN0041-26 |
16/01/2026 |
15/04/2026 |
Valid |
|
GW-RN0254-26 |
27/02/2026 |
26/05/2026 |
Valid |
|
GW-RN0166-26 |
08/02/2026 |
07/05/2026 |
Valid |
Table 1.3 Status of Environmental License, Notifications and Permits for
Works Contract No. ND/2024/02
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10024940 |
23/12/2025 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7057203 |
05/01/2026 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-545-B2803-01 |
11/02/2026 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
Application Ref. No.10026460 |
Applied on 06/02/2026 |
TBC |
Under application |
|
Construction Noise Permit (CNP) |
|
|
|
|
NIL |
NIL |
NIL |
NIL |
Table 1.4 Status of Environmental License, Notifications and Permits for
Works Contract No. ND/2024/03
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-465/2013/A |
20/01/2017 |
N/A |
Valid |
|
EP-466/2013/A |
18/08/2022 |
N/A |
Valid |
|
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10008101 |
15/08/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7052008 |
21/08/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-548-C5047-01 |
22/01/2025 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00046044-2025 |
07/11/2025 |
28/02/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN1262-25 |
06/11/2025 |
05/02/2026 |
Superseded by GW-RN1496-25 |
|
GW-RN1353-25 |
17/11/2025 |
16/02/2026 |
Valid |
|
GW-RN1496-25 |
19/12/2025 |
18/03/2026 |
Valid |
|
GW-RN0151-26 |
07/02/2026 |
08/02/2026 |
Valid until 08/02/2026 |
Table 1.5 Status of Environmental License, Notifications and Permits for
Works Contract No. ND/2024/04
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-465/2013/A |
20/01/2017 |
N/A |
Valid |
|
EP-471/2013/A |
10/10/2022 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10012919 |
06/01/2025 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7053746 |
13/02/2025 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-626-C5043-01 |
28/01/2025 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00047165-2025 |
15/12/2025 |
31/08/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN1044-25 |
17/09/2025 |
16/03/2026 |
Valid |
|
GW-RN1377-25 |
24/11/2025 |
23/03/2026 |
Valid |
|
GW-RN1376-25 |
24/11/2025 |
23/02/2026 |
Valid until 23/02/2026 |
|
GW-RN1405-25 |
28/11/2025 |
27/02/2026 |
Valid until 27/02/2026 |
|
GW-RN1457-25 |
10/12/2025 |
09/03/2026 |
Valid |
|
GW-RN1523-25 |
25/12/2025 |
28/02/2026 |
Valid |
|
GW-RN1379-25 |
01/12/2025 |
28/02/2026 |
Valid |
|
GW-RN0021-26 |
11/01/2026 |
31/03/2026 |
Valid |
|
GW-RN1510-25 |
01/01/2026 |
30/04/2026 |
Valid |
|
GW-RN0230-26 |
24/02/2026 |
31/05/2026 |
Valid |
|
GW-RN0251-26 |
28/02/2026 |
27/05/2026 |
Valid |
Table 1.6 Status of Environmental License, Notifications and Permits for
Works Contract No. ND/2024/06
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-470/2013/A |
13/05/2022 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10007695 |
06/08/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7051899 |
28/08/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-624-W3824-01 |
04/09/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00046560-2025 |
15/05/2025 |
31/05/2030 |
Valid |
|
WT00046847-2025 |
11/07/2025 |
31/07/2030 |
Valid |
|
WT00046588-2025 |
29/05/2025 |
31/05/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0972-25 |
02/09/2025 |
28/02/2026 |
Valid |
|
GW-RN1439-25 |
29/12/2025 |
28/04/2026 |
Valid |
Table 1.7 Status of Environmental License, Notifications and Permits for
Works Contract No. ND/2024/07
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-476/2013 |
21/11/2013 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10007874 |
09/08/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7051974 |
20/08/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-625-B2775-01 |
19/08/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00045532-2024 |
10/12/2024 |
31/12/2029 |
Valid |
|
WT00046059-2025 |
14/02/2025 |
28/02/2030 |
Valid |
|
WT00046059-2025 |
17/06/2025 |
28/02/2030 |
Valid |
|
WT00046342-2025 |
15/05/2025 |
31/05/2030 |
Valid |
|
WT00046692-2025 |
29/05/2025 |
31/05/2030 |
Valid |
|
WT00046655-2025 |
03/06/2025 |
30/06/2030 |
Valid |
|
WT00046819-2025 |
31/07/2025 |
31/07/2030 |
Valid |
|
WT00047343-2025 |
29/09/2025 |
30/09/2030 |
Valid |
|
WT00047250-2025 |
12/11/2025 |
30/11/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0975-25 |
23/08/2025 |
22/02/2026 |
Valid until 22/02/2026 |
|
GW-RN1224-25 |
01/11/2025 |
30/04/2026 |
Valid |
|
GW-RN1350-25 |
18/11/2025 |
17/02/2026 |
Valid until 17/02/2026 |
|
GW-RN1111-25 |
01/12/2025 |
28/02/2026 |
Valid |
|
GW-RN1299-25 |
01/12/2025 |
28/02/2026 |
Valid |
|
GW-RN1473-25 |
12/12/2025 |
31/05/2026 |
Valid |
|
GW-RN1480-25 |
19/12/2025 |
18/03/2026 |
Valid |
|
GW-RN0069-26 |
19/01/2026 |
18/06/2026 |
Valid |
|
GW-RN0168-26 |
18/02/2026 |
17/06/2026 |
Valid |
|
GW-RN0179-26 |
23/02/2026 |
22/08/2026 |
Valid |
2.2.1
According to the
EM&A Manual, the approved updated EM&A Manual for the First Phase, the
designated locations for impact air quality monitoring in related to the work
contracts in the reporting period are listed in Table 2.1 and their
locations are shown in Figure 2.1 and Figure 2.2.
Table 2.1 Summary of Impact Air Quality Monitoring Stations in related
to the Works Contracts in the Reporting Period
|
Monitoring Station(s) |
Works Contract(s) |
ASR ID in EIA |
Planned(3) or Existing |
Monitoring Location(s) |
|
KTN-DMS1 |
ND/2024/01, ND/2024/02, ND/2024/03 |
KTN-19 |
Planned |
Nursery Classes and Kindergarten; Post Offices |
|
KTN-DMS2 |
ND/2024/01, ND/2024/02 |
KTN-90 |
Planned |
Nursery Classes and Kindergarten (2 nos); District Elderly Community Centre |
|
KTN-DMS3 |
ND/2024/01, ND/2024/02, ND/2024/03 |
KTN-326 |
Planned |
Village Resite |
|
KTN-DMS4(B)(1)(2) |
ND/2024/01, ND/2024/03 |
KTN-E70 |
Existing |
Temporary Structure at Pak Shek Au |
|
FLN-DMS1 |
ND/2024/07 |
FLN-E62 |
Existing |
Scattered Village Houses North of Proposed Potential Ecopark |
|
FLN-DMS2 |
ND/2024/06, ND/2024/07 |
FLN-E243 |
Planned |
Residential Building, Nursery Classes and Kindergartens, Neighbourhood Elderly Community Centre, Residential Home for the Elderly, Post Office |
|
FLN-DMS5, FLN-DMS5(A) |
ND/2024/07 |
FLN-E124 |
Existing |
Noble Hill / Good View New Village |
|
FLN-DMS6(A) |
ND/2024/03, ND/2024/04 |
DMS-10 |
Existing |
Choi Ngan House, Choi Po Court |
|
FLN-DMS7 |
ND/2024/06, ND/2024/07 |
FLN-20 |
Planned |
Planned premise for Weapon Training Division |
Remarks:
(1) KTN-DMS4(B) is the alternative
air monitoring stations proposed to replace KTN-DMS4.
