Skip to main content

Works Progress

map
N
E
W
S
Contract No. ND/2019/01

Kwu Tung North New Development Area, Phase 1:
Site Formation and Infrastructure Works

ScopeThe works mainly comprise site formation of land under the First Phase of KTN NDA (including soil treatment works); construction of engineering infrastructures including drainage works, sewerage works (including temporary sewage treatment facilities), waterworks (including a fresh water service reservoir and a flushing water service reservoir), roadworks (including carriageway, footpaths, cycle tracks, a subway and junction improvement), pipeworks for district cooling system, slope works and landscaping works; and construction of associated environmental mitigation works including noise barriers/noise enclosures and low noise road surfacing.
Commencement Date6 December 2019
Completion Date2026 (tentative)
Contract Sum $2.888 Billion
ContractorBuild King – Richwell Engineering Joint Venture
Contract No. ND/2019/02

Kwu Tung North New Development Area, Phase 1:
Roads and Drains between Kwu Tung North
New Development Area and Shek Wu Hui

ScopeThe contract mainly comprises road and drainage works between Kwu Tung North New Development Area and Shek Wu Hui; construction of a sewage pumping station, a visitor centre for Long Valley Nature Park and a footbridge spanning across Sheung Yue River; and site formation of land and the associated engineering infrastructure works for a village resite area in Kwu Tung North New Development Area.
Commencement Date17 February 2020
Completion Date2026 (tentative)
Contract Sum$1.04 Billion
ContractorChun Wo – Kwan Lee Joint Venture
Contract No. ND/2019/03

Kwu Tung North New Development Area, Phase 1:
Development of Long Valley Nature Park

ScopeThe contract mainly comprises development of a nature park at Long Valley and ecological mitigation and enhancement works for the nature park.
Commencement Date19 December 2019
Completion DateEarly 2024
Contract Sum$0.324 Billion
ContractorSang Hing – Kuly Joint Venture
Contract No. ND/2019/04

Fanling North New Development Area, Phase 1:
Fanling Bypass Eastern Section
(Shek Wu San Tsuen North to Lung Yeuk Tau)

ScopeThe contract mainly comprises construction of an approximately 2-kilometre-long dual two-lane Fanling Bypass Eastern Section between Shek Wu San Tsuen North and Lung Yeuk Tau comprising viaduct, at-grade road and underpass sections; construction of Lung Yeuk Tau Interchange connecting Fanling Bypass Eastern Section with existing Sha Tau Kok Road – Lung Yeuk Tau; construction of a footbridge across Ng Tung River and a cycle track cum footbridge over Lung Yeuk Tau Interchange; construction of a sewage pumping station adjacent to Lung Yeuk Tau Interchange; reprovisioning of the On Lok Mun Street Playground, public toilet and refuse collection point near Lung Yeuk Tau Interchange; road junction improvement works in the North District; and associated ground investigation, geotechnical instrumentation and monitoring, slope and retaining wall works, drainage and sewerage works, waterworks, noise barrier works, traffic control and surveillance system installation, electrical and mechanical works and landscaping works.
Commencement Date14 August 2020
Completion Date2026 (tentative)
Contract Sum $3.501 Billion
ContractorDaewoo – Chun Wo – Kwan Lee Joint Venture
Contract No. ND/2019/05

Fanling North New Development Area, Phase 1:
Fanling Bypass Eastern Section
(Shung Him Tong to Kau Lung Hang)

ScopeThe contract mainly comprises construction of an approximately 2 kilometres (km) long dual two-lane Fanling Bypass Eastern Section between Shung Him Tong and Kau Lung Hang mainly on viaducts with two long span overbridges across the existing East Rail Line; realignment of part of the existing Tai Wo Service Road East, Tai Wo Service Road West and Fanling Highway; construction of approximately 2.4 km long noise barriers, and relocation of approximately 400 metres long existing noise barriers along Fanling Highway; alteration and addition works to the existing Ho Ka Yuen footbridge; reprovisioning of a bus-bus interchange at Fanling Highway with a proposed public toilet and covered walkway; and associated slope works, ground investigation, geotechnical instrumentation and monitoring, retaining wall, drainage works, waterworks, sewerage works, traffic control and surveillance system installation, electrical and mechanical works and landscaping works.
Commencement Date2 March 2020
Completion Date2026 (tentative)
Contract Sum$3.34 Billion
ContractorChina Railway 15 Bureau Group Co., Ltd. – Paul Y. Construction Company, Limited Joint Venture
Contract No. ND/2019/06

