_R5_(Verified)_files/image002.jpg)
_R5_(Verified)_files/image004.jpg)
Contents
1.3 Construction
Works Programme and Construction Works Area
1.4 Summary
of Environmental Status
2.3 Monitoring
Parameter and Frequency and Duration
2.5 Monitoring
Methodology and QA/QC Procedure
2.6 Action
and Limit Level for Air Quality Monitoring
3 Construction
Noise Monitoring
3.3 Noise
Monitoring Parameter, Frequency and Duration
3.4 Monitoring
Equipment, Methodology and QA / QC Procedure
3.5 Maintenance
and Calibration
6.4 Man Kam
To Road Egretry Monitoring
8 Land
Contamination (Ambient Arsenic Monitoring)
8.4 Monitoring
Parameters, Frequency and Duration
8.5 Monitoring
Methodology and QA/QC Procedure
8.7 Laboratory
Measurement / Analysis
9.2 Monitoring
Parameters and Frequency
10.3 Monitoring
Parameters and Frequency
11 Environmental
Site Inspection and Audit
11.1 Implementation
Status of Environmental Mitigation Measures
12 Summary
of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions
12.2 Summary
of Environmental Non-Compliance
12.3 Summary
of Environmental Complaint
12.4 Summary
of Environmental Summon and Successful Prosecution
13.1 Works and
Potential Environmental Issues in the next Reporting Period
14.2 Comments/
Recommendations
Figures
Figure 1.1 Location and Site Layout Plan (KTN)
Figure 1.2 Location and Site Layout Plan (FLN)
Figure 2.1 Location of Air Quality Monitoring Stations for KTN NDA
Figure 2.2 Location of Air Quality Monitoring Stations for FLN NDA
Figure 3.1 Location of Noise Monitoring Stations for KTN NDA
Figure 3.2 Location of Noise Monitoring Stations for FLN NDA
Figure 8.1 Location
of Ambient Arsenic Monitoring Stations for KTN NDA
Appendix 1.1 Construction Programme
Appendix 1.2 Project Organization Chart
Appendix 1.3 Implementation Status of Environmental
Mitigation Measure
Appendix 2.1 Impact Monitoring Schedule during the reporting
period
Appendix 2.2 Impact Air Quality Monitoring
Data &
Graphical Presentations & Calibration Certificates
Appendix 2.3 Weather Information during the
Reporting Period
Appendix 2.4 Event and Action Plan for Construction
Dust
Appendix 3.1 Impact Noise Monitoring Data & Graphical
Presentations & Calibration Certificates
Appendix 3.2 Event and Action Plan for Construction
Noise
Appendix 5.1 Summary of Monthly Waste Flow Table
Appendix 6.1
Detailed Results of the Ecological Waterbird Monitoring during this Reporting
Period
Appendix 6.2
Detailed Results of the Ecological Non-aquatic Monitoring during this Reporting
Period
Appendix 6.3
Event and Action Plan for Ecological Monitoring
Appendix 7.1 Event and Action
Plan for Landscape and Visual
Appendix 8.2 Event and Action
Plan for Ambient Arsenic Monitoring
Appendix 12.1
Statistical Summary of Environmental Complaints, Summons and Prosecution
Appendix 13.1
Impact Monitoring Schedule of Next Reporting Month
A1. This is the 15th Monthly Environment Monitoring and Audit (EM&A) Report for Remaining Phase Development of Kwu Tung North and Fanling North New Development Areas (the Project) for the reporting period between 1 and 31 March 2026. This report was prepared by Aurecon Hong Kong Limited (Aurecon) under Service Contract No. NDO 05/2024 Remaining Phase Development of Kwu Tung North and Fanling North New Development Areas - Environmental Team (hereinafter called the Service Contract).
A2. Since only construction works were undertaken under Works Contract No. ND/2024/01, Works Contract No. ND/2024/02, Works Contract No. ND/2024/03, Works Contract No. ND/2024/04, Works Contract No. ND/2024/06 and Works Contract No. ND/2024/07 during the reporting month, this report documents the findings of EM&A works at Works Contract No. ND/2024/01, Works Contract No. ND/2024/02, Works Contract No. ND/2024/03, Works Contract No. ND/2024/04, Works Contract No. ND/2024/06 and Works Contract No. ND/2024/07 under the Project during the reporting period only. No construction works occurred in the remaining contracts during the reporting period for Works Contract ND/2024/05 and ND/2024/08.
A3. This Project involves eight (8) Environmental Permits (EPs) (i.e. EP-465/2013/A, EP-466/2013/A, EP-467/2013/A, EP-468/2013/A, EP-470/2013/A, EP-471/2013/A, EP-472/2013/A and EP-476/2013). Details of each EPs are summarised in Table A1.
Table A1 Works Contracts under
relevant Environmental Permits in the Reporting Month
|
Environmental Permit No. |
Works Contracts |
Title of Designated
Project |
Designated Project (DP) |
|
EP-465/2013/A |
ND/2024/03 |
San Tin Highway and
Fanling Highway Kwu Tung Section Widening (Between San Tin Interchange and Po
Shek Wu Interchange) |
DP1 |
|
EP-466/2013/A |
ND/2024/03 |
Castle Peak Road Diversion |
DP2 |
|
EP-467/2013/A |
ND/2024/01 |
Kwu Tung North New
Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and
Pak Shek Au Interchange Improvement |
DP3 |
|
EP-468/2013/A |
ND/2024/01 |
Kwu Tung North New
Development Area Road D1 to D5 |
DP4 |
|
EP-469/2013 |
- |
Sewage Pumping Stations in
Kwu Tung North New Development Area |
DP5 |
|
EP-470/2013/A |
ND/2024/06 |
Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works |
DP7 |
|
EP-471/2013/A |
ND/2024/04 |
Po Shek Wu Interchange Improvement |
DP8 |
|
EP-472/2013/A |
ND/2024/08 |
Fanling Bypass Western
Section |
DP9 |
|
EP-473/2013/A |
- |
Fanling Bypass Eastern
Section |
DP10 |
|
- |
Shek Wu Hui Sewage Treatment
Works - Further Expansion at Fanling North New Development Area |
DP11 |
|
|
ND/2024/07 ND/2024/08 |
Sewage Pumping Stations in
Fanling North New Development Area (FLNDA) |
DP13 |
A4. Apart from the construction works undertaken under Works Contract No. ND/2024/01 since 20 January 2025, construction works under Works Contract No. ND/2024/07 commenced since 27 February 2025, construction works under Works Contract No. ND/2024/06 commenced since 10 March 2025, construction works under Works Contract No. ND/2024/04 commenced since 10 May 2025, construction works under Works Contract No. ND/2024/03 commenced since 2 June 2025, construction works under Works Contract No. ND/2024/02 has also been commenced since 9 February 2026. No construction works occurred in the remaining Works Contracts (i.e. Works Contract ND/2024/05 and ND/2024/08) during the reporting period. The commencement dates of each Works Contracts are summarized in Table A2.
Table
A2 Commencement Dates of Each Works Contracts
|
Works Contracts |
Commencement Dates |
|
ND/2024/01 |
20 January 2025 |
|
ND/2024/02 |
9 February 2026 |
|
ND/2024/03 |
2 June 2025 |
|
ND/2024/04 |
10 May 2025 |
|
ND/2024/05 |
Not Yet
Commenced |
|
ND/2024/06 |
10 March 2025 |
|
ND/2024/07 |
27 February 2025 |
|
ND/2024/08 |
April 2026 (Tentative) |
A5.
A summary of construction
activities undertaken during the reporting period is presented below:
Works
Contract No. ND/2024/01:
· All Site Resumption Area(s)
1.
Tree survey
2.
Site
Clearance
· Portion III (3), IV (4), V (5), VII (7) and XXXV
(35)
1.
Site
Formation
· Portion VI (6), XVIII
(18), XXXVIII (38)
1.
Site
Clearance
2.
Excavation
· Portion VIII (8)
1.
Site
Clearance &
Demolition
2.
Asbestos
Abatement Works
· Portion XI (11), XXIII (23)
1.
Formwork
Erection, Rebar Fixing, Concreting Works
· Portion XL (40)
1.
Retaining
Wall Construction
2.
Drainages
System Construction
3.
ELS
work
· Portion LIX (59)
1.
Treatment of
High Arsenic-Containing Soil (HAS)
· Portion XVII (17), XVII (18), XXI (21), XXXIV (34),
XXXV (35), XLI (41), XLII (42)
1.
Excavation
works
2.
Drainage Pipe Installation
· Portion XII (12), XV (15), XXV (25), XXVII (27), XXX (30), XXXI (31), XXXII (33), XLII (42) and XLIV (44), Portion LI
(51)
1.
Site
Clearance
· Portion XVI (16), XLII (42) and LIII (53)
1.
Site
Clearance & Demolition
n
n Works Contract No. ND/2024/02:
· Site clearance in Area B, D, L
· Site formation works in Area D
· Temporary storage fill bank in Kwu Tung Grass
Soccer Pitch
· Demolition works for Community Sports in Area J
· Asbestos survey in the resumed areas
Works
Contract No. ND/2024/03:
Fanling Highway & Castle Peak Road area
· Pak Sau Road Po Lau Road
1.
Tree Works
· Po Lau Road Sheung Yue River
1.
Asbestos
Removal Works at Portion IX
2.
Box Culvert
Bay 37 Bay 42 ELS
3.
Tree Works
· TTA Stage 1 Works
1.
Tree Works
New Tsung Pak Long Road
· Box culvert Bay 10 to 12, 14 to 16 Drainage/Watermains
1.
Drainage,
Sewerage & Watermain with Backfilling at Box Culvert Bay 15 & 16
2.
Box Culvert
Bay 14 ELS
· Box culvert Bay 17 to 19 & Drainage/Watermains
1.
Box Culvert
Bay 17 to 19 ELS, Base Slab, Wall and Top Slab
2.
Box culvert
Bay 17 & 19 Base Slab
· Retaining Wall RW01
1.
Pre-drilling
· Retaining Wall RW05A
1.
RW05A ELS
· Kwu Tung Road Bridge
1.
Site
Clearance and Tree Works
2.
Site
formation and cutback the existing slope
3.
Predrilling
4.
Foundation
& Piling
· Works Areas WA1, WA2, WA3, WA4 & WA5
1.
Site
Formation at PMs Site Office
2.
Site
Clearance, haul road and Temporary Drainage
3.
Asbestos
removal
Fanling Highway Cross River Bridge (along Sheung Yue River)
· Portion XI East Abutment & pier foundation
1.
Trial Pits
for UUs
2.
Piling Works
· Road L3 Viaduct
1.
Piling Works
2.
Pile Cap
L3A-02
· Kwu Tung Interchange Foundation & Substructure
- Bridge B1 & C1
1.
Piling Works
· Widening of Existing Bridge No.N526
1.
Tree Works
2.
ELS
3.
Pre-drilling
n
n Works Contract No. ND/2024/04:
· Site Clearance
· Site Establishment
· Tree Felling
· Trial Pit
· Pre-drilling
· Ground Investigation
· Existing Sewage Diversion
· Demolition of Existing Structures
· Haul Road Construction
· Bored Piling
· ELS Construction
· Slope Works
· Sheet Piling
n
n Works Contract No. ND/2024/06:
· Portion A
1.
Excavation to +90 mPD of Portion A
2.
Forming Haul Road from Area C to Portion A
· Portion C, Portion D, Portion E and Portion F
1.
Trench and Watermains Laying Works
· Pit B and Pit C
1.
Excavation
n
Works Contract No. ND/2024/07:
· Area C
1.
Tree Felling
2.
Site Formation
· Area D and Area E
1.
Site Formation
2.
Asbestos Removal
· Area G
1.
Site Clearance
2.
Site Formation
3.
Asbestos Removal
· Area H, Area I and Area R
1.
Asbestos Removal
· Area J
1.
Road Construction
· Area K
1.
Sewerage (DN1350) Construction Road Construction, Site Clearance
· Area O
1.
New Shrine Construction
· Area P
1.
Site Formation
2.
Drainage Construction
· Area Q
1.
Temporary Road Construction
2.
Drainage Construction
3.
Tree Transplant (1st Pruning)
4.
Storm Pipe (DN1650) Construction
5.
Tree Felling
· Portion 1b
1.
Assembly Yard for Bridge Construction
2.
Storage Yard for Concrete Pipe
· Portion 3b
1.
Sewerage Construction
· Portion 6c
1.
Improvement of Junction
· Portion 9b
1.
Rebar Yard
· Footbridge FB-4 (North)
1.
Lift Tower Construction
2.
ABWF Works
· Footbridge FB-4 (South)
1.
Piling Works
2.
ABWF Works
· Footbridge FB-5
1.
Pier Head Construction
2.
Lift Tower Construction
3.
Sump Pit Construction
n
Works Contract No. ND/2024/05 and ND/2024/08:
· No construction work during the reporting period.