(2) As KTN-DMS4 - Temporary
structure near Fanling Highway (near Pak Shek Au) is
no longer as existing ASR, air quality monitoring station should be relocated
to the alternative dust monitoring location according to the updated EM&A
Manual, Section 2.6.2. According to Figure 3.1 of Approved EIA report and site
visits conducted in June 2022, ASR at near KTN-E70 Temporary Structure near Fanling Highway near Pak Shek Au is considered as the most
representative alternative station KTN-DMS4(B) for air quality monitoring for
KTN-DMS4 (i.e. KTN-E162).
(3) Impact monitoring will be
carried out when the planned sensitive receivers are commissioned.
Table 2.2 Parameters Measured in the Impact Air Quality Monitoring
|
Parameter(s) |
Frequency(1)(2) |
|
1-hour TSP |
Three times / 6 days |
|
24-hour TSP |
Once / 6 days |
Remarks:
(1) The air quality monitoring
(1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting
period.
(2) The air quality monitoring
(1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the
reporting period.
Table
2.3 Air Quality Monitoring Equipment
|
Monitoring Station(s) |
Equipment |
Model |
Manufacturer |
Quantity |
|
KTN-DMS4(B)(1), FLN-DMS5(1), FLN-DMS5(A)(1) |
Dust Monitor (1-hour and 24-hour TSP) |
AEROCET-831 |
Met One Instruments |
7 |
|
FLN-DMS1(1) |
Dust Monitor (1-hour TSP) |
|||
|
HVS Sampler (24-hour TSP) |
TE-5170 |
Tisch |
1 |
|
|
FLN-DMS6(A)(2) |
Dust Monitor (1-hour and 24-hour TSP) |
LD-5R |
Sibata |
1 |
Table
2.3 Air Quality Monitoring Equipment
Remarks:
(1) The air quality monitoring
(1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting
period.
(2) The air quality monitoring
(1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the
reporting period.
Instrumentation
(AEROCET-831)
·
Place the
dust meter at least 1.3 meters above ground;
·
Press and
hold the Power key momentarily to power on the unit and make sure that the
battery level was not flash or in low level;
·
Allow the
instrument to stand for about 3 second to display the Sample Screen minutes;
·
Press the
START / STOP key to run the internal vacuum pump for 1 minute and be ready to use;
·
Use the
select dial to select the PM range and press the START / STOP key to start a measurement;
·
Finally,
push the START/STOP key to stop the measurement after 24-hour sampling;
·
Information
such as sampling date, time, value and site condition were recorded during the
monitoring period; and
·
All
data were recorded in the data logger for further data processing.
Maintenance/Calibration
· Check and calibrate the
meters by High Volume Sampler (HVS) to check the validity and accuracy of the
results measured by direct reading method at 2-month intervals throughout all
stages of the air quality monitoring.
Instrumentation
(TISCH
Model: TE-5170 / TE-5170X)
· A horizontal platform with
appropriate support was provided to secure the samplers against gusty wind. the
dust meter at least 1.3 meters above ground;
· No two samplers were
placed less than 2 metres apart.
· The distance between the
sampler and an obstacle, such as buildings, was at least twice the height that
the obstacle protrudes above the sampler.
· A minimum of 2 metres of
separation from walls, parapets and penthouses was required for rooftop
samples.
· A minimum of 2 metres
separation from any supporting structure, measured horizontally was required.
· No furnaces or
incineration flues were nearby.
· Airflow around the
sampler was unrestricted.
· The sampler were more
than 20 metres from the drip line.
· Any wire fence and gate,
to protect the sampler, should not cause any obstruction during monitoring.
· Permission and access to
monitoring stations have been obtained to set up the samplers.
· A secured supply of
electricity was provided to operate the samplers.
Filters
Preparation
Operating/Analytical Procedures
· Prior to the
commencement of dust sampling, the flow rate of the HVS was properly set
(between 1.1 m3 /min. and 1.4 m3 /min.) in accordance
with the manufacturer's instruction to within the range recommended in USEPA
Standard Title 40, CFR Part 50;
· The power supply was
checked to ensure the sampler worked properly;
· On sampling, the sampler
was operated for 5 minutes to establish thermal equilibrium before placing any
filter media at the designated air quality monitoring station;
· The filter holding frame
was then removed by loosening the four nuts and carefully a weighted and
conditioned filter was centered with the stamped number
upwards, on a supporting screen;
· The filter was aligned
on the screen so that the gasket formed an airtight seal on the outer edges of
the filter. The filter holding frame was then tightened to the filter holder
with swing bolts. The applied pressure should be sufficient to avoid air leakage
at the edges;
· The shelter lid was
closed and secured with the aluminium strip;
· The timer was then
programmed. Information was recorded on the record sheet, which included the
starting time, the weather condition and the filter number (the initial weight
of the filter paper can be found out by using the filter number);
· After sampling, the
filter was removed and kept in a clean and tightly sealed plastic bag. The
filter paper was then returned to the HOKLAS accredited laboratory (Wellab Ltd.) for reconditioning in the humidity-controlled
chamber followed by accurate weighting by an electronic balance with a readout
down to 0.1mg. The elapsed time was also recorded; and
· Before weighing, all
filters were equilibrated in a conditioning environment for 24 hours. The
conditioning environment temperature should be between 25°C and 30°C and did
not vary by more than ±3°C; the RH should be < 50% and did not vary by more
than ±5%. A convenient working RH is 40%. Weighing results were returned for
further analysis of TSP concentrations collected by each filter
Maintenance/Calibration
· The high-volume motors
and their accessories were properly maintained. Appropriate maintenance such as
routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power
supply are in good working conditions; and
· All HVS were calibrated
(five point calibration) using Calibration Kit prior
to the commencement of baseline monitoring and thereafter at bi-monthly
intervals.
Instrumentation
(Sibata Model: LD-5R)
· Placed the dust meters
at least 1.3m above ground
· Set POWER to ON and
make sure that the battery level not flashed or in low level;
· Pulled the air sampling
inlet cover up;
· Pushed the knob at
MEASURE position;
· Set time/mode setting to
[BG] by pushing the time setting switch. Then, started the background
measurement by pushing the start/stop switch once. It took 6 sec. to complete
the background measurement;
· Turned knob to SENSI.
ADJ position and pressed in;
· Pushed Start/Stop switch
once;
· Gently returned knob to
the MEASURE position;
· Pushed the time setting
switch to change the time setting display to [LOG] at the bottom left of the
liquid crystal display;
· Removed the cap and
started measurement; and
· Information such as
sampling date, time, count value and site condition were recorded during the
monitoring period.
Maintenance/Calibration
· Direct reading dust
meter shall be used in determining 1-hour TSP and 24-hour TSP at air quality
monitoring points. The direct reading dust meters have been calibrated against
high volume samplers (HVSs)
bi-monthly. A 2-day, three 3-hour measurement results
per day from direct reading dust meters were taken to compare with the sampling
results from the HVSs. The correlation between the direct reading dust meters
and the HVSs were then concluded. By accounting for the correlation factor, the
direct reading dust meters are considered to achieve comparable results as that
of the HVSs.
· The HVS used to
calibrate the direct dust monitor will need to be calibrated bi-monthly.
Details of maintenance and calibration for the HVS refers to Section 2.5.8.
Calibration for the air quality monitoring equipment is attached to the Appendix
2.2.
Table 2.4 Action and Limit Levels for 1-hour TSP Air Quality Monitoring
|
Monitoring Station |
AL (μg/m3) |
LL (μg/m3) |
|
KTN-DMS4(B) |
297 |
500 |
|
FLN-DMS1 |
303 |
500 |
|
FLN-DMS5 |
279 |
500 |
|
FLN-DMS6(A) |
286 |
500 |
Table 2.5 Action and Limit Levels for 24-hour of TSP Air Quality
Monitoring
|
Monitoring Station |
AL (μg/m3) |
LL (μg/m3) |
|
KTN-DMS4(B) |
192 |
260 |
|
FLN-DMS1 |
150 |
260 |
|
FLN-DMS5(A) |
153 |
260 |
|
FLN-DMS6(A) |
157 |
260 |
Table 2.6 Summary Table of 1-hour TSP Monitoring Result during the
Reporting Month
|
Monitoring Station |
Averaged Measured Value (μg/m3) |
Maximum Measured Value (μg/m3) |
Minimum Measured Value (μg/m3) |
Action Level (μg/m3) |
Limit Level, (μg/m3) |
|
KTN-DMS4(B)(1) |
67 |
108 |
39 |
297 |
500 |
|
FLN-DMS1(1) |
81 |
138 |
41 |
303 |
500 |
|
FLN-DMS5(1) |
59 |
84 |
43 |
279 |
500 |
|
FLN-DMS6(A)(2) |
62 |
76 |
40 |
286 |
500 |
(1) The air quality monitoring
(1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting
period.