Fanling North New Development Area, Phase 1:
Reprovisioning of North District
Temporary Wholesale Market for Agricultural Products

ScopeThe contract mainly comprises construction of an in-situ reprovisioned NDTWM and its facilities involving a steel canopy for the trading area and a management office building.
Commencement Date 27 September 2019
Completion Date17 March 2022 (actual completion)
Contract Sum$0.232 Billion
ContractorNew Concepts Engineering Development Limited
Contract No. ND/2019/07

Fanling North New Development Area, Phase 1:
Site Formation and Infrastructure Works

ScopeThe works mainly comprise site formation of land under the First Phase of Fanling North New Development Area; and construction of engineering infrastructures including drainage and sewerage works, waterworks, roadworks (including carriageway, footpaths and cycle tracks), noise barrier works, slope works and landscaping works.
Commencement Date31 August 2020
Completion Date2025
Contract Sum$0.442 Billion
ContractorChina Road and Bridge Corporation
Contract No. ND/2024/01

Kwu Tung North New Development Area, Remaining Phase:
Site Formation and Infrastructure Works (South)

ScopeThe works mainly comprise site formation of lands (including site clearance and land decontamination works) and ground investigation within Kwu Tung North New Development Area (KTN NDA); construction of at-grade roads within KTN NDA connecting to Castle Peak Road (Kwu Tung Section) and Fanling Highway; construction of a vehicular bridge connecting proposed Road L1 and Road L2; construction of footbridges at proposed Road P2; construction of noise barriers and low noise road surfacing; construction of common utility enclosure and associated works; construction of a visitor centre; and ancillary works including footpaths, cycle tracks, lighting, traffic aids, drainage, sewerage, water mains, district cooling mains, landscaping works, slope works and electrical and mechanical works.
Commencement Date23 August 2024
Completion DateMid 2030 (tentative)
Contract Sum$4.107 Billion
ContractorBuild King – Richwell Engineering Joint Venture
Contract No. ND/2024/02

Kwu Tung North New Development Area, Remaining Phase:
Site Formation and Infrastructure Works (North)

ScopeThe works mainly include site formation of lands (including site clearance and land decontamination works) and ground investigation within Kwu Tung North New Development Area (KTN NDA); construction of at-grade roads within KTN NDA; construction of noise barriers and low noise road surfacing; and ancillary works including footpaths, cycle tracks, lighting, traffic aids, drainage, sewerage, water mains, district cooling mains, landscaping works, slope works, flood prevention works and electrical and mechanical works.
Commencement Date2nd half of 2025 (tentative)
Completion DateMid 2030 (tentative)
Contract SumTo be confirmed
ContractorTo be confirmed
Contract No. ND/2024/03

Kwu Tung North New Development Area, Remaining Phase:
Improvement Works of Fanling Highway (Kwu Tung Portion) and
Associated Works

ScopeThe works mainly comprise site clearance and formation (including land decontamination works); widening of Fanling Highway (Kwu Tung Portion); modification of Castle Peak Road (Kwu Tung Portion); construction of footbridges across Fanling Highway (Kwu Tung Portion); construction of Kwu Tung Interchange; modification of Kwu Tung Road and construction of Road L3; construction of associated works including water mains, drainage and sewerage works, roadworks, cycle tracks, footpaths, box culverts, junction improvement works, slope works, retaining walls, street furniture, landscaping works, electrical and mechanical works and other ancillary works; implementation of environmental mitigation measures (including noise enclosures, noise barriers and low-noise road surfacing) and environmental monitoring works for the works mentioned above; and installation of Traffic Control and Surveillance System and conduction of associated testing and commissioning of Fanling Highway (Pak Shek Au, Kwu Tung and Tai Tau Leng Portion).
Commencement Date14 August 2024
Completion DateMid 2030 (tentative)
Contract Sum$4.833 Billion
ContractorChina State – Shanghai Tunnel Engineering Co., Ltd. Joint Venture
Contract No. ND/2024/04

Kwu Tung North New Development Area, Remaining Phase:
Improvement Works of Tai Tau Leng Roundabout and
Po Shek Wu Road and Associated Works