A6. The environmental monitoring activities, including 1-hour Total Suspended Particulates (TSP) monitoring, 24-hour TSP monitoring, noise monitoring, ecological survey, 24-hour Respirable Suspended Particulates (RSP) (Ambient Arsenic) monitoring for land contamination and environmental site inspection, were undertaken by Environmental Team (ET) under Service Contract No. NDO 04/2019 (i.e. First Phase ET Wellab) and under Service Contract No. NDO 05/2024 (i.e. Remaining Phase ET - Aurecon) during the reporting period in accordance with the approved Updated EM&A Manual. A summary of the monitoring and audit activities during the reporting period is presented in Table A3.
Table
A3 Summary of EM&A Activities in the Reporting Period
|
EM&A |
Monitoring Station(s) |
Works Contract(s)(5) |
|||||||
|
ND/2024/01 |
ND/2024/02 |
ND/2024/03 |
ND/2024/04 |
ND/2024/05 |
ND/2024/06 |
ND/2024/07 |
ND/2024/08 |
||
|
1-hour TSP Monitoring(1) |
KTN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS4(B)(2)(3) |
3, 9, 13, 19, 25, 31 March 2026 |
N/A |
3, 9, 13, 19, 25, 31 March 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
4, 10, 16, 20, 26 March 2026 |
N/A |
|
|
FLN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
3, 9, 13, 19, 25, 31 March 2026 |
N/A |
|
|
FLN-DMS6(A)(2)(3) |
N/A |
N/A |
5, 11, 17, 23, 28 March 2026(6) |
N/A |
N/A |
N/A |
N/A |
||
|
FLN-DMS7(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
24-hour TSP Monitoring(1) |
KTN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS4(B)(2)(3) |
3, 9, 13, 19, 25, 31 March 2026 |
N/A |
3, 9, 13, 19, 25, 31 March 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
3, 9, 13, 19, 25, 31 March 2026 |
N/A |
|
|
FLN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS5(A)(2)(3) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
3, 9, 13, 19, 25, 31 March 2026 |
N/A |
|
|
FLN-DMS6(A)(2)(3) |
N/A |
N/A |
5, 11, 17, 23, 28 March 2026(6) |
N/A |
N/A |
N/A |
N/A |
||
|
FLN-DMS7(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Noise Monitoring(1) |
CP-KTN-NMS1(2) |
5, 11, 17, 23 March 2026(6) |
5, 11, 17, 23 March 2026(6) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
CP-KTN-NMS2(2) |
3, 9, 19, 25, 31 March 2026 |
3, 9, 19, 25, 31 March 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS3(2) |
3, 9, 19, 25, 31 March 2026 |
3, 9, 19, 25, 31 March 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
3, 9, 19, 25, 31 March 2026 |
N/A |
N/A |
|
|
CP-KTN-NMS6(2) |
3, 9, 19, 25, 31 March 2026 |
3, 9, 19, 25, 31 March 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS7(2) |
5, 11, 17, 23 March 2026(6) |
5, 11, 17, 23 March 2026(6) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
4, 10, 16, 26 March 2026 |
N/A |
||
|
CP-FLN-NMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS4(A)(2)(3) |
N/A |
N/A |
N/A |
6, 12, 18, 24, 30 March 2026(6) |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
6, 12, 18, 24, 30 March 2026(6) |
N/A |
|
|
CP-FLN-NMS6(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
6, 12, 18, 24, 30 March 2026(6) |
N/A |
|
|
Ecological Monitoring (4) |
Monitoring of Measures to Minimise Disturbance to Water Birds on Ng
Tung River, Sheung Yue River, and Long Valley |
Weekly Monitoring:
2, 5, 9, 11, 17, 20, 23, 24, 30, 31 March 2026 (Transect T1, T2, T3 and T5)
|
Weekly Monitoring: 2, 3, 5, 9, 10, 11, 12, 17, 19, 20, 23, 24, 26, 30,
31 March 2026 (Transect T1, T2, T3, T4 and T5)
|
Weekly Monitoring:
2, 5, 9, 11, 17, 20, 23, 24, 30, 31 March 2026 (Transect T1, T2, T3 and T5)
|
Weekly Monitoring: 3, 5,
10, 12, 17, 19, 24, 26, 31 March 2026 (Transect T4) |
N/A |
Weekly Monitoring:
2, 5, 9, 11, 17, 20, 23, 24, 30, 31 March 2026 (Transect T1, T2, T3 and T5) |
Weekly Monitoring: 2, 3, 5, 9, 10, 11, 12, 17,
19, 20, 23, 24, 26, 30, 31 March 2026 (Transect T1, T2, T3 and T4) |
Weekly Monitoring: 2, 3, 5, 9, 10, 11, 12, 17,
19, 20, 23, 24, 26, 30, 31 March 2026 (Transect T1, T2, T3 and T4) |
|
Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and
Siu Hang San Tsuen Stream |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Monitoring of Measures to Minimise Impacts on Ecological Sensitive
Habitats from Disturbance and Pollution |
Monthly Monitoring: 6 March 2026 (Transect T1) |
Monthly Monitoring: 6 March 2026 (Transect T1 and T6) |
Monthly Monitoring: 3 March 2026 (Transect T4) |
N/A |
N/A |
Monthly Monitoring: 25 March 2026 (Transect T2) |
Monthly Monitoring: 3 March 2026 (Transect T3) |
Monthly Monitoring: 3 March 2026 (Transect T3) |
|
|
24-hour RSP (Ambient Arsenic) Monitoring for Land
Contamination (1) |
KTN-DMS-4A(2)(3) |
3, 9, 13, 19, 25, 31 March 2026 |
N/A |
3, 9, 13, 19, 25, 31 March 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Water Quality Monitoring(1) |
KTN-IS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-CS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-IS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-CS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Landfill Gas Monitoring |
250m Landfill Consultation Zone of Ma Tso Lung
Landfill |
N/A(7) |
N/A(7) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Environmental Site Inspection |
Site Area under Works Contract No. ND/2024/01 |
3, 10, 19, 27 March 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Site Area under Works Contract No. ND/2024/02 |
N/A |
3, 10, 19, 27 March 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/03 |
N/A |
N/A |
2, 9, 20, 25, 30 March 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/04 |
N/A |
N/A |
N/A |
6, 13, 20, 24 March 2026 |
N/A |
N/A |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/06 |
N/A |
N/A |
N/A |
N/A |
N/A |
2, 9, 16, 23, 30 March 2026 |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/07 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
5, 12, 19, 26 March 2026 |
N/A |
|
Remarks:
(1)
For 1-hour and 24-hour TSP & 24-hour RSP (Ambient Arsenic) monitoring, monitoring stations that are specifically
within the 500m buffer area projected from the site boundary of works
contract(s) will be considered being the representative monitoring stations for
the corresponding works contract(s) and the associated impact monitoring
exercises will be kicked off once the nearest works contracts have been
commenced and undertaken during the reporting period/month.
For Noise
Monitoring, monitoring stations that are specifically within the 300m buffer
area projected from the site boundary of works contract(s) will be considered
being the representative monitoring stations for the corresponding works
contract(s) and the associated impact monitoring exercises will be kicked off
once the nearest works contracts have been commenced and undertaken during the
reporting period/month.
(2)
New monitoring station IDs are presented. The
corresponding monitoring station IDs are as follows:
|
1-hour and 24-hour TSP / 24-hour RSP
(Ambient Arsenic) KTN-DMS1 = DMS1 |
Noise CP-KTN-NMS1
= CP-NMS1 CP-KTN-NMS7 = CP-NMS4 |
(3) Alternative
monitoring stations to the corresponding original monitoring stations.
(4) The monitoring date for the reporting month
was conducted by the ET from the First Phase of KTN/FLN NDAs Project, except
Transect T4 for the ecological monitoring item Monitoring of
Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue
River, and Long Valley, and Transect T2 for the ecological monitoring item Monitoring
of Measures to Minimise Impacts on Ecological Sensitive Habitats from
Disturbance and Pollution. No
ecological monitoring was conducted for the Monitoring of Measures to Minimise
Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream for this reporting
month as this monitoring is only conducted during wet season (April October).
Detailed divisions of work between First Phase ET and Remaining Phase can be
referred to Section 6 and relevant appendix.
(5) N/A No relevant monitoring is required
according to the approved updated EM&A Manual.
(7) As confirmed by the Supervisor Team, no ground disturbance works were
carried out in the work area within 250m Landfill Consultation Zone of Ma Tso
Lung Landfill including construction of the infrastructure, development works,
excavation works and works involve confined spaces. Routine gas monitoring
should be undertaken during groundwork construction and in all excavations.
A7. Summary of the environmental exceedances of the reporting period is tabulated in Table A4.
Table A4 Summary of Exceedances in the
Reporting Period
|
Environmental
Monitoring |
Parameter(s) |
No. of Exceedances |
Total No. of Exceedances |
No. of Non-project
Related Exceedances |
Total
No. of
Non-project Related Exceedances |
No.
of Exceedances Related
to the Project |
Total
No. of Exceedances Related
to the Project |
|||
|
AL |
LL |
AL |
LL |
AL |
LL |
|||||
|
Air Quality |
1-hour TSP |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
24-hourTSP |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
24-hour RSP (Ambient Arsenic) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
Noise |
Leq(30mins) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Ecological Monitoring |
Avifauna |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Non-aquatic fauna |
2 |
1 |
3 |
2 |
1 |
3 |
0 |
0 |
0 |
|
Air Quality
A8. No AL or LL exceedance was recorded for air quality monitoring in the reporting period.
Noise
A9. No AL or LL exceedance was recorded for construction noise monitoring in the reporting period.
Ambient Arsenic
A10. No AL or LL exceedance was recorded for ambient arsenic monitoring in the reporting period.
Ecological Monitoring
A11. 2 AL and 1 LL exceedances were recorded for the monitoring of measures to minimise impacts on ecological sensitive habitats from disturbance and pollution. All exceedances were deemed as non-project related with potential influences by abiotic factors.
Built Heritage Monitoring (Vibration Monitoring)
A12. No exceedance of limits was recorded for vibration monitoring in the reporting period.
A13. Total of 2 complaints were received during the reporting period.
A14. The first environmental complaint related to construction dust and wastewater generated from FLN NDA constructions sites, particularly at Ma Sik Road and Ma Tak Road on 16 March 2026 under works contract ND/2024/07. The complaint was received by EPD on 16 March 2026 and referred to CEDD, IEC and ET on 18 March 2026. The complaint case has been investigated by the Contractor and ET, investigation was closed out on 2 April 2026. The investigation findings indicate that the complaint was not project related.
A15. The second environmental complaint related to construction noise generated from FLN NDA constructions sites during restricted hours, particularly at Po Shek Wu Road near Tai Tau Leng Village Vehicular Access on 26 March 2026 under works contract ND/2024/04. The complaint was received via 1823 on 26 March 2026 and referred to CEDD. CEED referred the complaint to Engineers Representative (ER) on 27 March 2026. The Contractor, IEC and ET received the complaint from ER on 27 March 2026. The complaint case has been investigated by the Contractor and ET, investigation was closed out on 10 April 2026. The investigation findings indicate no non-compliance on conditions stipulated on the valid Construction Noise Permit (CNP).
A16. The details of the complaint and investigation result are shown in Appendix 12.1.
A17. No notification of summons or successful prosecutions was received
in the reporting period.
A18. There was no change to be reported that may affect the on-going EM&A programme.
A19. The major site activities for the next reporting period are summarized below and shown in Appendix 1.1:
Works Contract No.
ND/2024/01:
· All Site Resumption Area(s)
1.
Tree survey
2.
Site Clearance
· Portion III (3), IV (4), V (5),
VII (7) and XXXV (35)
1.
Site Formation
· Portion VIII (8)
1.
Site Clearance & Demolition
· Portion XVIII (18), XXXVIII (38)
1.
Excavation works
2.
Construction of CHC Box Culvert
· Portion XI (11), XXIII (23)
1.
Erection of Substructure of Metropolis Community Liaison and Visitor
Centre
· Portion XL (40)
1.
Retaining
Wall Construction
2.
Drainages
System Construction
3.
ELS
work
· Portion LIX (59)
1.
Treatment of
High Arsenic-Containing Soil (HAS)
2.
Erection of
Shredding Facility
· Portion XVII (17), XVII (18), XXI (21), XXXIV (34),
XXXV (35), XLI (41), XLII (42)
1.
Excavation
Works
2.
Drainage Pipe
Installation
3.
ELS Works
· Portion XXV (25), XXVII (27), XXXIII (33), XLII
(42) and XLIV (44)
1. Site Clearance
2. Site Formation
3. Construction of Box Culvert
n
Works Contract No.
ND/2024/02:
1.
Site clearance in Area A, B, C, D, T, L
2.
Site formation works in Area D
3.
Temporary storage fill bank
in Kwu Tung Grass Soccer Pitch
4.
Demolition works for Community Sports in Area
J
5.
Asbestos Survey
6.
Ground Investigation Works
n
Works Contract No.