(2) The air quality monitoring
(1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the
reporting period.
Table 2.7 Summary Table of 24-hour TSP Monitoring Result during the
Reporting Month
|
Monitoring Station |
Averaged Measured Value (μg/m3) |
Maximum Measured Value (μg/m3) |
Minimum Measured Value (μg/m3) |
Action Level (μg/m3) |
Limit Level, (μg/m3) |
|
KTN-DMS4(B)(1) |
69 |
107 |
40 |
192 |
260 |
|
FLN-DMS1(1) |
59 |
90 |
33 |
150 |
260 |
|
FLN-DMS5(A) (1) |
78 |
111 |
57 |
153 |
260 |
|
FLN-DMS6(A)(2) |
64 |
74 |
51 |
157 |
260 |
Remarks:
(1) The air quality monitoring
(1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting
period.
(2) The air quality monitoring
(1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the
reporting period.
Table 3.1 Construction Noise Monitoring Stations near in related to the
Works Contracts in the Reporting period
|
Monitoring Station(s) |
Works Contract(s) |
NSR EIA ID(s) |
Location(s) |
Planned(2) Or Existing |
Type of Measurement |
|
CP-KTN-NMS1 |
ND/2024/01, ND/2024/02 |
CP-NMS1 |
Residential Building at Ma Tso Lung |
Existing |
Free-Field(1) |
|
CP-KTN-NMS2 |
ND/2024/01, ND/2024/02 |
CP-NMS2 |
Residential Building at Ma Tso Lung |
Existing |
Free-Field(1) |
|
CP-KTN-NMS3 |
ND/2024/01,
|
CP-NMS3 |
Fung Kong Garden |
Existing |
|
|
CP-KTN-NMS4(3) |
ND/2024/01, ND/2024/02, ND/2024/03 |
CP-NMS5 |
Primary School |
Planned |
|
|
CP-KTN-NMS5 |
ND/2024/06 |
CP-NMS7 |
N/A |
Existing |
Free-Field(1) |
|
CP-KTN-NMS6 |
ND/2024/01, ND/2024/02 |
N/A |
Ho Sheung Heung, Hau Ku ShekAncestral Hall, Hung Shing Temple & Pai Fung Temple and Sin Wai Nunnery |
Existing |
Faηade |
|
CP-KTN-NMS7 |
ND/2024/01, ND/2024/02 |
CP-NMS4 |
Oi Lok Home |
Existing |
Free-Field(1) |
|
CP-FLN-NMS4(A)(4) |
ND/2024/04 |
CP-NMS6 |
Choi Ying House, Choi Po Court (Choi Yuen Estate) |
Existing |
Free-Field(1) |
|
CP-FLN-NMS1 |
ND/2024/06, ND/2024/07 |
CP-NMS10 |
Belair Monte |
Existing |
Facade |
|
CP-FLN-NMS3(3) |
ND/2024/06, ND/2024/07 |
CP-NMS12 |
Secondary School |
Planned |
Free-Field(1) |
|
CP-FLN-NMS5 |
ND/2024/07 |
CP-NMS8 |
Man Kok Village |
Existing |
Free-Field(1) |
|
CP-FLN-NMS6 |
ND/2024/07 |
CP-NMS9 |
Woodland Crest |
Existing |
Faηade |
Remarks:
(1)
For Free Field measurement, +3 dB(A) should be added to the measured
results.
(2)
Impact monitoring will be carried out when the planned sensitive
receivers are commissioned.
(3)
As confirmed with Engineer Representative, the planned school at
CP-KTN-NMS4 and CP-FLN-NMS3 are not constructed yet. Thus, the impact
noise monitoring will be carried out at monitoring station CP-KTN-NMS4 and
CP-FLN-NMS3 after the construction and occupation of the planned school.
No noise monitoring of the mentioned station was carried out in this reporting
period.
(4)
Alternative monitoring stations to the corresponding original monitoring
stations.
Table 3.2 Construction Noise Monitoring Parameter, Frequency and
Duration
|
Monitoring Station |
Parameter |
Frequency and Duration |
|
CP-KTN-NMS1(2), CP-KTN-NMS2(1), CP-KTN-NMS3(1), CP-KTN-NMS5(1), CP-KTN-NMS6(1),CP-KTN-NMS7(2),CP-FLN-NMS1(1), CP-FLN-NMS4(A)(2), CP-FLN-NMS5(2), CP-FLN-NMS6(2) |
Leq(30mins), L10 and L90 (as six consecutive Leq,5min readings) |
Once every week throughout the construction phase |
Remark:
(1) The noise monitoring was
conducted by First Phase ET during the reporting period.
(2) The noise monitoring was
conducted by Remaining Phase Environmental Team during the reporting period.
· For faηade measurement,
the monitoring station was set at a point 1 m from the exterior of the
sensitive receivers building faηade and set at a position 1.2 m above the
ground. For free-field measurement, the monitoring station was set at a
position 1.2 m above the ground.
· The battery condition
was checked to ensure good functioning of the meter.
· Parameters such as
frequency weighting, the time weighting and the interval were set as follows:
-
Frequency weighting: A
-
Time weighting: Fast
-
Interval: 30 minutes (Leq(30mins))
· Prior to and after each noise
measurement, the meter was calibrated using an acoustic calibrator for 94.0 dB
at 1000 Hz. If the difference in the calibration level before and after
measurement is more than 1.0 dB, the measurement was considered invalid and
repeat of noise measurement will be required after re-calibration or repair the
equipment.
· At the end of the
monitoring period, the values of Leq, L10
and L90 were recorded. In addition, noise sources were
recorded on a standard record sheet.
Table 3.3 Construction Noise Monitoring Equipment
|
Equipment |
Manufacturer |
Model |
No. of Equipment |
Serial No. |
|
Sound Level Meter |
NTi Audio(2) |
XL2 |
2 |
A2A-13548-E0 A2A-17638-E0 |
|
XL3 |
2 |
A3A-01229-F0 A3A-01231-F0 |
||
|
BSWA(1) |
BSWA 308 |
3 |
580006 580011 580013 |
|
|
Acoustic Calibrator |
RION(2) |
NC-75 |
3 |
34724244 35124529 34724245 |
|
SVANTEK(1) |
SV30A |
3 |
24803 24791 24780 |
Remark:
(1) The noise monitoring equipment was used by First Phase
ET during the reporting period.
(2) The noise monitoring equipment was used by Remaining
Phase Environmental Team during the reporting period.
· The microphone head of
the sound level meter and calibrator were regularly cleaned with a soft cloth;
· The sound level meter
and acoustic calibrator were calibrated annually; and
· The accuracy of the
sound level meter was checked using an acoustic calibrator generating a known
sound pressure level at a known frequency immediately prior to and following
each noise measurement. Measurements were accepted as valid only if the calibration
level from before and after the noise measurement agree to within 1.0 dB.
Table 3.4 Action and Limit Levels for Construction Noise Monitoring
|
Time Period |
Action |
Limit Level |
|
07:00 19:00 on normal weekdays |
When one or more documented complaints are received |
75 dB(A) |
Remark:
(1) Time period for construction noise monitoring during
normal construction working hour (0700-1900 Monday to Saturday).
(2) If works are to be carried out during restricted
hours, the conditions stipulated in the Construction Noise Permit (CNP) issued
by the Noise Control Authority have to be followed.
(3) 70 dB(A) and 65 dB(A) for schools during normal
teaching periods and school examination periods, respectively.