ScopeThe works mainly include widening of Fanling Highway (Tsung Pak Long to Tai Tau Leng Roundabout Portion); modification of Tsung Pak Long local road; construction of footbridge across Fanling Highway (Tsung Pak Long Portion); construction of Po Shek Wu Road Flyover connected to Fanling Highway westbound; road improvements at Tai Tau Leng Roundabout and Po Shek Wu Road; extension of existing subways no. NS201 and NS201A; construction of footbridge and cycle track at Po Shek Wu Road across MTR East Rail Line; construction of associated works including water mains, drainage and sewerage works, roadworks, cycle tracks, footpaths, box culverts, junction improvement works, slope works, retaining walls, street furniture, landscaping works, electrical and mechanical works and other ancillary works; and implementation of environmental mitigation measures (including noise enclosures, noise barriers and low-noise road surfacing) and environmental monitoring works for the works mentioned above.
Commencement Date31 December 2024
Completion DateMid 2030 (tentative)
Contract Sum$1.598 Billion
ContractorChun Wo – China Railway 15 Bureau Group Co., Ltd. (ND202404) Joint Venture
Contract No. ND/2024/05

Kwu Tung North New Development Area, Remaining Phase:
Improvement Works of Fanling Highway (Pak Shek Au Portion) and
Associated Works

ScopeThe works mainly include site clearance and formation (including land decontamination works); widening of Fanling Highway (Chau Tau to Pak Shek Au Portion); modification of Castle Peak Road (Chau Tau Portion); construction of Pak Shek Au Interchange; modification of Pak Shek Au Bridge across Fanling Highway; construction of footbridge across Fanling Highway (Pak Shek Au Portion); extension of existing subways no. NS161 and NS161A; construction of associated works including water mains, drainage, retention tanks, sewerage works, roadworks, cycle tracks, footpaths, junction improvement, box culverts, slope works, retaining walls, street furniture, landscaping works, electrical and mechanical works and other ancillary works; and implementation of environmental mitigation measures (including noise barriers and low-noise road surfacing) and environmental monitoring works for the works mentioned above.
Commencement Date2nd half of 2025 (tentative)
Completion DateMid 2030 (tentative)
Contract SumTo be confirmed
ContractorTo be confirmed
Contract No. ND/2024/06

Fanling North New Development Area, Remaining Phase: Fresh Water and Flushing Water Service Reservoirs and Associated Works

ScopeThe works mainly comprise construction of a fresh water service reservoir, a flushing water service reservoir and associated site formation, geotechnical, roadworks, power supply, drainage and landscaping works; laying of about 5.7-kilometre-long fresh water mains and about 5.7-kilometre-long flushing water mains; installation of pumps and associated electrical and mechanical works within Shek Wu Hui Water Reclamation Plant constructed by the Water Supplies Department; and implementation of environmental mitigation measures for the works mentioned above.
Commencement Date30 July 2024
Completion Date2nd half of 2027 (tentative)
Contract Sum$1.29 Billion
ContractorWo Hing – Tsun Yip Joint Venture
Contract No. ND/2024/07

Fanling North New Development Area, Remaining Phase: Site Formation and Infrastructure Works (East)

ScopeThe works mainly comprise site formation of lands and ground investigation within Fanling North New Development Area (FLN NDA); construction of at-grade roads connecting FLN NDA to Fanling Highway and associated junction/road improvements; construction of noise barriers and low noise road surfacing; and ancillary works including footbridges, footpaths, cycle tracks, lighting, traffic aids, sewage pumping stations, drainage, sewerage, water mains, landscaping works, slope works and electrical and mechanical works.
Commencement Date14 August 2024
Completion Date1st half of 2030 (tentative)
Contract Sum$3.5696 Billion
ContractorBuild King - Richwell Civil Joint Venture
Contract No. ND/2024/08

Fanling North New Development Area, Remaining Phase: Site Formation and Infrastructure Works (West)

ScopeThe works mainly include site formation of lands and ground investigation within Fanling North New Development Area (FLN NDA); construction of at-grade roads connecting FLN NDA to Fanling Highway; construction of Fanling Bypass Western Section; construction of noise barriers and low noise road surfacing; and ancillary works including vehicular bridge, footbridges, footpaths, cycle tracks, lighting, traffic aids, sewage pumping stations, drainage, sewerage, water mains, landscaping works, slope works and electrical and mechanical works.
Commencement Date2nd half of 2025 (tentative)
Completion DateMid 2030 (tentative)
Contract SumTo be confirmed
ContractorTo be confirmed
back to Top