ND/2024/03:
Fanling Highway & Castle Peak Road area
· Pak Sau Road Po Lau Road
1.
Relocation/Reprovision/Removal
of Existing TCSS, Fire Hydrant, Signage & Streetlighting
2.
Tree Works
· Po Lau Road Sheung Yue River
1.
Asbestos
Removal Works at Portion IX
2.
Box Culvert
Bay 37 Bay 42 ELS
· TTA Stage 1 Works
1. Tree Works
2. Removal or relocation of
directly impacted Shrine/historical building at HKT08 & KT72
3. Demolish of Central Divider
& Barrier along FL Highway E/B
New Tsung Pak Long Road
· Box culvert Bay 10 to 12, 14 to 16 Drainage/Watermains
1. Drainage, Sewerage &
Watermain with Backfilling at Box Culvert Bay 15 & 16
2. Box Culvert Bay 10-13
& 14 ELS
3. Removal of ELS and Temp
Road Diversion
· Box culvert Bay 17 to 19 & Drainage/Watermains
1.
Box Culvert
Bay 17 to 19 ELS, Base Slab, Wall and Top Slab
· TTA Stage 1B
1.
Box Culvert
Bay 3, 5 to 7, 7A ELS
2.
Box Culvert
Base Slab
· Retaining Wall RW05A
1.
RW05A ELS
2.
Base Slab and
Wall
· Kwu Tung Road Bridge
1.
Site
Clearance and Tree Works
2.
Site
formation and cutback the existing slope
3.
Foundation
& Piling
· Works Areas WA1, WA2, WA3, WA4 & WA5
1.
Site
Clearance and Site Formation at PMs Site Office
2.
Temporary
Drainage
3.
Asbestos
removal
Fanling Highway Cross River Bridge (along Sheung Yue River)
· Portion XI East Abutment & pier foundation (No works at wet season between
1 Apr 2026 and 31 Oct 2026)
1.
Trial Pits
for UUs
2.
Piling Works
· Road L3 Viaduct
1.
Piling Works
2.
Pile Cap
L3A-02
Kwu Tung Interchange Foundation & Substructure
· Bridge B1 & C1
1.
Piling Works
2.
ELS
· Bridge B2 & C2
1.
Piling Work
· Footbridges No. 4 at TTA Stage 1
1.
Ground Investigation
2.
Underground Utilities Works
· Footbridges No. 5 at TTA Stage 2
1. Predrilling
· Widening of Existing Bridge No.N526
1.
Tree Works
2.
ELS
3.
Pilling
n
Works Contract No.
ND/2024/04:
1.
Site Clearance
2.
Site Establishment
3.
Tree Felling
4.
Trial Pit
5.
Predrilling
6.
Ground Investigation
7.
Existing Sewage Diversion
8.
Demolition of Existing Structures
9.
Haul Road Construction
10.Bored Piling
11.ELS Construction
12.Slope Works
13.Pier Cap Construction
14.Sheet Pilling
n
n Works Contract No. ND/2024/06:
· Portion A
1.
Excavation to +90 mPD of
Portion A
2. Forming Haul Road form Area C to Portion A
· Portion C, D, E
& F
1.
Trench
and Watermans Laying Works
· Area N
1.
Jacking Pit
Excavation
· Pre-boring of Pit B & C
n
Works Contract No. ND/2024/07:
1. Site Clearance
2. Site Formation
3. Ground Investigation
4. Pre-bored Socketed H Pile Construction
5. Bridge Construction
6. Bridge Deck Connection (Footbridge FB5)
7. Lift Tower Construction
8. Sump Pit Construction
9. ABWF Works
10.Drainage Construction
11.Improvement of Junction
12.Road Construction
13.Temporary Road Construction
14.Open Landscaping Works
15.Tree Felling & Transplantation
16.Asbestos Containing Materials Survey & Removal
17.Land Contamination (Environmental Ground Investigation)
18.Internal Movement, Importation & Exportation of C&D materials
19.Sewage Construction
20. Old Shrine Removal and New Shrine Construction
21. Storm pipe Construction
22. Box Culvert Construction
23.Temporary Drainage Diversion
24. Rebar Yard
25.Storage Yard for Concrete Pipe
n
Works Contract No. ND/2024/05 and ND/2024/08:
1. The construction work has not commenced in the
reporting month.
1.1.1 The
Kwu Tung North and Fanling North New Development Areas
(KTN and FLN NDAs) development are implemented in two phases, comprising First
Phase and Remaining Phase developments. The construction works for the
First Phase development commenced in December 2019. The construction works for
the Remaining Phase development (the Project), including
site clearance and formation, roads, drainage, sewerage and water supply
systems, commenced progressively from the January 2025.
1.1.2 The
Project is delivered under eight (8) Works Contracts as below.
·
Contract No. ND/2024/01: Site Formation and
Infrastructure Works (South);
· Contract
No. ND/2024/02: Site Formation and Infrastructure Works (North);
· Contract
No. ND/2024/03: Improvement Works of Fanling Highway (Kwu Tung Portion) and
Associated Works;
· Contract
No. ND/2024/04: Improvement Works of Tai Tau Leng Roundabout and Po Shek Wu
Road and Associated Works;
· Contract
No. ND/2024/05: Improvement Works of Fanling Highway (Pak Shek Au Portion) and
Associated Works;
· Contract
No. ND/2024/06: Fresh Water and Flushing Water Service Reservoirs and
Associated Works;
· Contract
No. ND/2024/07: Site Formation and Infrastructure Works (East); and
· Contract
No. ND/2024/08: Site Formation and Infrastructure Works (West).
1.1.3
The EIA Report (AEIAR-175/2013) for NENT NDA was
approved with conditions under EIAO in 2013. The Environmental Permits for
corresponding Designated Projects were also issued by DEP in November 2013.
Subsequent to the findings of preliminary design and P&E Review for
accommodating additional population in KTN and FLN NDAs, VEP were subsequently
applied for eight EPs under the Project (i.e. EP-465/2013/A, EP-466/2013/A,
EP-467/2013/A, EP-468/2013/A, EP-470/2013/A, EP-471/2013/A, EP-472/2013/A and
EP-476/2013).
1.1.4
Aurecon was commissioned by Civil
Engineering and Development Department (CEDD) to provide
EM&A services for the works contracts in relation to the Project pursuant
to the requirements as specified in relevant EPs, the EM&A Manual issued in
the EIA stage, the Updated EM&A Manual prepared for Contract No. NDO
14/2018 and the approved EIA Report for the Project to discharge the duties of
the ET for the Project.
1.1.5 This is the 15th Monthly EM&A Report summarizing the findings of EM&A works at Works Contract No. ND/2024/01 under the Project with EP-467/2013/A and EP-468/2013/A, Works Contract No. ND/2024/02 under the Project with EP-467/2013/A and EP-468/2013/A, Works Contract No. ND/2024/03 under the Project with EP-465/2013/A, EP-466/2013/A and EP-467/2023/A, Works Contract No. ND/2024/04 under the Project with EP-465/2013/A and EP-471/2013/A, Works Contract No. ND/2024/06 under Environmental Permit No. EP-470/2013/A and for Contract No. ND/2024/07 under Environmental Permit No. EP-476/2013 during the reporting period from 1 to 31 March 2026. No construction works occur in the remaining contracts during the reporting period for Contract No. ND/2024/05 and ND/2024/08.
Table
1.1 Parties Involved in Project Organization for all Works Contracts
|
|
Works Contract(s) |
||||||||
|
Parties |
ND/2024/01 |
ND/2024/02 |
ND/2024/03 |
ND/2024/04 |
ND/2024/05 |
ND/2024/06 |
ND/2024/07 |
ND/2024/08 |
|
|
Project Proponent |
CEDD |
||||||||
|
Supervisor / Engineers Representative (ER) |
AECOM Asia Co. Ltd. |
AECOM Asia Co.
Ltd. |
AECOM Asia Co. Ltd |
AECOM Asia Co. Ltd |
AECOM Asia Co. Ltd |
Binnies Hong Kong Limited |
AtkinsRιalis |
AtkinsRιalis |
|
|
Contractor |
Build King - Richwell Engineering Joint
Venture |
Build King Richwell Civil Joint Venture |
China State -
STEC Joint Venture |
CW CRCC (ND202404) Joint Venture |
Lanon Sinohydro Excel JV |
Wo Hing-Tsun Yip Joint Venture |
Build King Richwell Civil Joint Venture |
Gammon - STEC Joint Venture |
|
|
ET |
Aurecon Hong Kong Limited |
||||||||
|
Independent Environmental Checker (IEC) |
Mott MacDonald Hong Kong Limited |
||||||||
Works Contract No. ND/2024/01:
· All Site Resumption Area(s)
3.
Tree survey
4.
Site
Clearance
· Portion III (3), IV (4), V (5), VII (7) and XXXV
(35)
2.
Site
Formation
· Portion VI (6), XVIII (18), XXXVIII (38)
3.
Site
Clearance
4.
Excavation
· Portion VIII (8)
3.
Site
Clearance & Demolition
4.
Asbestos
Abatement Works
· Portion XI (11), XXIII (23)
2.
Formwork
Erection, Rebar Fixing, Concreting Works
· Portion XL (40)
4.
Retaining
Wall Construction
5.
Drainages
System Construction
6.
ELS
work
· Portion LIX (59)
2.
Treatment of
High Arsenic-Containing Soil (HAS)
· Portion XVII (17), XVII (18), XXI (21), XXXIV (34),
XXXV (35), XLI (41), XLII (42)
3.
Excavation
works
4.
Drainage Pipe Installation
· Portion XII (12), XV (15), XXV (25), XXVII (27), XXX (30), XXXI (31), XXXII (33), XLII (42) and XLIV (44), Portion LI
(51)
2.
Site
Clearance
· Portion XVI (16), XLII (42) and LIII (53)
2.
Site
Clearance & Demolition
n
n Works Contract No. ND/2024/02:
· Site clearance in Area B, D, L
· Site formation works in Area D
· Temporary storage fill bank in Kwu Tung Grass
Soccer Pitch
· Demolition works for Community Sports in Area J
· Asbestos survey in the resumed areas
Works Contract No.
ND/2024/03:
Fanling Highway & Castle Peak Road area
· Pak Sau Road Po Lau Road
1.
Tree Works
· Po Lau Road Sheung Yue River
1.
Asbestos
Removal Works at Portion IX
2.
Box Culvert
Bay 37 Bay 42 ELS
3.
Tree Works
· TTA Stage 1 Works
1.
Tree Works
New Tsung Pak Long Road
· Box culvert Bay 10 to 12, 14 to 16 Drainage/Watermains
1.
Drainage,
Sewerage & Watermain with Backfilling at Box Culvert Bay 15 & 16
2.
Box Culvert
Bay 14 ELS
· Box culvert Bay 17 to 19 & Drainage/Watermains
1.
Box Culvert
Bay 17 to 19 ELS, Base Slab, Wall and Top Slab
2.
Box culvert
Bay 17 & 19 Base Slab
· Retaining Wall RW01
1.
Pre-drilling
· Retaining Wall RW05A
1.
RW05A ELS
· Kwu Tung Road Bridge
1.
Site
Clearance and Tree Works
2.
Site
formation and cutback the existing slope
3.
Predrilling
4.
Foundation
& Piling
· Works Areas WA1, WA2, WA3, WA4 & WA5
1.
Site
Formation at PMs Site Office
2.
Site
Clearance, haul road and Temporary Drainage
3.
Asbestos
removal
Fanling Highway Cross River Bridge (along Sheung Yue River)
· Portion XI East Abutment & pier foundation
1.
Trial Pits
for UUs
2.
Piling Works
· Road L3 Viaduct
1.
Piling Works
2.
Pile Cap
L3A-02
· Kwu Tung Interchange Foundation & Substructure
- Bridge B1 & C1
1.
Piling Works
· Widening of Existing Bridge No.N526
1.
Tree Works
2.
ELS
3.
Pre-drilling
n
n Works Contract No. ND/2024/04:
· Site Clearance
· Site Establishment
· Tree Felling
· Trial Pit
· Pre-drilling
· Ground Investigation
· Existing Sewage Diversion
· Demolition of Existing Structures
· Haul Road Construction
· Bored Piling
· ELS Construction
· Slope Works
· Sheet Piling
n
n Works Contract No. ND/2024/06:
· Portion A
1.
Excavation to +90 mPD of Portion A
2.
Forming Haul Road from Area C to Portion A
· Portion C, Portion D, Portion E and Portion F
1.
Trench and Watermains Laying Works
· Pit B and Pit C
1.
Excavation
n
Works Contract No.
ND/2024/07:
· Area C
1.
Tree Felling
2.
Site Formation
· Area D and Area E
1.
Site Formation
2.
Asbestos Removal
· Area G
1.
Site Clearance
2.
Site Formation
3.
Asbestos Removal
· Area H, Area I and Area R
1.
Asbestos Removal
· Area J
1.