Table 3.5 Summary of Construction Noise Monitoring Results during the
Reporting Month
|
Works Contracts |
Monitoring Stations |
Noise Levels, Leq(30min), dB(A) |
Baseline Levels, dB(A) |
Limit Levels, dB(A) |
|
ND/2024/01, ND/2024/02 |
CP-KTN-NMS1(1)(3) |
50.6 52.2 |
65.7 |
75 |
|
CP-KTN-NMS2(1)(2) |
50.8 56.0 |
58.6 |
||
|
CP-KTN-NMS3(1)(2) |
47.6 55.2 |
51.6 |
||
|
CP-KTN-NMS6(2) |
55.9 60.7 |
55.1 |
||
|
CP-KTN-NMS7(1)(3) |
62.1 68.0 |
64.6 |
||
|
ND/2024/04 |
CP-FLN-NMS4(A)(1)(3)(4) |
69.8 71.8 |
72.4 |
|
|
ND/2024/06 |
CP-KTN-NMS5(1)(2) |
47.8 59.7 |
57.2 |
|
|
ND/2024/06, ND/2024/07 |
CP-FLN-NMS1(2) |
62.4 65.9 |
69.9 |
|
|
ND/2024/07 |
CP-FLN-NMS5(1)(3) |
67.9 68.3 |
69.5 |
|
|
CP-FLN-NMS6(3) |
54.8 56.5 |
55.0 |
Remarks:
(1) For Free Field measurement, +3
dB(A) was added to the measured results.
(2) The noise monitoring was
conducted by First Phase ET during the reporting period.
(3) The noise monitoring was
conducted by Remaining Phase Environmental Team during the reporting period.
(4) Alternative monitoring stations
to the corresponding original monitoring stations.
Table 3.6 Summary
of Observations
at Noise Monitoring Stations
|
Works Contracts |
Monitoring Stations |
Location |
Major Noise Sources |
|
ND/2024/01, ND/2024/02 |
CP-KTN-NMS1 |
Residential Building at Ma Tso Lung |
Household noise (dog barking) from nearby village house |
|
CP-KTN-NMS2 |
Residential Building at Ma Tso Lung |
Road Traffic Noise, Excavator, Crane |
|
|
CP-KTN-NMS3 |
Fung Kong Garden |
Road Traffic Noise, Excavator |
|
|
CP-KTN-NMS4 |
Primary School |
N/A(1) |
|
|
CP-KTN-NMS6 |
Ho Sheung Heung, Hau Ku Shek Ancestral Hall, Hung Shing Temple & Pai Fung Temple and Sin Wai Nunnery |
Road Traffic Noise, Dump Truck, Excavator, Backhoe |
|
|
CP-KTN-NMS7 |
Oi Lok Home |
Road Traffic Noise |
|
|
ND/2024/04 |
CP-FLN-NMS4(A)(2) |
Choi Ying House, Choi Po Court (Choi Yuen Estate) |
Road Traffic Noise |
|
ND/2024/06 |
CP-KTN-NMS5 |
N/A |
Excavator, Breaker, Road Traffic Noise |
|
ND/2024/06, ND/2024/07 |
CP-FLN-NMS1 |
Belair Monte |
Road Traffic Noise, Excavator, Dump Truck |
|
CP-FLN-NMS3 |
Secondary School |
N/A(1) |
|
|
ND/2024/07 |
CP-FLN-NMS5 |
Man Kok Village |
Road Traffic Noise |
|
CP-FLN-NMS6 |
Woodland Crest |
No construction activity and other noise source was observed |
Remarks:
(1) No impact noise monitoring was carried
out at the monitoring station. Thus, not applicable (N/A).
(2)
Alternative monitoring stations to the corresponding original monitoring
stations.
Table 4.1 Summary of Water Quality Monitoring
Locations
|
New Monitoring Station(s) |
Original Monitoring Station ID(s) |
Description |
Location(s) |
Measurement Period |
|
KTN NDA |
||||
|
KTN-CS1 |
CS1 |
Control Station for KTN NDA |
Centreline of river, upstream of the channel |
During construction of channel |
|
KTN-IS1 |
IS1 |
Impact Station for KTN NDA |
Centreline of river, downstream of the channel |
During construction of channel |
|
FLN NDA |
||||
|
FLN-CS1 |
CS2 |
Control Station for FLN NDA |
Centreline of river, upstream of the channel |
During construction of channel |
|
FLN-IS1 |
IS2 |
Impact Station for FLN NDA |
Centreline of river, downstream of the channel |
During construction of channel |
Table 5.1 Summary of Waste Generated
by the Construction Works from Works Contracts in the Reporting Period
|
Works Contract(s) |
Month |
Actual Quantalities of Inert C&D Materials Generated Monthly |
Actual Quantities of C&D Wastes Generated Monthly |
||||||||||
|
Total Quantity Generated |
Hard Rock and Lage Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
Metals |
Paper / Carboard Packing |
Plastics |
Chemical Waste |
Yard Waste recycled in Shredding Facility |
Others e.g., general refuse |
||
|
(in 000m3) |
(in 000m3) |
(in 000m3) |
(in 000m3) |
(in 000m3) |
(in 000m3) |
(in 000kg) |
(in 000kg) |
(in 000kg) |
(in 000kg) |
(in 000kg) |
(in 000m3) |
||
|
ND/2024/01 |
February 2026 |
1.684 |
0.000 |
0.415 |
1.269 |
0.000 |
0.370 |
0.001 |
0.095 |
0.000 |
0.000 |
0.000 |
0.404 |
|
ND/2024/02 |
February 2026 |
10145.822 |
0.000 |
308.617 |
8769.217 |
1067.989 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
232.633 |
|
ND/2024/03 |
February 2026 |
4924.060 |
0.000 |
0.000 |
0.000 |
4924.060 |
0.000 |
0.000 |
0.050 |
0.000 |
0.000 |
1.000 |
156.630(1) |
|
ND/2024/04 |
February 2026 |
1.593 |
0.000 |
0.000 |
0.000 |
1.593 |
0.000 |
7.870 |
0.000 |
0.000 |
0.000 |
23.810 |
0.047 |
|
ND/2024/06 |
February 2026 |
10.080 |
0.500 |
3.708 |
4.973 |
0.899 |
0.000 |
0.008 |
0.030 |
0.000 |
0.000 |
0.000 |
0.031 |
|
ND/2024/07 |
February 2026 |
7.277 |
0.000 |
4.326 |
0.000 |
0.020 |
2.687 |
0.000 |
0.000 |
0.000 |
13.750 |
0.000 |
231.310(1) |
Note: (1)
Quantity was presented in 000 kg.
Table 6.1 Summary of Monitoring Activities, Relevant Contracts, and
Corresponding Transects
|
Monitoring Activity |
Relevant Works Contract(s) |
Relevant Transect(s)/Monitoring Station(s) |
|
|
First Phase ET |
Remaining Phase ET |
||
|
Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung, Sheung Yue, and Shek Sheung Rivers and Long Valley |
ND/2024/01* |
T1, T2, T3, T5 |
- |
|
ND/2024/02* |
T1, T2, T3, T5 |
T4 |
|
|
ND/2024/03* |
T1, T2, T3, T5 |
- |
|
|
ND/2024/04* |
- |
T4 |
|
|
ND/2024/05 |
N/A(1) |
N/A(1) |
|
|
ND/2024/06* |
T1, T2, T3 |
- |
|
|
ND/2024/07* |
T1, T2, T3 |
T4 |
|
|
ND/2024/08* |
T1, T2, T3 |
T4 |
|
|
Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream, and Long Valley |
ND/2024/01*^ |
MS_01, MS_02, MS_03, MS_04, MS_05, MS_06, MS_07, MS_08, MS_09, MS_10 |
- |
|
ND/2024/02*^ |
MS_01, MS_02, MS_03, MS_04, MS_05, MS_06, MS_07, MS_08, MS_09, MS_10 |
- |
|
|
ND/2024/03* |
N/A(2) |
N/A(2) |
|
|
ND/2024/04* |
N/A(2) |
N/A(2) |
|
|
ND/2024/05 |
N/A(2) |
N/A(2) |
|
|
ND/2024/06* |
N/A(2) |
N/A(2) |
|
|
ND/2024/07*^ |
MS_11, MS_12, MS_13, MS_14, MS_15 |
- |
|
|
ND/2024/08*^ |
MS_11, MS_12, MS_13, MS_14, MS_15 |
N/A(2) |
|
|
|
|
|
|
|
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution |
ND/2024/01* |
T1 |
- |
|
ND/2024/02* |
- |
T1, T6 # |
|
|
ND/2024/03* |
T4 |
- |
|
|
ND/2024/04* |
N/A(3) |
N/A(3) |
|
|
ND/2024/05 |
T4, T6 |
- |
|
|
ND/2024/06* |
- |
T2 |
|
|
ND/2024/07* |
T3 |
- |
|
|
ND/2024/08* |
T3 |
- |
|
Remarks:
(1) Contracts that are located
relatively far from river channels.
(2) Contracts that are located
relatively far from Ma Tso Lung and Siu Hang San Tsuen streams.
(3) Contracts that are located
relatively far from the Ecological Sensitive Habitats as identified in the EIA.
(4) * = active works contracts
(ND/2024/01, ND/2024/02, ND/2024/03, ND/2024/04, ND/2024/06, ND/2024/07 and
ND/2024/08); ^ = monitoring only in April October # = conducted by the
Remaining Phase for the reporting month to cover the ecological monitoring requirement
upon the commencement of the Works Contract No. ND/2024/02.
Monitoring Methodology
Monitoring Parameters
· Abundance of birds;
· Types of habitats
utilized by birds; and
· Notable bird behaviours
such as roosting, feeding, nesting and presence of juveniles.
Monitoring Location
Table 6.2 Summary of Active Works Contracts and Corresponding Transects
|
Monitoring |
Relevant Works Contract(s) |
||||||
|
ND/2024/01 |
ND/2024/02 |
ND/2024/03 |
ND/2024/04 |
ND/2024/06 |
ND/2024/07 |
ND/2024/08 |
|
|
T1. Ng Tung River |
✓ |
✓ |
✓ |
|
✓ |
✓ |
✓ |
|
T2. Ng Tung River |
✓ |
✓ |
✓ |
|
✓ |
✓ |
✓ |
|
T3. Sheung Yue River |
✓ |
✓ |
✓ |
|
✓ |
✓ |
✓ |
|
T4. Shek Sheung River |
|
✓ |
|
✓ |
|
✓ |
✓ |
|
T5. Long Valley |
✓ |
✓ |
✓ |
|
|
|
|
Monitoring Frequency
Table 6.3 Monitoring Programme for
Waterbirds Monitoring, February 2026
|
Week |
Date |
Transect(1) |
|
1 |
2 Feb 2026 |
T4 |
|
3 Feb 2026 |
T1, T2 |
|
|
5 Feb 2026 |
T3, T4, T5 |
|
|
2 |
10 Feb 2026 |
T1, T2, T4 |
|
12 Feb 2026 |
T3, T4, T5 |
|
|
3 |
16 Feb 2026 |
T1, T2, T4 |
|
20 Feb 2026 |
T3, T4, T5 |
|
|
4 |
24 Feb 2026 |
T1, T2, T4 |
|
26 Feb 2026 |
T3, T4, T5 |
|
|
Additional Nighttime |
12 Feb 2026 |
T5 |
|
26 Feb 2026 |
Remarks:
(1) Transects T1, T2, T3, and T5
are relevant to Works Contract ND/2024/01 and ND/2024/03; Transect T4 is
relevant to Works Contract ND/2024/04; Transects T1, T2, and T3 are relevant to
Works Contract ND/2024/06; Transects T1, T2, T3 and T4 are relevant to Works
Contract ND/2024/07 and ND/2024/08; Transect T1, T2, T3, T4 and T5 are relevant
to Works Contract No. ND/2024/02.
Monitoring Results
Table 6.4 Summary Table of Waterbird Monitoring
Results Relative to Corresponding Action and Limit Levels, February, Transects
T1, T2, T3, T4 and T5
|
Monitoring Parameter |
Result in Reporting
Month |
Baseline Level in
Corresponding Month |
Action |
Limit |
|
|
T1, T2 and T3 |
|||||
|
Mean abundance of large waterbirds using Ng Tung River, Sheung Yue River and Shek Sheung River (3) |
63 |
31 |
21 |
15 |
|
|
Mean abundance of Chinese Pond Heron using Ng Tung River, Sheung Yue River and Shek Sheung River |
12 |
11 |
8 |
5 |
|
|
T4 |
|||||
|
Mean abundance of large waterbirds using Shek Sheung River (3) |
9 |
7 |
5 |
4 |
|
|
Mean abundance of Chinese Pond Heron using Shek Sheung River |
4 |
4 |
3 |
2 |
|
|
T5 Long Valley |
|||||
|
Mean Abundance of birds (all species) recorded in LVNP |
1380 |
596 |
417 |
298 |
|
|
Mean abundance of the Chinese Pond Heron |
20 |
11 |
8 |
5 |
|
|
Environmental disturbance and damage from activities in LVNP |
- |
- |
Activity likely to cause unacceptable environmental disturbance or damage noted in LVNP. |
Activity likely to cause unacceptable environmental disturbance or damage noted in LVNP. |
|
Remarks:
(1) Exceedance of Action Level
occurs when the monitoring result is lower than the Action Level.
(2) Exceedance of Limit Level
occurs when the monitoring result is lower than the Limit Level.
(3) Large waterbird species for
mean abundance calculation include Great Cormorant (Phalacrocorax carbo);
Grey Heron (Ardea cinerea); Great Egret (Ardea alba);
Intermediate Egret (Ardea intermedia); Little Egret (Egretta garzetta) and Chinese Egret (Egretta eulophotes).
Monitoring of Measures to Minimise
Impacts on Ecological Sensitive Habitats from Disturbance and Pollution
Monitoring Methodology
Terrestrial Mammal
Herpetofauna (Amphibians and
Reptiles)
Butterfly and Odonates
Monitoring Parameters
· Species composition;
· Abundance;
· Distribution for fauna
observed; and
· Species of conservation importance
would be specified.
Monitoring Location
· T1. Ma Tso Lung riparian
zone and associated wetland habitats; green belt areas E1-8, D1-8 and G1-3 in
KTN NDA; AGR
zone C2-4 and C2-2 in KTN NDA, and area north of Ng Tung River;
· T2. Fanling
North Freshwater Service Reservoir
· T3. Area west of Siu
Hang San Tsuen Stream;
· T4. South side of Fanling Highway and Castle Peak Road in the vicinity of Pak
Shek Au;
· T5. Area west and east
of the southern limit of the FLN NDA work area; and
· T6. Areas in the western
part of KTN.
Monitoring Frequency
|
Responsible ET |
Date |
Transect(1) |
|
First Phase ET |
9 Feb 2026 |
T3, T4 |
|
Remaining Phase ET |
25 Feb 2026 |
T1, T2, T6 |
Remarks:
(1)
Transect
T1 is relevant to Works Contract ND/2024/01 and Works Contract ND/2024/02;
Transect T2 is relevant to Works Contract ND/2024/06; Transect T3 is relevant
to Works Contracts ND/2024/07 and ND/2024/08; Transect T4 is relevant to Works
Contract ND/2024/03; Transect T6 is relevant to Works Contract ND/2024/02.