Road Construction
· Area K
1.
Sewerage (DN1350) Construction Road Construction, Site Clearance
· Area O
1.
New Shrine Construction
· Area P
1.
Site Formation
2.
Drainage Construction
· Area Q
1.
Temporary Road Construction
2.
Drainage Construction
3.
Tree Transplant (1st Pruning)
4.
Storm Pipe (DN1650) Construction
5.
Tree Felling
· Portion 1b
1.
Assembly Yard for Bridge Construction
2.
Storage Yard for Concrete Pipe
· Portion 3b
1.
Sewerage Construction
· Portion 6c
1.
Improvement of Junction
· Portion 9b
1.
Rebar Yard
· Footbridge FB-4 (North)
1.
Lift Tower Construction
2.
ABWF Works
· Footbridge FB-4 (South)
1.
Piling Works
2.
ABWF Works
· Footbridge FB-5
1.
Pier Head Construction
2.
Lift Tower Construction
3.
Sump Pit Construction
n
Works Contract No. ND/2024/05 and ND/2024/08:
· No construction work during the reporting period.
Table 1.2 Status of Environmental License,
Notifications and Permits for Works Contract No. ND/2024/01
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction
Dust) Regulation |
|||
|
10008709 |
02/09/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7052236 |
20/09/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN: 5213-548-B2781-01 |
06/12/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control
Ordinance |
|||
|
WT00045924-2024 |
15/01/2025 |
31/01/2030 |
Valid |
|
WT00046627-2025 |
03/06/2025 |
30/06/2030 |
Valid |
|
WT00046736-2025 |
10/06/2025 |
30/06/2030 |
Valid |
|
WT00046982-2025 |
03/10/2025 |
31/10/2030 |
Valid |
|
WT00047583-2025 |
19/01/2026 |
31/01/2031 |
Valid |
|
WT00048070-2025 |
28/01/2026 |
31/01/2031 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN1540-25 |
26/12/2025 |
25/03/2026 |
Valid until 25/03/2026 |
|
GW-RN0390-26 |
26/03/2026 |
25/07/2026 |
Valid |
|
GW-RN1593-25 |
04/01/2026 |
30/06/2026 |
Valid |
|
GW-RN0041-26 |
16/01/2026 |
15/04/2026 |
Valid |
|
GW-RN0254-26 |
27/02/2026 |
26/05/2026 |
Valid |
|
GW-RN0166-26 |
08/02/2026 |
07/05/2026 |
Valid |
Table
1.3 Status of Environmental License,
Notifications and Permits for Works Contract
No. ND/2024/02
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction
Dust) Regulation |
|||
|
10024940 |
23/12/2025 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7057203 |
05/01/2026 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-545-B2803-01 |
11/02/2026 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control
Ordinance |
|||
|
WT00048304-2026 |
18/03/2026 |
31/03/2031 |
Valid |
|
Application
Ref. No.10027555 |
Applied on 11/03/2026 |
TBC |
Under application |
|
Construction Noise Permit (CNP) |
|
|
|
|
NIL |
NIL |
NIL |
NIL |
Table
1.4 Status of Environmental License,
Notifications and Permits for Works Contract
No. ND/2024/03
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-465/2013/A |
20/01/2017 |
N/A |
Valid |
|
EP-466/2013/A |
18/08/2022 |
N/A |
Valid |
|
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction
Dust) Regulation |
|||
|
10008101 |
15/08/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7052008 |
21/08/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-548-C5047-01 |
22/01/2025 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control
Ordinance |
|||
|
WT00046044-2025 |
07/11/2025 |
28/02/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN1496-25 |
19/12/2025 |
18/03/2026 |
Valid until 18/03/2026 |
|
GW-RN0243-26 |
19/03/2026 |
18/06/2026 |
Valid |
Table
1.5 Status of Environmental License,
Notifications and Permits for Works Contract
No. ND/2024/04
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-465/2013/A |
20/01/2017 |
N/A |
Valid |
|
EP-471/2013/A |
10/10/2022 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction
Dust) Regulation |
|||
|
10012919 |
06/01/2025 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7053746 |
13/02/2025 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-626-C5043-01 |
28/01/2025 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control
Ordinance |
|||
|
WT00047165-2025 |
15/12/2025 |
31/08/2030 |
Valid |
|
WT00048247-2026 |
18/03/2026 |
31/03/2031 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN1044-25 |
17/09/2025 |
16/03/2026 |
Valid until 16/03/2026 |
|
GW-RN1377-25 |
24/11/2025 |
23/03/2026 |
Valid until 23/03/2026 |
|
GW-RN1457-25 |
10/12/2025 |
09/03/2026 |
Valid |
|
GW-RN0021-26 |
11/01/2026 |
31/03/2026 |
Valid until 31/03/2026 |
|
GW-RN1510-25 |
01/01/2026 |
30/04/2026 |
Valid |
|
GW-RN0230-26 |
24/02/2026 |
31/05/2026 |
Valid |
|
GW-RN0251-26 |
28/02/2026 |
27/05/2026 |
Valid |
|
GW-RN0201-26 |
01/03/2026 |
31/05/2026 |
Valid |
|
GW-RN0205-26 |
01/03/2026 |
31/05/2026 |
Valid |
|
GW-RN0381-26 |
24/03/2026 |
23/07/2026 |
Valid |
Table
1.6 Status of Environmental License,
Notifications and Permits for Works Contract
No. ND/2024/06
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-470/2013/A |
13/05/2022 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction
Dust) Regulation |
|||
|
10007695 |
06/08/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7051899 |
28/08/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-624-W3824-01 |
04/09/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control
Ordinance |
|||
|
WT00046560-2025 |
15/05/2025 |
31/05/2030 |
Valid |
|
WT00046847-2025 |
11/07/2025 |
31/07/2030 |
Valid |
|
WT00046588-2025 |
29/05/2025 |
31/05/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN1439-25 |
29/12/2025 |
28/04/2026 |
Valid |
Table
1.7 Status of Environmental License,
Notifications and Permits for Works Contract
No. ND/2024/07
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-476/2013 |
21/11/2013 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction
Dust) Regulation |
|||
|
10007874 |
09/08/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7051974 |
20/08/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-625-B2775-01 |
19/08/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control
Ordinance |
|||
|
WT00045532-2024 |
10/12/2024 |
31/12/2029 |
Valid |
|
WT00046059-2025 |
14/02/2025 |
28/02/2030 |
Valid |
|
WT00046059-2025 |
17/06/2025 |
28/02/2030 |
Valid |
|
WT00046342-2025 |
15/05/2025 |
31/05/2030 |
Valid |
|
WT00046692-2025 |
29/05/2025 |
31/05/2030 |
Valid |
|
WT00046655-2025 |
03/06/2025 |
30/06/2030 |
Valid |
|
WT00046819-2025 |
31/07/2025 |
31/07/2030 |
Valid |
|
WT00047343-2025 |
29/09/2025 |
30/09/2030 |
Valid |
|
WT00047250-2025 |
12/11/2025 |
30/11/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN1224-25 |
01/11/2025 |
30/04/2026 |
Valid |
|
GW-RN1473-25 |
12/12/2025 |
31/05/2026 |
Valid |
|
GW-RN1480-25 |
19/12/2025 |
18/03/2026 |
Valid |
|
GW-RN0069-26 |
19/01/2026 |
18/06/2026 |
Valid |
|
GW-RN0168-26 |
18/02/2026 |
17/06/2026 |
Valid |
|
GW-RN0179-26 |
23/02/2026 |
22/08/2026 |
Valid |
2.2.1
According to the EM&A Manual,
the approved updated EM&A Manual for the First Phase, the designated
locations for impact air quality monitoring in related to the work contracts in
the reporting period are listed in Table
2.1 and their locations are shown in Figure
2.1 and Figure 2.2.
Table
2.1 Summary of Impact Air Quality Monitoring Stations in related to the Works Contracts
in the Reporting Period
|
Monitoring
Station(s) |
Works
Contract(s) |
ASR
ID in EIA |
Planned(3) or Existing |
Monitoring
Location(s) |
|
KTN-DMS1 |
ND/2024/01, ND/2024/02, ND/2024/03 |
KTN-19 |
Planned |
Nursery Classes and Kindergarten; Post
Offices |
|
KTN-DMS2 |
ND/2024/01, ND/2024/02 |
KTN-90 |
Planned |
Nursery Classes and Kindergarten (2 nos);
District Elderly Community Centre |
|
KTN-DMS3 |
ND/2024/01, ND/2024/02, ND/2024/03 |
KTN-326 |
Planned |
Village Resite |
|
KTN-DMS4(B)(1)(2) |
ND/2024/01, ND/2024/03 |
KTN-E70 |
Existing |
Temporary Structure at Pak Shek Au |
|
FLN-DMS1 |
ND/2024/07 |
FLN-E62 |
Existing |
Scattered Village Houses North of Proposed
Potential Ecopark |
|
FLN-DMS2 |
ND/2024/06, ND/2024/07 |
FLN-E243 |
Planned |
Residential Building, Nursery Classes and
Kindergartens, Neighbourhood Elderly Community Centre, Residential Home for
the Elderly, Post Office |
|
FLN-DMS5, FLN-DMS5(A) |
ND/2024/07 |
FLN-E124 |
Existing |
Noble Hill / Good View New Village |
|
FLN-DMS6(A) |
ND/2024/03, ND/2024/04 |
DMS-10 |
Existing |
Choi Ngan House, Choi Po Court |
|
FLN-DMS7 |
ND/2024/06, ND/2024/07 |
FLN-20 |
Planned |
Planned premise for Weapon Training
Division |
Remarks:
(1) KTN-DMS4(B) is the
alternative air monitoring stations proposed to replace KTN-DMS4.
(2) As KTN-DMS4 - Temporary structure near Fanling
Highway (near Pak Shek Au) is no longer as existing ASR, air quality monitoring
station should be relocated to the alternative dust monitoring location
according to the updated EM&A Manual, Section 2.6.2. According to Figure
3.1 of Approved EIA report and site visits conducted in June 2022, ASR at near
KTN-E70 Temporary Structure near Fanling Highway near Pak Shek Au is
considered as the most representative alternative station KTN-DMS4(B) for air
quality monitoring for KTN-DMS4 (i.e. KTN-E162).
(3) Impact monitoring will be
carried out when the planned sensitive receivers are commissioned.
Table
2.2 Parameters Measured in the Impact Air Quality Monitoring
|
Parameter(s) |
Frequency(1)(2) |
|
1-hour TSP |
Three times / 6 days |
|
24-hour TSP |
Once / 6 days |
Remarks:
(1) The air
quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET
during the reporting period.
(2) The air
quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET
during the reporting period.
Table 2.3 Air Quality Monitoring Equipment
|
Monitoring Station(s) |
Equipment |
Model |
Manufacturer |
Quantity |
|
KTN-DMS4(B)(1), FLN-DMS5(1),
FLN-DMS5(A)(1) |
Dust Monitor (1-hour and 24-hour TSP) |
AEROCET-831 |
Met One
Instruments |
9 |
|
FLN-DMS1(1) |
Dust Monitor (1-hour TSP) |
|||
|
HVS Sampler (24-hour TSP) |
TE-5170 |
Tisch |
1 |
|
|
FLN-DMS6(A)(2) |
Dust Monitor (1-hour and 24-hour TSP) |
LD-5R |
Sibata |
1 |
Remarks:
(1) The air
quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET
during the reporting period.
(2) The air
quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET
during the reporting period.
Instrumentation
(AEROCET-831)
· Place the dust meter at least 1.3 meters above
ground;
· Press and hold the Power key momentarily to power
on the unit and make sure that the battery level was not flash or in low level;
· Allow the instrument to stand for about 3 second to
display the Sample Screen minutes;
· Press the START / STOP key to run the internal
vacuum pump for 1 minute and be ready to use;
· Use the select dial to select the PM range and
press the START / STOP key to start a measurement;
· Finally, push the START/STOP key to stop the
measurement after 24-hour sampling;
· Information such as sampling date, time, value and
site condition were recorded during the monitoring period; and
· All data
were recorded in the data logger for further data processing.
Maintenance/Calibration
· Check and calibrate the
meters by High Volume Sampler (HVS) to check the validity
and accuracy of the results measured by direct reading method at 2-month
intervals throughout all stages of the air quality monitoring.
Instrumentation
(TISCH Model: TE-5170 / TE-5170X)
·
A horizontal
platform with appropriate support was provided to secure the samplers against
gusty wind. the dust meter at least 1.3 meters above ground;
·
No two samplers
were placed less than 2 metres apart.
·
The distance
between the sampler and an obstacle, such as buildings, was at least twice the
height that the obstacle protrudes above the sampler.
·
A minimum of 2
metres of separation from walls, parapets and penthouses was required for
rooftop samples.
·
A minimum of 2
metres separation from any supporting structure, measured horizontally was
required.
·
No furnaces or
incineration flues were nearby.
·
Airflow around
the sampler was unrestricted.
·
The sampler were
more than 20 metres from the drip line.
·
Any wire fence
and gate, to protect the sampler, should not cause any obstruction during
monitoring.
·
Permission and
access to monitoring stations have been obtained to set up the samplers.
·
A secured supply
of electricity was provided to operate the samplers.
Filters
Preparation
Operating/Analytical Procedures
·
Prior to the
commencement of dust sampling, the flow rate of the HVS was properly set
(between 1.1 m3 /min. and 1.4 m3 /min.) in accordance
with the manufacturer's instruction to within the range recommended in USEPA
Standard Title 40, CFR Part 50;
·
The power supply
was checked to ensure the sampler worked properly;
·
On sampling, the
sampler was operated for 5 minutes to establish thermal equilibrium before
placing any filter media at the designated air quality monitoring station;
·
The filter
holding frame was then removed by loosening the four nuts and carefully a
weighted and conditioned filter was centered with the stamped number upwards,
on a supporting screen;
·
The filter was
aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter. The filter holding frame was then tightened to the filter
holder with swing bolts. The applied pressure should be sufficient to avoid air
leakage at the edges;
·
The shelter lid
was closed and secured with the aluminium strip;
·
The timer was
then programmed. Information was recorded on the record sheet, which included
the starting time, the weather condition and the filter number (the initial
weight of the filter paper can be found out by using the filter number);
·
After sampling,
the filter was removed and kept in a clean and tightly sealed plastic bag. The
filter paper was then returned to the HOKLAS accredited laboratory (Wellab
Ltd.) for reconditioning in the humidity-controlled chamber followed by
accurate weighting by an electronic balance with a readout down to 0.1mg. The
elapsed time was also recorded; and
·
Before weighing,
all filters were equilibrated in a conditioning environment for 24 hours. The
conditioning environment temperature should be between 25°C and 30°C and did
not vary by more than ±3°C; the RH should be < 50% and did not vary by more
than ±5%. A convenient working RH is 40%. Weighing results were returned for
further analysis of TSP concentrations collected by each filter
Maintenance/Calibration
· The high-volume motors
and their accessories were properly maintained. Appropriate maintenance such as
routine motor brushes replacement and electrical wiring checking were made to
ensure that the equipment and necessary power supply are in good working
conditions; and
· All HVS were calibrated
(five point calibration) using Calibration Kit prior to the commencement of
baseline monitoring and thereafter at bi-monthly intervals.
Instrumentation
(Sibata Model: LD-5R)
· Placed the dust meters at
least 1.3m above ground
· Set POWER to ON and
make sure that the battery level not flashed or in low level;
· Pulled the air sampling
inlet cover up;
· Pushed the knob at
MEASURE position;
· Set time/mode setting to
[BG] by pushing the time setting switch. Then, started the background
measurement by pushing the start/stop switch once. It took 6 sec. to complete
the background measurement;
· Turned knob to SENSI. ADJ
position and pressed in;
· Pushed Start/Stop switch
once;
· Gently returned knob to
the MEASURE position;
· Pushed the time setting
switch to change the time setting display to [LOG] at the bottom left of the
liquid crystal display;
· Removed the cap and
started measurement; and
· Information such as
sampling date, time, count value and site condition were recorded during the
monitoring period.
Maintenance/Calibration
· Direct reading dust meter
shall be used in determining 1-hour TSP and 24-hour TSP at air quality
monitoring points. The direct reading dust meters have been calibrated against
high volume samplers (HVSs) bi-monthly. A 2-day, three 3-hour measurement
results per day from direct reading dust meters were taken to compare with the
sampling results from the HVSs. The correlation between the direct reading dust
meters and the HVSs were then concluded. By accounting for the correlation
factor, the direct reading dust meters are considered to achieve comparable
results as that of the HVSs.
· The HVS used to calibrate
the direct dust monitor will need to be calibrated bi-monthly. Details of
maintenance and calibration for the HVS refers to Section 2.5.8.
Calibration for the air quality monitoring equipment is attached to the Appendix
2.2.
Table
2.4 Action and Limit Levels for 1-hour TSP Air
Quality Monitoring
|
Monitoring
Station |
AL
(μg/m3) |
LL
(μg/m3) |
|
KTN-DMS4(B) |
297 |
500 |
|
FLN-DMS1 |
303 |
500 |
|
FLN-DMS5 |
279 |
500 |
|
FLN-DMS6(A) |
286 |
500 |
Table
2.5 Action and Limit Levels for 24-hour of TSP
Air Quality Monitoring
|
Monitoring
Station |
AL
(μg/m3) |
LL
(μg/m3) |
|
KTN-DMS4(B) |
192 |
260 |
|
FLN-DMS1 |
150 |
260 |
|
FLN-DMS5(A) |
153 |
260 |
|
FLN-DMS6(A) |
157 |
260 |
Table
2.6 Summary Table of 1-hour TSP Monitoring Result during the Reporting Month
|
Monitoring Station |
Averaged
Measured Value (μg/m3) |
Maximum
Measured Value
(μg/m3) |
Minimum
Measured Value (μg/m3) |
Action
Level (μg/m3) |
Limit
Level, (μg/m3) |
|
KTN-DMS4(B)(1) |
44 |
57 |
27 |
297 |
500 |
|
FLN-DMS1(1) |
55 |
73 |
34 |
303 |
500 |
|
FLN-DMS5(1) |
44 |
61 |
35 |
279 |
500 |
|
FLN-DMS6(A)(2) |
66 |
78 |
51 |
286 |
500 |
(1) The air
quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET
during the reporting period.
(2) The air
quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET
during the reporting period.
Table
2.7 Summary Table of 24-hour TSP Monitoring Result during the Reporting Month
|
Monitoring Station |
Averaged
Measured Value (μg/m3) |
Maximum
Measured Value
(μg/m3) |
Minimum
Measured Value (μg/m3) |
Action
Level (μg/m3) |
Limit
Level, (μg/m3) |
|
KTN-DMS4(B)(1) |
47 |
58 |
32 |
192 |
260 |
|
FLN-DMS1(1) |
34 |
47 |
19 |
150 |
260 |
|
FLN-DMS5(A) (1) |
58 |
72 |
35 |
153 |
260 |
|
FLN-DMS6(A)(2) |
71 |
78 |
56 |
157 |
260 |
Remarks:
(1) The air
quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET
during the reporting period.
(2) The air
quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET
during the reporting period.
Table
3.1 Construction Noise Monitoring Stations near in related to the Works Contracts
in the Reporting period
|
Monitoring
Station(s) |
Works Contract(s) |
NSR EIA ID(s) |
Location(s) |
Planned(2) Or Existing |
Type
of Measurement |
|
CP-KTN-NMS1 |
ND/2024/01, ND/2024/02 |
CP-NMS1 |
Residential Building at Ma Tso Lung |
Existing |
Free-Field(1) |
|
CP-KTN-NMS2 |
ND/2024/01, ND/2024/02 |
CP-NMS2 |
Residential Building at Ma Tso Lung |
Existing |
Free-Field(1) |
|
CP-KTN-NMS3 |
ND/2024/01, |
CP-NMS3 |
Fung Kong Garden |
Existing |
|
|
CP-KTN-NMS4(3) |
ND/2024/01, ND/2024/02, ND/2024/03 |
CP-NMS5 |
Primary School |
Planned |
|
|
CP-KTN-NMS5 |
ND/2024/06 |
CP-NMS7 |
N/A |
Existing |
Free-Field(1) |
|
CP-KTN-NMS6 |
ND/2024/01, ND/2024/02 |
N/A |
Ho Sheung Heung, Hau Ku ShekAncestral Hall, Hung Shing Temple & Pai Fung Temple and Sin
Wai Nunnery |
Existing |
Faηade |
|
CP-KTN-NMS7 |
ND/2024/01, ND/2024/02 |
CP-NMS4 |
Oi Lok Home |
Existing |
Free-Field(1) |
|
CP-FLN-NMS4(A)(4) |
ND/2024/04 |
CP-NMS6 |
Choi Ying House, Choi Po Court (Choi Yuen Estate) |
Existing |
Free-Field(1) |
|
CP-FLN-NMS1 |
ND/2024/06, ND/2024/07 |
CP-NMS10 |
Belair Monte |
Existing |
Facade |
|
CP-FLN-NMS3(3) |
ND/2024/06, ND/2024/07 |
CP-NMS12 |
Secondary School |
Planned |
Free-Field(1) |
|
CP-FLN-NMS5 |
ND/2024/07 |
CP-NMS8 |
Man Kok Village |
Existing |
Free-Field(1) |
|
CP-FLN-NMS6 |
ND/2024/07 |
CP-NMS9 |
Woodland Crest |
Existing |
Faηade |
Remarks:
(1)
For Free
Field measurement, +3 dB(A) should be added to the measured results.
(2) Impact monitoring will be carried out when the
planned sensitive receivers are commissioned.
(3) As confirmed with Engineer Representative, the
planned school at CP-KTN-NMS4 and CP-FLN-NMS3 are not constructed yet. Thus, the impact noise monitoring will be
carried out at monitoring station CP-KTN-NMS4 and CP-FLN-NMS3 after the
construction and occupation of the planned school. No noise monitoring of the mentioned station
was carried out in this reporting period.
(4) Alternative
monitoring stations to the corresponding original monitoring stations.
Table
3.2 Construction Noise Monitoring Parameter, Frequency and Duration
|
Monitoring Station |
Parameter |
Frequency and Duration |
|
CP-KTN-NMS1(2), CP-KTN-NMS2(1), CP-KTN-NMS3(1), CP-KTN-NMS5(1), CP-KTN-NMS6(1),CP-KTN-NMS7(2),CP-FLN-NMS1(1), CP-FLN-NMS4(A)(2), CP-FLN-NMS5(2), CP-FLN-NMS6(2) |
Leq(30mins), L10 and L90 (as six
consecutive Leq,5min readings) |
Once every week throughout the construction phase |
Remark:
(1) The noise
monitoring was conducted by First Phase ET during the reporting period.
(2) The noise
monitoring was conducted by Remaining Phase Environmental Team during the
reporting period.
·
For faηade
measurement, the monitoring station was set at a point 1 m from the exterior of
the sensitive receivers building faηade and set at a position 1.2 m above the
ground. For free-field measurement, the monitoring station was set at a
position 1.2 m above the ground.
·
The battery
condition was checked to ensure good functioning of the meter.
·
Parameters such
as frequency weighting, the time weighting and the interval were set as
follows:
-
Frequency weighting: A
-
Time weighting: Fast
-
Interval: 30 minutes (Leq(30mins))
·
Prior to and
after each noise measurement, the meter was calibrated using an acoustic
calibrator for 94.0 dB at 1000 Hz. If
the difference in the calibration level before and after measurement is more
than 1.0 dB, the measurement was considered invalid and repeat of noise
measurement will be required after re-calibration or repair the equipment.
·
At the end of
the monitoring period, the values of Leq, L10 and L90
were recorded. In addition, noise
sources were recorded on a standard record sheet.
Table
3.3 Construction Noise Monitoring Equipment
|
Equipment |
Manufacturer |
Model |
No. of Equipment |
Serial
No. |
|
Sound
Level Meter |
NTi Audio(2) |
XL2 |
1 |
A2A-17638-E0 |
|
XL3 |
2 |
A3A-01229-F0 A3A-01220-F0 |
||
|
BSWA(1) |
BSWA 308 |
3 |
580006 580011 580013 |
|
|
Acoustic
Calibrator |
RION(2) |
NC-75 |
3 |
34724244 35124527 35124529 |
|
SVANTEK(1) |
SV30A |
3 |
24803 24791 24780 |
Remark:
(1)
The noise monitoring
equipment was used by First Phase ET during the reporting period.
(2)
The noise monitoring
equipment was used by Remaining Phase Environmental Team during the reporting
period.
·
The microphone
head of the sound level meter and calibrator were regularly cleaned with a soft
cloth;
·
The sound level
meter and acoustic calibrator were calibrated annually; and
·
The accuracy of
the sound level meter was checked using an acoustic calibrator generating a
known sound pressure level at a known frequency immediately prior to and
following each noise measurement. Measurements were accepted as valid only if
the calibration level from before and after the noise measurement agree to
within 1.0 dB.
Table
3.4 Action and Limit Levels for Construction Noise Monitoring
|
Time Period |
Action |
Limit Level |
|
07:00 19:00 on normal weekdays |
When one or more documented complaints are received |
75
dB(A) |
Remark:
(1)
Time period for
construction noise monitoring during normal construction working hour
(0700-1900 Monday to Saturday).
(2)
If
works are to be carried out during restricted hours, the conditions stipulated
in the Construction Noise Permit (CNP) issued by the Noise Control Authority
have to be followed.
(3)
70 dB(A) and 65 dB(A) for
schools during normal teaching periods and school examination periods,
respectively.