Monitoring Results
Terrestrial Mammals
Herpetofauna (Amphibians and
Reptiles)
Butterfly and Odonates
Summary of Monitoring Results
Table 6.6 Summary Table of Monitoring Results
for Non-aquatic Fauna Relative to Action and Limit Levels, February 2026,
Transect T1, T2, T3, T4 and T6
|
Monitoring Parameter |
Result in |
Baseline Level in Corresponding Month (February 2020) (1) |
Action Level(2) |
Limit Level(3) |
|
T1 |
||||
|
Terrestrial Mammals |
5 |
1 |
N/A |
N/A |
|
Herpetofauna |
6 |
3 |
2 |
1 |
|
Odonates |
6 |
4 |
3 |
2 |
|
Butterflies |
17 |
8 |
6 |
4 |
|
T2 |
||||
|
Terrestrial Mammals |
2 |
0 |
N/A |
N/A |
|
Herpetofauna |
3 |
0 |
N/A |
N/A |
|
Odonates |
1 |
1 |
N/A |
N/A |
|
Butterflies |
11 |
4 |
3 |
2 |
|
T3 |
||||
|
Terrestrial Mammals |
1 |
1 |
N/A |
N/A |
|
Herpetofauna |
0 |
1 |
N/A |
N/A |
|
Odonates |
0 |
5 |
4 |
3 |
|
Butterflies |
2 |
3 |
2 |
1 |
|
T4 |
||||
|
Terrestrial Mammals |
1 |
0 |
N/A |
N/A |
|
Herpetofauna |
0 |
2 |
N/A |
1 |
|
Odonates |
0 |
2 |
N/A |
1 |
|
Butterflies |
4 |
5 |
4 |
3 |
|
T6 |
||||
|
Terrestrial Mammals |
2 |
0 |
N/A |
N/A |
|
Herpetofauna |
2 |
2 |
N/A |
1 |
|
Odonates |
2 |
3 |
2 |
1 |
|
Butterflies |
3 |
3 |
2 |
1 |
Remarks:
(1)
Number
of species (species richness) recorded; the results in the reporting month for
terrestrial mammals, herpetofauna and odonates are
calculated based on the number of native species recorded along the transects.
(2) Exceedance of Action Level
occurs when the monitoring result is lower than the Action Level.
(3) Exceedance of Limit Level
occurs when the monitoring result is lower than the Limit Level.
Details
of the Influencing Factors
Survey
Summary
· Compendium Method 1O-3.1
Selection, Preparation and Extraction of Filter Material, Center
for Environmental Research Information, Office of Research and Development,
USEPA, June 1999; and Compendium Method 1O-3.5 determination of Metals in
Ambient Particulate Matter using Inductively Coupled Plasma/Mass Spectrometry
(ICP/MS., Center for Environmental Research
Information, Office of Research and Development, USEPA, June 1999.
Table 8.1 Location of Ambient
Arsenic Monitoring station
|
Monitoring Station(s) |
Location(s) |
Works Contract(s) |
|
KTN-DMS-4A(1)(2) |
Temporary Structure at Pak Shek Au |
ND/2024/01 |
Remarks:
(1)
Monitoring at the original location of KTN-DMS-4 (originally proposed in
the approved EM&A Manual) was denied as there was no electricity supply. An
alternative location (KTN-DMS-4A) was proposed by First Phase ET.
(2) The ambient
arsenic monitoring was conducted by First Phase ET during the reporting period.
Table 8.2 Ambient Arsenic Monitoring Equipment
|
Monitoring Station |
Equipment |
Manufacturer |
Model |
No. of Equipment |
|
KTN-DMS-4A(1)(2) |
Calibrator |
TISCH |
TE-5025A |
1 |
|
HVS Sampler (RSP) |
TISCH |
TE-6070X |
1 |
Remarks:
(1)
Monitoring at the original location of KTN-DMS-4 (originally proposed in
the approved EM&A Manual) was denied as there was no electricity supply. An
alternative location (KTN-DMS-4A) was proposed by First Phase ET.
(2) The ambient
arsenic monitoring was conducted by First Phase ET during the reporting period.
Table 8.3 Impact Ambient Arsenic Monitoring Parameters, Frequency and
Duration
|
Parameters |
Frequency(1) |
|
24-hour RSP (Ambient Arsenic) |
Once/ 6 days |
Remark:
1. The ambient
arsenic monitoring was conducted by First Phase ET during the reporting period.
Instrumentation
· a horizontal platform
with appropriate support to secure the samplers against gusty wind was provided;
· no two samplers were
placed less than 2 meters apart;
· the distance between the
sampler and an obstacle, such as buildings, was at least twice the height that
the obstacle protrudes above the sampler;
· a minimum of 2 meters of
separation from walls, parapets and penthouses was required for rooftop samplers;
· a minimum of 2 meters
separation from any supporting structure, measured horizontally was required;
· no furnace or
incinerator flue was nearby;
· airflow around the
sampler was unrestricted;
· the sampler was more
than 20 meters from the dripline;
· any wire fence and gate,
to protect the sampler, were not cause any obstruction during monitoring;
· permission was obtained
to set up the samplers and to obtain access to the monitoring stations; and
· a secured supply of electricity
was needed to operate the samplers
Operating/analytical procedures for the
operation of HVS
·
Prior to the
commencement of the dust sampling, the flow rate of the high
volume sampler was properly set (between 1.1 m3 /min. and 1.4
m3 /min.) in accordance with the manufacturer's instruction to
within the range recommended in USEPA Standard Title 40, CFR Part 50;
·
The power supply was
checked to ensure the sampler worked properly. On sampling, the sampler was
operated for 5 minutes to establish thermal equilibrium before placing any
filter media at the designated air monitoring station;
·
The filter holding
frame was then removed by loosening the four nuts and a weighted and
conditioned filter was carefully centered with the
stamped number upwards, on a supporting screen;
· The filter was aligned
on the screen so that the gasket formed an airtight seal on the outer edges of
the filter. The filter holding frame was then tightened to the filter holder
with swing bolts. The applied pressure was sufficient to avoid air leakage at
the edges;
· The shelter lid was
closed and secured with the aluminium strip;
· The timer was then
programmed. Information was recorded on the record sheet, which included the
starting time, the weather condition and the filter number (the initial weight
of the filter paper can be found out by using the filter number);
· After sampling, the
filter was removed and sent to the Wellab Ltd. for
weighing. The elapsed time was also recorded; and
· Before weighing, all
filters were equilibrated in a conditioning environment for 24 hours. The
conditioning environment temperature was between 25°C and 30°C and did not vary
by more than ±3°C; the relative humidity (RH) was < 50% and did not vary by more
than ±5%. A convenient working RH was 40%. Weighing results were further
analysis of RSP concentrations collected by each filter.
· The high
volume motors and their accessories were properly maintained.
Appropriate maintenance such as routine motor brushes replacement and
electrical wiring checking were made to ensure that
the equipment and necessary power supply were in good working condition; and
· High volume samplers
were calibrated at bi-monthly intervals using TE-5025A Calibration Kit
throughout all stages of the ambient arsenic monitoring.
Table 8.4 Result Summary Against Action and Limit Levels for 24-hour RSP
Monitoring Results (Ambient Arsenic)
|
Contract No. |
Monitoring Date |
Monitoring Station |
Concentration (ƞg/m3) |
AL (ƞg/m3) |
LL (ƞg/m3) |
|
ND/2024/01 |
3/2/2026 |
KTN-DMS4A* |
4.95 |
9.36 |
11.7 |
|
9/2/2026 |
5.45 |
||||
|
14/2/2026 |
4.15 |
||||
|
20/2/2026 |
3.22 |
||||
|
25/2/2026 |
4.88 |
Remark:
* The 24-hour RSP
monitoring for ambient arsenic was conducted by First Phase ET during the
reporting period.
Ψ Excavation
Locations:
N/A
Ψ Manholes and Chambers:
N/A
Ψ Relocation of monitoring wells: N/A
Ψ Any other Confined
Spaces: N/A
Table 10.1 Location of Construction Vibration Monitoring
|
EP No. |
Contact No. |
Monitoring Station(s) |
Nature of Cultural Heritage |
Location(s) |
|
NIL |
NIL |
NIL |
NIL |
NIL |
Table 10.2 Vibration Monitoring Plan
|
EP No. |
Contact No. |
Monitoring Station(s) |
Distance with Construction Works |
Monitoring Plan |
|
NIL |
NIL |
NIL |
Within 50m
Within 75m
Within 100m |
Daily assessment is required Bi-daily assessment is required Weekly assessment is required |
Remarks:
(1)
Baseline condition survey was conducted for built heritage features at
G302, G303, G308, KT26, KT53, KT65 and HKT03 for ND/2024/01 under
EP-468/2013/A, G102, G202, G203, G303 and HKT03 for ND/2024/03 under
EP-465-2013A and EP-466/2013A. As G102, G202, G203, G302, G303, G308, HKT03,
KT26, KT 53 and KT65 were not within the assessment area of the related
construction work, no construction vibration monitoring was conducted for the
built heritage in the reporting month.