Table
3.5 Summary of Construction Noise Monitoring Results during the Reporting Month
|
Works Contracts |
Monitoring Stations |
Noise Levels, Leq(30min), dB(A) |
Baseline Levels, dB(A) |
Limit Levels, dB(A) |
|
ND/2024/01, ND/2024/02 |
CP-KTN-NMS1(1)(3) |
48.6 52.9 |
65.7 |
75 |
|
CP-KTN-NMS2(1)(2) |
51.2 64.6 |
58.6 |
||
|
CP-KTN-NMS3(1)(2) |
52.0 54.6 |
51.6 |
||
|
CP-KTN-NMS6(2) |
55.6 63.9 |
55.1 |
||
|
CP-KTN-NMS7(1)(3) |
63.6 68.5 |
64.6 |
||
|
ND/2024/04 |
CP-FLN-NMS4(A)(1)(3)(4) |
69.7 72.1 |
72.4 |
|
|
ND/2024/06 |
CP-KTN-NMS5(1)(2) |
47.9 65.3 |
57.2 |
|
|
ND/2024/06, ND/2024/07 |
CP-FLN-NMS1(2) |
61.5 69.0 |
69.9 |
|
|
ND/2024/07 |
CP-FLN-NMS5(1)(3) |
63.6 67.4 |
69.5 |
|
|
CP-FLN-NMS6(3) |
53.0 58.8 |
55.0 |
Remarks:
(1) For Free
Field measurement, +3 dB(A) was added to the measured results.
(2) The noise
monitoring was conducted by First Phase ET during the reporting period.
(3) The noise
monitoring was conducted by Remaining Phase Environmental Team during the
reporting period.
(4) Alternative
monitoring stations to the corresponding original monitoring stations.
Table 3.6
Summary of Observations at Noise Monitoring Stations
|
Works Contracts |
Monitoring Stations |
Location |
Major Noise Sources |
|
ND/2024/01, ND/2024/02 |
CP-KTN-NMS1 |
Residential Building at Ma Tso Lung |
Household
noise (dog barking) from nearby village house |
|
CP-KTN-NMS2 |
Residential
Building at Ma Tso Lung |
Road
Traffic Noise |
|
|
CP-KTN-NMS3 |
Fung Kong Garden |
Road Traffic Noise |
|
|
CP-KTN-NMS4 |
Primary School |
N/A(1) |
|
|
CP-KTN-NMS6 |
Ho Sheung Heung, Hau Ku Shek Ancestral Hall, Hung Shing Temple & Pai Fung Temple and Sin
Wai Nunnery |
Road
Traffic Noise, Dump Truck, Excavator |
|
|
CP-KTN-NMS7 |
Oi
Lok Home |
Road
Traffic Noise |
|
|
ND/2024/04 |
CP-FLN-NMS4(A)(2) |
Choi Ying House, Choi Po Court (Choi Yuen Estate) |
Road
Traffic Noise |
|
ND/2024/06 |
CP-KTN-NMS5 |
N/A |
Road
Traffic Noise, Excavator, Roller |
|
ND/2024/06, ND/2024/07 |
CP-FLN-NMS1 |
Belair Monte |
Road
Traffic Noise, Excavator, Dump Truck |
|
CP-FLN-NMS3 |
Secondary School |
N/A(1) |
|
|
ND/2024/07 |
CP-FLN-NMS5 |
Man Kok Village |
Road
Traffic Noise |
|
CP-FLN-NMS6 |
Woodland Crest |
No
construction activity and other noise source was observed |
Remarks:
(1)
No
impact noise monitoring was carried out at the monitoring station. Thus, not
applicable (N/A).
(2) Alternative
monitoring stations to the corresponding original monitoring stations.
Table 4.1 Summary of Water Quality
Monitoring Locations
|
New
Monitoring Station(s) |
Original
Monitoring Station ID(s) |
Description |
Location(s) |
Measurement Period |
|
KTN NDA |
||||
|
KTN-CS1 |
CS1 |
Control Station for KTN NDA |
Centreline of river, upstream of the
channel |
During construction of channel |
|
KTN-IS1 |
IS1 |
Impact Station
for KTN NDA |
Centreline of river, downstream of
the channel |
During construction of channel |
|
FLN NDA |
||||
|
FLN-CS1 |
CS2 |
Control Station for FLN NDA |
Centreline of river, upstream of the
channel |
During construction of channel |
|
FLN-IS1 |
IS2 |
Impact Station
for FLN NDA |
Centreline of river, downstream of
the channel |
During construction of channel |
Table 6.1 Summary of Monitoring Activities,
Relevant Contracts, and Corresponding Transects
|
Monitoring Activity |
Relevant
Works Contract(s) |
Relevant
Transect(s)/Monitoring Station(s) |
|
|
First
Phase ET |
Remaining
Phase ET |
||
|
Monitoring of Measures to
Minimise Disturbance to Water Birds on Ng Tung, Sheung Yue, and Shek Sheung
Rivers and Long Valley |
ND/2024/01* |
T1, T2, T3, T5 |
- |
|
ND/2024/02* |
T1, T2, T3, T5 |
T4 |
|
|
ND/2024/03* |
T1, T2, T3, T5 |
- |
|
|
ND/2024/04* |
- |
T4 |
|
|
ND/2024/05 |
N/A(1) |
N/A(1) |
|
|
ND/2024/06* |
T1, T2, T3 |
- |
|
|
ND/2024/07* |
T1, T2, T3 |
T4 |
|
|
ND/2024/08* |
T1, T2, T3 |
T4 |
|
|
Monitoring of
Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen
Stream, and Long Valley |
ND/2024/01*^ |
MS_01,
MS_02, MS_03, MS_04, MS_05, MS_06,
MS_07, MS_08, MS_09, MS_10 |
- |
|
ND/2024/02*^ |
MS_01,
MS_02, MS_03, MS_04, MS_05, MS_06,
MS_07, MS_08, MS_09, MS_10 |
- |
|
|
ND/2024/03* |
N/A(2) |
N/A(2) |
|
|
ND/2024/04* |
N/A(2) |
N/A(2) |
|
|
ND/2024/05 |
N/A(2) |
N/A(2) |
|
|
ND/2024/06* |
N/A(2) |
N/A(2) |
|
|
ND/2024/07*^ |
MS_11,
MS_12, MS_13, MS_14, MS_15 |
- |
|
|
ND/2024/08*^ |
MS_11,
MS_12, MS_13, MS_14, MS_15 |
N/A(2) |
|
|
|
|
|
|
|
Monitoring
of Measures to Minimise Impacts on Ecological Sensitive Habitats from
Disturbance and Pollution |
ND/2024/01* |
T1 |
- |
|
ND/2024/02* |
T1, T6 |
- |
|
|
ND/2024/03* |
T4 |
- |
|
|
ND/2024/04* |
N/A(3) |
N/A(3) |
|
|
ND/2024/05 |
T4, T6 |
- |
|
|
ND/2024/06* |
- |
T2 |
|
|
ND/2024/07* |
T3 |
- |
|
|
ND/2024/08* |
T3
|
- |
|
Remarks:
(1)
Contracts that are located relatively far from
river channels.
(2)
Contracts that are located relatively far from Ma
Tso Lung and Siu Hang San Tsuen streams.
(3)
Contracts that are located relatively far from the
Ecological Sensitive Habitats as identified in the EIA.
(4)
* = active works contracts (ND/2024/01, ND/2024/02,
ND/2024/03, ND/2024/04, ND/2024/06, ND/2024/07 and ND/2024/08); ^ = monitoring
only in April October.
Monitoring Methodology
Monitoring
Parameters
·
Abundance of
birds;
·
Types of
habitats utilized by birds; and
·
Notable bird
behaviours such as roosting, feeding, nesting and presence of juveniles.
Monitoring Location
Table 6.2 Summary of Active Works Contracts
and Corresponding Transects
|
Monitoring |
Relevant
Works Contract(s) |
||||||
|
ND/2024/01 |
ND/2024/02 |
ND/2024/03 |
ND/2024/04 |
ND/2024/06 |
ND/2024/07 |
ND/2024/08 |
|
|
T1. Ng Tung River |
✓ |
✓ |
✓ |
|
✓ |
✓ |
✓ |
|
T2. Ng Tung River |
✓ |
✓ |
✓ |
|
✓ |
✓ |
✓ |
|
T3. Sheung Yue River |
✓ |
✓ |
✓ |
|
✓ |
✓ |
✓ |
|
T4. Shek Sheung River |
|
✓ |
|
✓ |
|
✓ |
✓ |
|
T5. Long Valley |
✓ |
✓ |
✓ |
|
|
|
|
Monitoring Frequency
Table 6.3 Monitoring Programme for Waterbirds Monitoring, March 2026
|
Week |
Date |
Transect(1) |
|
1 |
2 Mar 26 |
T1, T2 |
|
3 Mar 26 |
T4 |
|
|
5 Mar 26 |
T3, T4, T5 |
|
|
2 |
9 Mar 26 |
T1, T2 |
|
10 Mar 26 |
T4 |
|
|
11 Mar 26 |
T3, T5 |
|
|
12 Mar 26 |
T4 |
|
|
3 |
17 Mar 26 |
T3, T4, T5 |
|
19 Mar 26 |
T4 |
|
|
20 Mar 26 |
T1, T2 |
|
|
4 |
23 Mar 26 |
T3, T5 |
|
24 Mar 26 |
T1, T2, T4 |
|
|
26 Mar 26 |
T4 |
|
|
5 |
30 Mar 26 |
T3, T5 |
|
31 Mar 26 |
T1, T2, T4 |
|
|
Additional Nighttime |
17 Mar
26 |
T5 |
|
30 Mar
26 |
Remarks:
(1)
Transects T1, T2, T3, and T5 are relevant to Works
Contract ND/2024/01 and ND/2024/03; Transect T4 is relevant to Works Contract
ND/2024/04; Transects T1, T2, and T3 are relevant to Works Contract ND/2024/06;
Transects T1, T2, T3 and T4 are relevant to Works Contract ND/2024/07 and
ND/2024/08; Transect T1, T2, T3, T4 and T5 are relevant to Works Contract No.
ND/2024/02.
Monitoring Results
Table 6.4
Summary Table of Waterbird Monitoring Results Relative to Corresponding Action
and Limit Levels, March, Transects T1, T2, T3, T4 and T5
|
Monitoring Parameter |
Result in Reporting Month |
Baseline Level in Corresponding Month |
Action |
Limit |
|
|
T1, T2
and T3 |
|||||
|
Mean abundance of large waterbirds using Ng
Tung River, Sheung Yue River and Shek Sheung River (3) |
98 |
26 |
18 |
13 |
|
|
Mean abundance of Chinese Pond Heron using Ng
Tung River, Sheung Yue River and Shek
Sheung River |
16 |
12 |
8 |
6 |
|
|
T4 |
|||||
|
Mean abundance of large waterbirds using Shek
Sheung River (3) |
9 |
5 |
3 |
2 |
|
|
Mean abundance of Chinese Pond Heron using
Shek Sheung River |
4 |
4 |
3 |
2 |
|
|
T5 Long
Valley |
|||||
|
Mean Abundance of birds (all species)
recorded in LVNP |
1027 |
564 |
395 |
282 |
|
|
Mean abundance of the Chinese Pond Heron |
10 |
12 |
9 |
6 |
|
|
Environmental disturbance and damage from
activities in LVNP |
- |
- |
Activity likely to cause unacceptable environmental disturbance or damage noted in LVNP. |
Activity likely to cause unacceptable environmental disturbance or damage noted in LVNP. |
|
Remarks:
(1)
Exceedance of Action Level occurs when the
monitoring result is lower than the Action Level.
(2)
Exceedance of Limit Level occurs when the
monitoring result is lower than the Limit Level.
(3)
Large waterbird species for mean abundance
calculation include Great Cormorant (Phalacrocorax carbo); Grey Heron (Ardea
cinerea); Great Egret (Ardea alba); Intermediate Egret (Ardea
intermedia); Little Egret (Egretta garzetta) and Chinese Egret (Egretta
eulophotes).
Monitoring of
Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance
and Pollution
Monitoring Methodology
Terrestrial Mammal
Herpetofauna (Amphibians and Reptiles)
Butterfly and Odonates
Monitoring Parameters
·
Species
composition;
·
Abundance;
·
Distribution for
fauna observed; and
·
Species of
conservation importance would be specified.
Monitoring Location
·
T1. Ma Tso Lung
riparian zone and associated wetland habitats; green belt areas E1-8, D1-8 and
G1-3 in KTN NDA; AGR zone C2-4 and C2-2 in
KTN NDA, and area north of Ng Tung River;
·
T2. Fanling
North Freshwater Service Reservoir
·
T3. Area west of
Siu Hang San Tsuen Stream;
·
T4. South side
of Fanling Highway and Castle Peak Road in the vicinity of Pak Shek Au;
·
T5. Area west
and east of the southern limit of the FLN NDA work area; and
·
T6. Areas in the
western part of KTN.
Monitoring Frequency
|
Responsible ET |
Date |
Transect(1) |
|
First Phase ET |
3 Mar
26 |
T3, T4 |
|
6 Mar
26 |
T1, T6 |
|
|
Remaining Phase ET |
25 Mar
26 |
T2 |
Remarks:
(1)
Transect T1 is relevant to Works Contract
ND/2024/01 and Works Contract ND/2024/02; Transect T2 is relevant to Works
Contract ND/2024/06; Transect T3 is relevant to Works Contracts ND/2024/07 and
ND/2024/08; Transect T4 is relevant to Works Contract ND/2024/03; Transect T6
is relevant to Works Contract ND/2024/02.
Monitoring Results
Terrestrial Mammals
Herpetofauna (Amphibians and Reptiles)
Butterfly and Odonates
Summary of Monitoring Results
Table 6.6
Summary Table of Monitoring Results for Non-aquatic Fauna Relative to Action
and Limit Levels, March 2026, Transect T1, T2, T3, T4 and T6
|
Monitoring
Parameter |
Result
in |
Baseline Level in Corresponding
Month (March 2020) (1) |
Action Level(2) |
Limit Level(3) |
|
T1 |
||||
|
Terrestrial Mammals |
0 |
1 |
N/A |
N/A |
|
Herpetofauna |
3 |
4 |
3 |
2 |
|
Odonates |
3 |
5 |
4 |
3 |
|
Butterflies |
24 |
9 |
6 |
5 |
|
T2 |
||||
|
Terrestrial Mammals |
6 |
0 |
N/A |
N/A |
|
Herpetofauna |
3 |
0 |
N/A |
N/A |
|
Odonates |
3 |
1 |
N/A |
N/A |
|
Butterflies |
18 |
4 |
3 |
2 |
|
T3 |
||||
|
Terrestrial Mammals |
2 |
1 |
N/A |
N/A |
|
Herpetofauna |
1 |
2 |
N/A |
1 |
|
Odonates |
1 |
4 |
3 |
2 |
|
Butterflies |
4 |
4 |
3 |
2 |
|
T4 |
||||
|
Terrestrial Mammals |
1 |
0 |
N/A |
N/A |
|
Herpetofauna |
4 |
3 |
2 |
1 |
|
Odonates |
1 |
2 |
N/A |
1 |
|
Butterflies |
8 |
6 |
4 |
3 |
|
T6 |
||||
|
Terrestrial Mammals |
0 |
0 |
N/A |
N/A |
|
Herpetofauna |
1 |
2 |
N/A |
1 |
|
Odonates |
1 |
3 |
2 |
1 |
|
Butterflies |
7 |
5 |
4 |
3 |
Remarks:
(1)
Number of species (species richness) recorded; the
results in the reporting month for terrestrial mammals, herpetofauna and
odonates are calculated based on the number of native species recorded along
the transects.
(2)
Exceedance of Action Level occurs when the
monitoring result is lower than the Action Level.
(3)
Exceedance of Limit Level occurs when the
monitoring result is lower than the Limit Level.
Details of the Influencing
Factors
Survey Summary
·
Compendium
Method 1O-3.1 Selection, Preparation and Extraction of Filter Material, Center
for Environmental Research Information, Office of Research and Development,
USEPA, June 1999; and Compendium Method 1O-3.5 determination of Metals in
Ambient Particulate Matter using Inductively Coupled Plasma/Mass Spectrometry
(ICP/MS., Center for Environmental Research Information, Office of Research and
Development, USEPA, June 1999.
Table 8.1 Location of Ambient Arsenic Monitoring station
|
Monitoring Station(s) |
Location(s) |
Works Contract(s) |
|
KTN-DMS-4A(1)(2) |
Temporary Structure at Pak Shek Au |
ND/2024/01 |
Remarks:
(1)
Monitoring at the original
location of KTN-DMS-4 (originally proposed in the approved EM&A Manual) was
denied as there was no electricity supply. An alternative location (KTN-DMS-4A)
was proposed by First Phase ET.
(2)
The ambient arsenic
monitoring was conducted by First Phase ET during the reporting period.
Table
8.2 Ambient Arsenic Monitoring Equipment
|
Monitoring Station |
Equipment |
Manufacturer |
Model |
No.
of Equipment |
|
KTN-DMS-4A(1)(2) |
Calibrator |
TISCH |
TE-5025A |
1 |
|
HVS
Sampler (RSP) |
TISCH |
TE-6070X |
1 |
Remarks:
(1) Monitoring
at the original location of KTN-DMS-4 (originally proposed in the approved
EM&A Manual) was denied as there was no electricity supply. An alternative
location (KTN-DMS-4A) was proposed by First Phase ET.
(2) The ambient arsenic monitoring was conducted by
First Phase ET during the reporting period.
Table
8.3 Impact Ambient Arsenic Monitoring
Parameters, Frequency and Duration
|
Parameters |
Frequency(1) |
|
24-hour RSP (Ambient Arsenic) |
Once/ 6 days |
Remark:
1. The ambient arsenic monitoring was conducted by
First Phase ET during the reporting period.
Instrumentation
·
a horizontal
platform with appropriate support to secure the samplers against gusty wind was
provided;
·
no two samplers
were placed less than 2 meters apart;
·
the distance
between the sampler and an obstacle, such as buildings, was at least twice the
height that the obstacle protrudes above the sampler;
·
a minimum of 2
meters of separation from walls, parapets and penthouses was required for
rooftop samplers;
·
a minimum of 2
meters separation from any supporting structure, measured horizontally was
required;
·
no furnace or
incinerator flue was nearby;
·
airflow around
the sampler was unrestricted;
·
the sampler was
more than 20 meters from the dripline;
·
any wire fence
and gate, to protect the sampler, were not cause any obstruction during
monitoring;
·
permission was
obtained to set up the samplers and to obtain access to the monitoring
stations; and
·
a secured supply
of electricity was needed to operate the samplers
Operating/analytical
procedures for the operation of HVS
· Prior to the commencement of the dust sampling, the flow rate of the high volume sampler was properly set (between 1.1 m3 /min. and 1.4 m3 /min.) in accordance with the manufacturer's instruction to within the range recommended in USEPA Standard Title 40, CFR Part 50;
· The power supply was checked to ensure the sampler worked properly. On sampling, the sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter media at the designated air monitoring station;
· The filter holding frame was then removed by loosening the four nuts and a weighted and conditioned filter was carefully centered with the stamped number upwards, on a supporting screen;
·
The filter was
aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter. The filter holding frame was then tightened to the filter
holder with swing bolts. The applied pressure was sufficient to avoid air
leakage at the edges;
·
The shelter lid
was closed and secured with the aluminium strip;
·
The timer was
then programmed. Information was recorded on the record sheet, which included
the starting time, the weather condition and the filter number (the initial
weight of the filter paper can be found out by using the filter number);
·
After sampling,
the filter was removed and sent to the Wellab Ltd. for weighing. The elapsed
time was also recorded; and
·
Before weighing,
all filters were equilibrated in a conditioning environment for 24 hours. The
conditioning environment temperature was between 25°C and 30°C and did not vary
by more than ±3°C; the relative humidity (RH) was < 50% and did not vary by more
than ±5%. A convenient working RH was 40%. Weighing results were further
analysis of RSP concentrations collected by each filter.
·
The high volume
motors and their accessories were properly maintained. Appropriate maintenance
such as routine motor brushes replacement and electrical wiring checking were
made to ensure that the equipment and necessary power supply were in good
working condition; and
·
High volume
samplers were calibrated at bi-monthly intervals using TE-5025A Calibration Kit
throughout all stages of the ambient arsenic monitoring.
Table
8.4 Result Summary Against Action and Limit
Levels for 24-hour RSP Monitoring Results (Ambient Arsenic)
|
Contract No. |
Monitoring Date |
Monitoring Station |
Concentration (ƞg/m3) |
AL (ƞg/m3) |
LL (ƞg/m3) |
|
ND/2024/01 |
3/3/2026 |
KTN-DMS4A* |
3.37 |
9.36 |
11.7 |
|
9/3/2026 |
5.61 |
||||
|
13/3/2026 |
5.81 |
||||
|
19/3/2026 |
4.50 |
||||
|
25/3/2026 |
4.11 |
||||
|
31/3/2026 |
3.47 |
Remark:
* The 24-hour RSP monitoring
for ambient arsenic was conducted by First Phase ET during the reporting period.
Ψ Excavation Locations: N/A
Ψ Manholes and Chambers: N/A
Ψ Relocation of monitoring wells: N/A
Ψ Any other Confined Spaces: N/A
Table
10.1 Location of Construction Vibration Monitoring
|
EP No. |
Contact No. |
Monitoring Station(s) |
Nature of Cultural
Heritage |
Location(s) |
|
NIL |
NIL |
NIL |
NIL |
NIL |
Table
10.2 Vibration Monitoring Plan
|
EP No. |
Contact No. |
Monitoring Station(s) |
Distance with
Construction Works |
Monitoring Plan |
|
NIL |
NIL |
NIL |
Within 50m Within 75m Within 100m |
Daily assessment is required Bi-daily assessment is required Weekly assessment is required |
Remarks:
(1) Baseline
condition survey was conducted for built heritage features at G302, G303, G308,
KT26, KT53, KT65 and HKT03 for ND/2024/01 under EP-468/2013/A, G102, G202,
G203, G303 and HKT03 for ND/2024/03 under EP-465-2013A and EP-466/2013A. As G102,
G202, G203, G302, G303, G308, HKT03, KT26, KT 53 and KT65 were not within the
assessment area of the related construction work, no construction vibration
monitoring was conducted for the built heritage in the reporting month.
Table
10.3 Levels of Alert, Alarm and Actions for Tilting, Vibration and Settlement
|
Monitoring Types |
Alert |
Alarm |
Acton |
|
Tilting |
1:2000 |
1:1500 |
1:1000 |
|
Settlement |
6 mm |
8 mm |
10 mm |
|
Ground Settlement |
15 mm |
20 mm |
25 mm |
|
Vibration (PPV) |
5 mm/s |
6 mm/s |
7.5 mm/s |
Table 11.1 Site Observations at Works Contract No. ND/2024/01, ND/2024/02, ND/2024/03, ND/2024/04, ND/2024/06 and
ND/2024/07 during the Reporting Period
|
Works
Contracts |
Inspection
Date |
Key
Observations/ Reminders |
Follow-up
Action |
|
ND/2024/01 |
3 March 2026 |
Observation: Nil |
Nil |
|
Reminder: 1. Contractor was reminded that the area within 30m of construction site entrance or exit shall be kept clear of dusty materials in order to avoid fugitive dust emission at Portion 40. |
Nil |
||
|
10 March 2026 |
Observation: Nil |
Nil |
|
|
Reminder: 1. Contractor was reminded that the temporary
ditches should be provided to facilitate the runoff discharge into an
appropriate watercourse, through a silt/sediment trap at Portions 10, 11, 23. |
Nil |
||
|
19 March 2026 |
Observation: Nil |
Nil |
|
|
Reminder: Nil |
Nil |
||
|
27 March 2026 |
Observation: 1. At Portion 40,
dusty materials or earth should be kept clear of the area within 30m of the
construction site entrance or exit. |
1. The construction site entrance / exit was
wetted and cleared of dusty material. (Rectified on 27 March 2026) |
|
|
Reminder: Nil |
Nil |
||
|
ND/2024/02 |
3 March 2026 |
Observation: Nil |
Nil |
|
Reminder: Nil |
Nil |
||
|
10 March 2026 |
Observation: Nil |
Nil |
|
|
Reminder: Nil |
Nil |
||
|
19 March 2026 |
Observation: Nil |
Nil |
|
|
Reminder: Nil |
Nil |
||
|
27 March 2026 |
Observation: Nil |
Nil |
|
|
Reminder: Nil |
Nil |
||
|
ND/2024/03 |
2 March 2026 |
Observation: Nil |
Nil |
|
Reminder: Nil |
Nil |
||
|
9 March 2026 |
Observation: Nil |
Nil |
|
|
Reminder: 1. Stagnant water inside the drip trays were
observed in oil drums near the Sheung Yue River. The contractor was reminded
to clear the stagnant water regularly after raining. |
Nil |
||
|
20 March 2026 |
Observation: Nil |
Nil |
|
|
Reminder: Nil |
Nil |
||
|
25 March 2026 |
Observation: Nil |
Nil |
|
|
Reminder: 1. The contractor was reminded that to review the effectiveness of
the silt curtain regularly and remove mud and silt at Sheung Yue River
worksite to avoid accumulation. |
Nil |
||
|
30 March 2026 |
Observation: Nil |
Nil |
|
|
Reminder: 1. Stagnant water inside the
drip trays were observed in oil drums near the Sheung Yue River.