Table 10.3 Levels of Alert, Alarm and Actions for Tilting, Vibration and
Settlement
|
Monitoring Types |
Alert |
Alarm |
Acton |
|
Tilting |
1:2000 |
1:1500 |
1:1000 |
|
Settlement |
6 mm |
8 mm |
10 mm |
|
Ground Settlement |
15 mm |
20 mm |
25 mm |
|
Vibration (PPV) |
5 mm/s |
6 mm/s |
7.5 mm/s |
Table 11.1
Site Observations at Works Contract No. ND/2024/01, ND/2024/02, ND/2024/03, ND/2024/04,
ND/2024/06 and ND/2024/07 during the Reporting Period
|
|
Works Contracts |
Inspection Date |
Key Observations/ Reminders |
Follow-up Action |
|
ND/2024/01 |
3 February 2026 |
Observation:
1.Impervious sheeting should be provided for excavated or stockpile of dusty material at Portion 59. |
1.Impervious sheeting was provided for excavated or stockpile of dusty material at Portion 59. |
|
|
Reminder:
1.The Contractor was reminded to provide tarpaulin for exposed slope surfaces at Portion 10, 11, 23, 42. |
Nil |
|||
|
12 February 2026 |
Observation:
1.Impervious sheeting should be provided for excavated or stockpile of dusty material at Portion 40.
2. The area within 30m of construction site entrance or exit shall be kept clear of dusty materials in order to avoid fugitive dust emission at Portion 40.
3. Drip tray should be provided for the chemical container at Portion 40 in order to avoid potential contamination. |
1.Exposed earth is properly treated by compaction.
2.The area within 30m construction site entrance or exit was kept clear.
3. The chemical containers were removed.
|
||
|
Reminder:
1.The Contractor was reminded to provide impervious sheeting for excavated or stockpile of dusty material at Portion 7.
2.Contractor was reminded to prevent surface runoff from entering public drainage at Portion 7.
3.Contractor was reminded that NRMM label in an appropriate colour shall be affixed onto the machinery at Portion 7. |
Nil |
|||
|
16 February 2026 |
Observation:
Nil |
Nil |
||
|
Reminder:
Nil |
Nil |
|||
|
24 February 2026 |
Observation:
Nil |
Nil |
||
|
Reminder:
1. The Contractor was reminded to provide water spraying to the haul road in order to avoid fugitive dust emission at Portion 40. |
Nil |
|||
|
|
ND/2024/02 |
12 February 2026 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
|
16 February 2026 |
Observation:
Nil |
Nil |
|
|
|
Reminder:
Nil |
Nil |
||
|
|
27 February 2026 |
Observation:
Nil |
Nil |
|
|
|
Reminder:
1.At Area D, Contractor was reminded to perform regular water spraying on areas of exposed earth. |
Nil |
||
|
ND/2024/03 |
2 February 2026 |
Observation:
Nil |
Nil |
|
|
|
|
|
Reminder:
Nil |
Nil |
|
|
12 February 2026 |
Observation:
1. The contractor was reminded that to reinstate the integrity of earth bunds/ sandbags barrier to fully enclose the works area and properly deploy the silt curtain to completely surround the Sheung Yue River worksite. |
1.The earth bund and silt curtain were fully enclosed the works area. |
|
|
Reminder:
1.The Contractor was reminded that silencers or mufflers or any mitigation measures should be provided to reduce the noise level during the construction works at Tsung Pak Long.
2.The Contractor was reminded that various waste should be disposed of in a timely manner for the temporary waste collection container at Sheung Yue River. |
Nil |
|||
|
16 February 2026 |
Observation:
Nil |
Nil |
||
|
Reminder:
Nil |
Nil |
|||
|
25 February 2026 |
Observation:
Nil |
Nil |
||
|
Reminder:
Nil |
Nil |
|||
|
ND/2024/04 |
6 February 2026 |
Observation:
Nil |
Nil |
|
|
Reminder:
1. Contractor was reminded to place sandbags to seal site boundary to prevent site runoff onto public roads at Portion 2 |
Nil |
|||
|
13 February 2026 |
Observation:
Nil |
Nil |
||
|
Reminder:
Nil |
Nil |
|||
|
26 February 2026 |
Observation:
Nil |
Nil |
||
|
Reminder:
Nil |
Nil |
|||
|
ND/2024/06 |
2 February 2026 |
Observation:
Nil |
Nil |
|
|
Reminder:
1.The Contractor was reminded to provide full water spraying on main haul road at Portion C.
2.The Contractor was reminded to provide full water spraying on main haul road at Portion D.
3.The Contractor was reminded to provide impervious sheeting for placing the break head to prevent oil spillage at Portion D. |
Nil |
|||
|
9 February 2026 |
Observation:
1.Drip tray should be provided for storing chemicals at Area C. |
1. The chemical was removed. |
||
|
Reminder:
1.The Contractor was reminded to cover stockpiles with tarpaulin when they are not in use at Portion C and Portion F.
2. The Contractor was reminded to provide water spraying on main haul road at Area C.
3. The Contractor was reminded to replace the broken acoustic mat wrapped around the breaker head at Portion A. |
Nil |
|||
|
23 February 2026 |
Observation:
Nil |
Nil |
||
|
Reminder:
1. The Contractor was reminded to cover exposed slope for dust suppression when no works are performed nearby at Portion A. |
Nil |
|||
|
ND/2024/07 |
5 February 2026 |
Observation:
Nil |
Nil |
|
|
Reminder:
1. Any excavated or stockpile of dusty material should be covered entirely by impervious sheeting when no construction work occurred at Road L2. |
Nil |
|||
|
12 February 2026 |
Observation:
1. Impervious sheeting should provide for placing the construction equipment which involves the use of chemicals to prevent oil spillage at Area B. |
1. Impervious sheeting has been provided. |
||
|
Reminder:
1. Any excavated or stockpile of dusty material should be covered entirely by impervious sheeting when no construction work occurred at Area L. |
Nil |
|||
|
26 February 2026 |
Observation:
Nil |
Nil |
||
|
Reminder:
1. Any excavated or stockpile of dusty material should be covered entirely by impervious sheeting when no construction work occurred at Areas C and P. |
Nil |
|||
Table 11.2 Photographic Records and Implementation Status of Measures
for Ecological Impacts
|
Works Contracts |
EP No. |
Photographic Record |
Implementation Status |
|
ND/2024/01 |
EP-467/2013/A
(Condition 2.9) |
To minimise adverse impacts
on habitats of ecological importance in the vicinity of the Project, 2m high
solid dull green site barrier fences shall be erected around all active works
areas. |
^ |
|
EP-468/2013/A (Condition 2.11) |
|||
|
ND/2024/03 |
EP-465/2013/A (Condition 2.9) |
To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas. |
^ |
|
EP-466/2013/A (Condition 2.9) |
|||
|
EP-467/2013/A (Condition 2.11) |
|
Implementation status: |
^ Mitigation measure was fully implemented |
|
* Observation / reminder was made during site audit but improved / rectified by the contractor |
|
|
# Observation / reminder was made during site audit but not yet improved / rectified by the contractor |
|
|
X Non-compliance of mitigation measure |
|
|
Non-compliance but rectified by the contractor |
|
|
|
N/A Not Applicable at this stage as no such site activities were conducted in the reporting period |
Works
Contract No. ND/2024/01:
· All Site
Resumption Area(s)
1. Tree
survey
2. Site
Clearance
· Portion
III (3), IV (4), V (5), VII (7) and XXXV (35)
1. Site
Clearance and Demolition
2. Site
Formation
3. Asbestos
Abatement Works