The contractor was reminded to clear the stagnant water regularly after
raining. |
Nil |
||
|
ND/2024/04 |
6 March 2026 |
Observation: Nil |
Nil |
|
Reminder: 1. Contractor was reminded to replace the discoloured NRMM label on PME
(excavator) at Portion 1. |
Nil |
||
|
13 March 2026 |
Observation: 1. The Contractor shall ensure proper site drainage
is functioning and measures to prevent site run-off going onto public areas
at Portion 1. |
1. The drainage was functioned and cement seal was provided. (Rectified on 16 March 2026) |
|
|
Reminder: Nil |
Nil |
||
|
20 March 2026 |
Observation: Nil |
Nil |
|
|
Reminder: Nil |
Nil |
||
|
24 March 2026 |
Observation: Nil |
Nil |
|
|
Reminder: Nil |
Nil |
||
|
ND/2024/06 |
2 March 2026 |
Observation: 1. Drip tray should be provided for storing
chemicals at Portion D. |
1. The concerned chemical container was removed. |
|
Reminder: 1. The
Contractor was reminded to regularly clean up dusty materials on the surfaces
of the main haul road at Area C. |
Nil |
||
|
9 March 2026 |
Observation: 1. Drip tray should be provided for storing
chemicals at Portion C. 2. NRMM label should be displayed on the roller at
Area C. |
1. The concerned chemical container was
removed. 2. NRMM
label was displayed on the roller. |
|
|
Reminder: 1. The
Contractor was reminded to cover stockpiles with tarpaulin when they are not
in use at Portions C and D. 2. The Contractor
was reminded to replace the faded NRMM labels on the generator at Portion D
and on the crawler crane at Pit C. |
Nil |
||
|
16 March 2026 |
Observation: 1. Impervious sheeting should be provided for placing the
machinery equipment to prevent oil spillage at Area C and Pit C. |
1. Impervious sheeting was provided for placing the breaker heads. |
|
|
Reminder: 1. The Contractor was
reminded to ensure stockpiles are covered with tarpaulin when they are not in
use at Area C and Portion F. 2. The
Contractor was reminded to provide containers for temporary storage of
general waste at Area C. 3. The
Contractor was reminded to replace the faded NRMM labels on the excavators at
Portions D and F. |
Nil |
||
|
23 March 2026 |
Observation: 1. Sandbags/ Bunding should be provided to prevent any sand and silt washing into the nearby watercourse at Portion D. 2. Impervious sheeting should be provided for properly placing the
breaker head to prevent oil spillage at Area C and Portion D. 3. Drip trays should
be provided for storing chemicals at Portion C. |
1. Sandbags/ Bunding were provided to prevent any sand and silt washing into the nearby watercourse at Portion D. 2. Impervious sheeting was provided for properly placing the breaker
head to prevent oil spillage at Area C and Portion D. 3. Drip trays were
provided for storing chemicals at Portion C. |
|
|
Reminder: 1. The Contractor was
reminded that regular water spraying for dust suppression shall be provided
during excavation works in Portion C.
3. The Contractor was reminded to wrap the acoustic
mat on the breaker head during construction works at Area C. |
Nil |
||
|
30 March 2026 |
Observation: 1. The outfall of the sump pit should be completely sealed to prevent the collected surface runoff being directly washed into the drainage system at Pit B. 2. Impervious
sheeting should be provided for properly placing the breaker head to prevent
oil spillage at Portion D. |
1. Sand
bags were deployed at the outfall of the sump pit. 2. Impervious
sheeting was provided for placing the breaker heads. |
|
|
Reminder: 1. The Contractor was
reminded to properly cover exposed slope for dust suppression when no works
are performed nearby at Portion C. |
Nil |
||
|
ND/2024/07 |
5 March 2026 |
Observation: 1. The Contractor
should provide sandbags or bundings to prevent washing of sand and silt out
of site area at FB-4(s). |
1. Bunding has been formed to prevent the
sand and silt from washing out of the site area. (Rectified on 6 March 2026) |
|
Reminder: Nil |
Nil |
||
|
12 March 2026 |
Observation: Nil |
Nil |
|
|
Reminder: 1. The Contractor was reminded to
provide regular water spraying on main haul road at Area K. 2. Any
excavated or stockpile of dusty material should be covered entirely by
impervious sheeting when no construction work occurred at Area K. |
Nil |
||
|
19 March 2026 |
Observation:
|
Nil |
|
|
Reminder:
|
Nil |
||
|
26 March 2026 |
Observation: 1. Sand bags or bundings should be provided to prevent any runoff
flowing out of site at FB-4(s). 2. Drip tray should be provided for storing chemical containers at
Road L2. 3. Impervious sheeting should be provided for placing the breaker head
to prevent oil spillage at Area E. |
1. Sand bags have been provided. (Rectified
on 26 March 2026)
3. Impervious sheeting has been provided.
(Rectified on 26 March 2026) |
|
|
Reminder:
|
Nil |
Table
11.2 Photographic Records and Implementation Status of Measures for Ecological
Impacts
|
Works Contracts |
EP No. |
Photographic Record |
Implementation
Status |
||
|
ND/2024/01 |
EP-467/2013/A (Condition 2.9) |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the
Project, 2m high solid dull green site barrier fences shall be erected around
all active works areas. |
^ |
||
|
EP-468/2013/A (Condition 2.11) |
|||||
|
ND/2024/03 |
EP-465/2013/A (Condition 2.9) |
To minimise adverse impacts on habitats of ecological importance
in the vicinity of the Project, 2m high solid dull green site barrier fences
shall be erected around all active works areas. |
^ |
||
|
EP-466/2013/A (Condition 2.9) |
|||||
|
EP-467/2013/A (Condition 2.11) |
|
Implementation
status: |
^ Mitigation measure was fully implemented |
|
* Observation / reminder was made during
site audit but improved / rectified by the contractor |
|
|
# Observation / reminder was made during
site audit but not yet improved / rectified by the contractor |
|
|
X Non-compliance of mitigation measure |
|
|
Non-compliance but rectified by the contractor |
|
|
|
N/A Not Applicable at this stage as no such
site activities were conducted in the reporting period |
Works Contract No. ND/2024/01:
· All Site Resumption Area(s)
1.
Tree survey
2.
Site Clearance
· Portion III (3), IV (4), V (5),
VII (7) and XXXV (35)
1.
Site Formation
· Portion VIII (8)
1.
Site Clearance & Demolition
· Portion XVIII (18), XXXVIII (38)
1.
Excavation works
2.
Construction of CHC Box Culvert
· Portion XI (11), XXIII (23)
1.
Erection of Substructure of Metropolis Community Liaison and Visitor
Centre
· Portion XL (40)
1.
Retaining
Wall Construction
2.
Drainages
System Construction
3.
ELS
work
· Portion LIX (59)
1.
Treatment of
High Arsenic-Containing Soil (HAS)
2.
Erection of
Shredding Facility
· Portion XVII (17), XVII (18), XXI (21), XXXIV (34),
XXXV (35), XLI (41), XLII (42)
1.
Excavation
Works
2.
Drainage Pipe
Installation
3.
ELS Works
· Portion XXV (25), XXVII (27), XXXIII (33), XLII
(42) and XLIV (44)
1. Site Clearance
2. Site Formation
3. Construction of Box Culvert
n
Works Contract No.
ND/2024/02:
1.
Site clearance in Area A,
B, C, D, T, L
2.
Site formation works in
Area D
3.
Temporary storage fill bank
in Kwu Tung Grass Soccer Pitch
4.
Demolition works for
Community Sports in Area J
5.
Asbestos Survey
6.
Ground Investigation Works
n
Works Contract No.
ND/2024/03:
Fanling Highway & Castle Peak Road area
· Pak Sau Road Po Lau Road
1.
Tree Works
· Po Lau Road Sheung Yue River
1.
Asbestos
Removal Works at Portion IX
2.
Box Culvert
Bay 37 Bay 42 ELS
3.
Tree Works
· TTA Stage 1 Works
1.
Tree Works
New Tsung Pak Long Road
· Box culvert Bay 10 to 12, 14 to 16 Drainage/Watermains
1.
Drainage,
Sewerage & Watermain with Backfilling at Box Culvert Bay 15 & 16
2.
Box Culvert
Bay 14 ELS
· Box culvert Bay 17 to 19 & Drainage/Watermains
1.
Box Culvert
Bay 17 to 19 ELS, Base Slab, Wall and Top Slab
2.
Box culvert
Bay 17 & 19 Base Slab
· Retaining Wall RW01
1.
Pre-drilling
· Retaining Wall RW05A
1.
RW05A ELS
· Kwu Tung Road Bridge
1.
Site
Clearance and Tree Works
2.
Site
formation and cutback the existing slope
3.
Predrilling
4.
Foundation
& Piling
· Works Areas WA1, WA2, WA3, WA4 & WA5
1.
Site
Formation at PMs Site Office
2.
Site
Clearance, haul road and Temporary Drainage
3.
Asbestos
removal
Fanling Highway Cross River Bridge (along Sheung Yue River)
· Portion XI East Abutment & pier foundation
1.
Trial Pits
for UUs
2.
Piling Works
· Road L3 Viaduct
1.
Piling Works
2.
Pile Cap
L3A-02
· Kwu Tung Interchange Foundation & Substructure
- Bridge B1 & C1
1.
Piling Works
· Widening of Existing Bridge No.N526
1.
Tree Works
2.
ELS
3.
Pilling
n
n Works Contract No. ND/2024/04:
· Site Clearance
· Site Establishment
· Tree Felling
· Trial Pit
· Pre-drilling
· Ground Investigation
· Existing Sewage Diversion
· Demolition of Existing Structures
· Haul Road Construction
· Bored Piling
· ELS Construction
· Slope Works
· Sheet Piling
n
n Works Contract No. ND/2024/06:
· Portion A
1.
Excavation to +90 mPD of
Portion A
2. Forming Haul Road form Area C to Portion A
· Portion C, D, E
& F
1.
Trench
and Watermans Laying Works
· Area N
1.
Jacking Pit
Excavation
· Pre-boring of Pit B & C
n
Works Contract No. ND/2024/07:
1. Site Clearance
2. Site Formation
3. Ground Investigation
4. Pre-bored Socketed H Pile Construction
5. Bridge Construction
6. Bridge Deck Connection (Footbridge FB5)
7. Lift Tower Construction
8. Sump Pit Construction
9. ABWF Works
10. Drainage Construction
11. Improvement of Junction
12. Road Construction
13. Temporary Road Construction
14. Open Landscaping Works
15. Tree Felling & Transplantation
16. Asbestos Containing Materials Survey & Removal
17. Land Contamination (Environmental Ground Investigation)
18. Internal Movement, Importation & Exportation of C&D materials
19. Sewage Construction
20. Old Shrine Removal and New Shrine
Construction
21. Storm pipe Construction
22. Box Culvert Construction
23. Temporary Drainage Diversion
24. Rebar yard
25. Storage Yard for Concrete Pipe
n
n
Works Contract No.
ND/2024/05 and No. ND/2024/08:
1.
The
construction work has not commenced in the reporting month.
Dust
Regular watering to reduce dust emissions from exposed site surface;
Stockpile of dusty materials shall be covered entirely by impervious sheeting;
Provide vehicles washing facilities at all site exits to wash away any dusty materials from vehicle body;
NRMM Labels should be displayed on the applicable equipment on site by the Contractor;
Provision of water sprinklers along the haul road for dust suppression.
Noise
Only well-maintained plant should be operated on-site, and plant should be maintained regularly during the construction programme; and
Quality Powered Mechanical Equipment (QPME) should be adopted as far as possible.
Water
Quality
No effluent discharge would be allowed before acquired the effluent discharge license;
Surface run-off from construction sites should be discharged into dedicated discharge point via adequately designed sand/ silt removal facilities;
Channels/ earth bunds/ sandbags barriers should be provided on site to properly direct stormwater to silt removal facilities;
Silt removal facilities, channels and manholes should be maintained, and the deposited silt and grit should be removed regularly;
Open stockpiles of construction materials on sites should be covered with tarpaulin or similar fabric during rainstorms; and
Perimeter channels should be provided on site boundaries where necessary to intercept stormwater run-off from outside the site so that it will not wash across the site.
Waste
Management
Provision of sufficient waste disposal points and regular collection of waste;
Regular cleaning and maintenance programme for drainage system; and
Chemical containers shall be stored with drip tray underneath.
Landscape
and Visual
Construction activities shall be carefully designed to minimize impact on existing retained trees.
Land Contamination
Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be properly covered by impermeable sheeting to reduce dust emission during dry season or contaminated run-off during rainy season. Watering should be avoided on stockpiles of soil to minimise runoff.
Landfill Gas Hazard
No Smoking and No Naked Flame notices in Chinese and English should be posted prominently around the construction site.
Ecology
Properly erect and maintain 2m high solid barriers for protection.
An individual of orchid Eulophia cernua was found growing underneath the
pipeline adjacent to the access road leading to the summit of the Table Hill
Freshwater Service Reservoir for Contract No. ND/2024/06. The species of
conservation importance should be fenced off for protection to minimise the
potential impacts aroused from nearby construction activities as far as
possible.