4. Construction
of Temporary Drainage Diversion
· Portion
VIII (8)
1. Site Clearance & Demolition
2. Asbestos Abatement Works
· Portion
XVIII (18), XXXVIII (38)
1. Excavation works
2. Construction of CHC Box Culvert
· Portion
XI (11), XXIII (23)
1. Formwork Erection, Rebar Fixing, Concreting Works
· Portion
XL (40)
1. Retaining
Wall Construction
2. Drainages
System Construction
3. ELS
work
· Portion
LIX (59)
1. Treatment
of High Arsenic-Containing Soil (HAS)
· Portion
XVII (17), XVII (18), XXI (21), XXXIV (34), XXXV (35), XLI (41), XLII (42)
1. Excavation
Works
2. Drainage
Pipe Installation
3. ELS
Works
· Portion XXV (25), XXVII (27), XXXIII (33),
XLII (42) and XLIV (44)
1. Site Clearance
2. Site Formation
3. Construction of Box Culvert
Works Contract
No. ND/2024/02:
· Site clearance in Area B, D, L
· Site formation works in Area D
· Temporary storage fill bank in Kwu
Tung Grass Soccer Pitch
· Demolition works for Community Sports in Area J
Works
Contract No. ND/2024/03:
Fanling Highway & Castle Peak Road area
· Pak Sau
Road Po Lau Road
1. Relocation/Reprovision/Removal
of Existing TCSS, Fire Hydrant, Signage & Streetlighting
2. Tree
Works
· Po Lau
Road Sheung Yue River
1. Asbestos
Removal Works at Portion IX
2. Box
Culvert Bay 37 Bay 42 ELS
· TTA Stage
1 Works
1. Tree
Works
2. Removal
or relocation of directly impacted Shrine/historical building at HKT08 &
KT72
3. Demolish
of Central Divider & Barrier along FL Highway E/B
New Tsung Pak Long Road
· Box
culvert Bay 10 to 12, 14 to 16 Drainage/Watermains
1. Drainage,
Sewerage & Watermain with Backfilling at Box Culvert Bay 15 & 16
2. Box
Culvert Bay 10-13 & 14 ELS
3. Removal
of ELS and Temp Road Diversion
· Box
culvert Bay 17 to 19 & Drainage/Watermains
1. Box
Culvert Bay 17 to 19 ELS, Base Slab, Wall and Top Slab
· TTA Stage
1B
1. Box
Culvert Bay 3, 5 to 7, 7A ELS
2. Box
Culvert Base Slab
· Retaining
Wall RW05A
1. RW05A
ELS
2. Base
Slab and Wall
· Kwu Tung Road Bridge
1. Site
Clearance and Tree Works
2. Site
formation and cutback the existing slope
3. Foundation
& Piling
· Works
Areas WA1, WA2, WA3, WA4 & WA5
1. Site
Clearance and Site Formation at PMs Site Office
2. Temporary
Drainage
3. Asbestos
removal
Fanling Highway Cross River Bridge (along Sheung Yue
River)
· Portion
XI East Abutment & pier foundation (No Work: Wet Season (1 Apr 31 Oct))
1. Trial
Pits for UUs
2. Piling
Works
· Road L3
Viaduct
1. Piling
Works
2. Pile
Cap L3A-02
· Kwu Tung Interchange Foundation & Substructure
Bridge B1 & C1
1. Piling
Works
2. ELS
· Bridge B2
& C2
1. Piling
Work
· Footbridges
No. 4 at TTA Stage 1
1. Ground
Investigation
2. Underground
Utilities Works
· Footbridges
No. 5 at TTA Stage 2
1. Predrilling
· Widening
of Existing Bridge No.N526
1. Tree
Works
2. ELS
3. Piling
Works
Contract No. ND/2024/04:
1. Site
Clearance
2. Site
Establishment
3. Tree
Felling
4. Existing
Sewage Diversion
5. Trial
Pit
6. Predrilling
7. Ground
Investigation
8. Demolition
of Existing Structures
9. Bored
Piling
10.Pier Cap Construction
11.Sheet Piling
12.Soil Nailing
13.Shotcreting
Works Contract No. ND/2024/06:
· Portion A
1. Excavation to +90 mPD of Portion
A
2. Forming Haul Road form
Area C to Portion A
· Portion C
1. Trench and Watermans Laying
Works of Portion C
· Portion D
1.
Trench and Watermans
Laying Works of Portion D
2.
Demolition of Thrust Blocks of
Portion D
· Portion E
& F
1.
Trench and Watermans
Laying Works of Portion E & F
· Area N
1. Jacking Pit
Excavation
Works
Contract No. ND/2024/07:
1. Site Clearance
2. Site Formation
3. Ground Investigation
4. Pre-bored Socketed H Pile
Construction
5. Pier Construction
6. Lift Tower Construction
7. ABWF Works
8. Bridge Deck Connection (Footbridge
FB5)
9. Drainage Construction
10.Storm Pipe Construction
11.Improvement of Junction
12.Road Improvement & Works
13.Open Landscaping Works
14.Assembly Yard for Bridge Construction
15.Storage Yard for Concrete Pipe
16.Sewage Construction
17.Drainage Construction
18.New Shrine Construction
19.Rebar Yard
20.Tree Felling
21.Asbestos Containing Materials Survey & Removal
22.Old Shine Removal
23.Temporary Road Construction
24.Box Culvert 5 Construction
25.Land Contamination (Environmental Ground Investigation)
26.Internal Movement, Importation & Exportation of C&D materials
Works
Contract No. ND/2024/08:
1. The construction work will be commenced in March 2026.
Dust
Regular watering to reduce
dust emissions from exposed site surface;
Stockpile of dusty
materials shall be covered entirely by impervious sheeting;
Provide vehicles
washing facilities at all site exits to wash away any
dusty materials from vehicle body;
NRMM Labels should be
displayed on the applicable equipment on site by the Contractor;
Provision of water
sprinklers along the haul road for dust suppression.
Noise
Only well-maintained
plant should be operated on-site, and plant should be maintained regularly
during the construction programme; and
Quality Powered
Mechanical Equipment (QPME) should be adopted as far as possible.
Water Quality
No effluent discharge
would be allowed before acquired the effluent discharge license;
Surface run-off from
construction sites should be discharged into dedicated discharge point via
adequately designed sand/ silt removal facilities;
Channels/ earth bunds/
sandbags barriers should be provided on site to properly direct stormwater to
silt removal facilities;
Silt removal
facilities, channels and manholes should be maintained, and the deposited silt
and grit should be removed regularly;
Open stockpiles of
construction materials on sites should be covered with tarpaulin or similar
fabric during rainstorms; and
Perimeter channels
should be provided on site boundaries where necessary to intercept stormwater
run-off from outside the site so that it will not wash across the site.
Waste Management
Provision of sufficient
waste disposal points and regular collection of waste;
Regular cleaning and
maintenance programme for drainage system; and
Chemical containers
shall be stored with drip tray underneath.
Landscape and Visual
Construction activities
shall be carefully designed to minimize impact on existing retained trees.
Land Contamination
Stockpiling site(s) should
be lined with impermeable sheeting and bunded. Stockpiles should be properly
covered by impermeable sheeting to reduce dust emission during dry season or
contaminated run-off during rainy season. Watering should be avoided on
stockpiles of soil to minimise runoff.
Landfill
Gas Hazard
No Smoking and No Naked Flame notices in
Chinese and English should be posted prominently around the construction site.
Ecology
Properly erect and
maintain 2m high solid barriers for protection.
An individual of orchid
Eulophia cernua was found growing underneath the
pipeline adjacent to the access road leading to the summit of the Table Hill
Freshwater Service Reservoir for Contract No. ND/2024/06. The species of
conservation importance should be fenced off for protection to minimise the
potential impacts aroused from nearby construction activities as far as
possible.